PART 275—PERFORMANCE REPORTING SYSTEM Authority: 7 U.S.C. 2011-2036. Editorial Note: OMB control numbers relating to this part 275 are contained in § 271.8. Subpart A—Administration § 275.1 General scope and purpose. Under the Food and Nutrition Act of 2008, each State agency is responsible for the administration of SNAP in accordance with the Act, Regulations, and the State agency's plan of operation. To fulfill the requirements of the Act, each State agency shall have a system for monitoring and improving its administration of the program. The State agency is also responsible for reporting on its administration to FNS. These reports shall identify program deficiencies and the specific administrative action proposed to meet the program requirements established by the Secretary. If it is determined, however, that a State has failed without good cause to meet any of the program requirements established by the Secretary, or has failed to carry out the approved State plan of operation, the Department shall suspend and/or disallow from the State such funds as are determined to be appropriate in accordance with part 276 of this chapter. [Amdt. 160, 45 FR 15898, Mar. 11, 1980, as amended by Amdt. 266, 52 FR 3407, Feb. 4, 1987; Amdt. 328, 56 FR 60051, Nov. 27, 1991; 75 FR 33436, June 11, 2010] § 275.2 State agency responsibilities. (a) Establishment of the performance reporting system. (i) Data collection through management evaluation (ME) reviews and quality control (QC) reviews; (ii) Analysis and evaluation of data from all sources; (iii) Corrective action planning; (iv) Corrective action implementation and monitoring; and (v) Reporting to FNS on program performance. (2) The State agency must ensure corrective action is effected at the State and project area levels. (b) Staffing standards. (1) Taken any part in the decision that has been made in the case; (2) any discussion of the case with staff who participated in the decision; or (3) any personal knowledge of or acquaintance with persons in the case itself. To ensure no prior knowledge on the part of QC or ME reviewers, local project area staff shall not be used to conduct QC or ME reviews; exceptions to this requirement concerning local level staff may be granted with prior approval from FNS. However, local personnel shall not, under any circumstances, participate in ME reviews of their own project areas. (c) Use of third party contractors. (1) For expenses related to the hiring of a contractor for any quality control related work to qualify for SNAP administrative cost reimbursement under § 277.4(b), FNS requires the following: (i) The State must notify FNS in writing of its intent to hire a contractor at least 30 days prior to entering into the contract to do so. The notification must include a copy of the selected contractor's complete proposal, which must receive FNS approval before the State may proceed with the procuring the contract. (ii) Once the contract is procured, the State must submit to FNS a copy of the signed contract and documentation that outlines all tasks and deliverables to be performed or produced by the contractor. (iii) The State must submit to FNS a copy of all deliverables, including any training materials, provided by the contractor. (iv) The State must notify FNS of the date, time, and location of any training sessions led by the contractor at least 10 days in advance of the training. FNS shall be allowed to attend any such training session with or without providing prior notice to the State agency or the contractor. (v) If the State discusses individual sampled cases with the contractor, the State must document, within the case file, the contents of the discussion and any action taken by the State as a result of the discussion. If the discussion occurs orally, FNS shall be given notice 24 hours in advance of the discussion and shall be allowed to participate in the discussion. If the discussion occurs in writing, the State must ensure that FNS is copied on all written correspondence discussing individual sampled cases. (2) Copies of documentation and notices required in paragraph (c)(1) of this section must be provided to the appropriate FNS Regional SNAP Director. (3) In accordance with the non-procurement debarment procedures under 2 CFR part 417, or successor regulations, FNS shall debar any person that, in carrying out the quality control system, knowingly submits or causes to be submitted false information to FNS. (d) FNS Access to State Systems. [Amdt. 160, 45 FR 15898, Mar. 11, 1980, as amended by Amdt. 266, 52 FR 3407, Feb. 4, 1987; 86 FR 44586, Aug. 13, 2021; 88 FR 23559, Apr. 18, 2023] § 275.3 Federal monitoring. The Food and Nutrition Service shall conduct the review described in this section to determine whether a State agency is operating SNAP and the Performance Reporting System in accordance with program requirements. The Federal reviewer may consolidate the scheduling and conduction of these reviews to reduce the frequency of entry into the State agency. FNS regional offices will conduct additional reviews to examine State agency and project area operations, as considered necessary to determine compliance with program requirements. FNS shall notify the State agency of any deficiencies detected in program or system operations. Any deficiencies detected in program or system operations which do not necessitate long range analytical and evaluative measures for corrective action development shall be immediately corrected by the State agency. Within 60 days of receipt of the findings of each review established below, State agencies shall develop corrective action addressing all other deficiencies detected in either program or system operations and shall ensure that the State agency's own corrective action plan is amended and that FNS is provided this information at the time of the next formal semiannual update to the State agency's Corrective Action Plan, as required in § 275.17. (a) Reviews of State Agency's Administration/Operation of SNAP. (b) Reviews of State Agency's Management Evaluation System. (c) Reviews of State Agency's Quality Control System. (d) Validation of State Agency error rates. (1) Payment error rate. (i) FNS will select a subsample of a State agency's completed active cases, as follows: (A) For State agencies that determine their active sample sizes in accordance with § 275.11(b)(1)(ii), the Federal review sample for completed active cases is determined as follows: Average monthly reviewable caseload (N) Federal subsample target (n′) 31,489 and over n′ = 400 10,001 to 31,488 n′ = .011634 N + 33.66 10,000 and under n′ = 150 (B) For State agencies that determine their active sample sizes in accordance with § 275.11(b)(1)(iii), the Federal review sample for completed active cases is determined as follows: Average monthly reviewable caseload (N) Federal subsample target (n′) 60,000 and over n′ = 400 10,001 to 59,999 n′ = .005 N + 100 10,000 and under n′ = 150 (C) In the above formula, n' is the minimum number of Federal review sample cases which must be selected when conducting a validation review, except that FNS may select a lower number of sample cases if: ( 1 ( 2 (D) The reduction in the number of Federal cases selected will be equal to the number of cases that would have been selected had the Federal sampling interval been applied to the State agency's shortfall in its required sample size. This number may not be exact due to random starts and rounding. (E) In the above formula, N is the State agency's minimum active case sample size as determined in accordance with § 275.11(b)(1). (ii) FNS Regional Offices will conduct case record reviews to the extent necessary to determine the accuracy of the State agency's findings using the household's certification records and the State agency's QC records as the basis of determination. The FNS Regional Office may choose to verify any aspects of a State agency's QC findings through telephone interviews with participants or collateral contacts. In addition, the FNS Regional Office may choose to conduct field investigations to the extent necessary. (iii) Upon the request of a State agency, the appropriate FNS Regional Office will assist the State agency in completing active cases reported as not completed due to household refusal to cooperate. (iv) FNS will also review the State agency's sampling procedures, estimation procedures, and the State agency's system for data management to ensure compliance with §§ 275.11 and 275.12. (v) FNS validation reviews of the State agency's active sample cases will be conducted on an ongoing basis as the State agency reports the findings for individual cases and supplies the necessary case records. FNS will begin the remainder of each State agency's validation review as soon as possible after the State agency has supplied the necessary information regarding its sample and review activity. (2) Underissuance error rate. (3) Negative case error rate. (i) FNS will select a subsample of a State agency's completed negative cases, as follows: Average monthly reviewable negative caseload (N) Federal subsample target (n′) 5,000 and over n′ = 160 501 to 4,999 n′ = .0188 N + 65.7 Under 500 n′ = 75 (A) In the above formula, n' is the minimum number of Federal review sample cases which must be selected when conducting a validation review, except that FNS may select a lower number of sample cases if: ( 1 ( 2 (B) The reduction in the number of Federal cases selected will be equal to the number of cases that would have been selected had the Federal sampling interval been applied to the State agency's shortfall in its required sample size. This number may not be exact due to random starts and rounding. (C) In the above formula, N is the State agency's minimum negative case sample size as determined in accordance with § 275.11(b)(2). (ii) FNS Regional Offices will conduct case record reviews to the extent necessary to determine whether the household case record contained sufficient documentation to justify the State agency's QC findings of the correctness of the State agency's decision to deny, suspend or terminate a household's participation. (iii) FNS will also review each State agency's negative case sampling and review procedures against the provisions of §§ 275.11 and 275.13. (iv) FNS will begin each State agency's negative sample case validation review as soon as possible after the State agency has supplied the necessary information, including case records and information regarding its sample and review activity. (4) Arbitration. (A) The State agency may only request arbitration when the State agency's and FNS regional office's findings or disposition of an individual QC case disagree. (B) The arbitration review shall be limited to the point(s) within the Federal findings or disposition that the State agency disputes. However, if the arbitrator in the course of the review discovers a mathematical error in the computational sheet, the arbitration shall correct the error while calculating the allotment. (ii) The FNS Arbitrator(s) shall be an individual or individuals who are not directly involved in the validation effort. (iii) With the exception of the restrictions contained in paragraph (c)(4)(iii), for an arbitration request to be considered, it must be received by the appropriate FNS regional office within 20 calendar days of the date of receipt by the State agency of the regional office case findings. In the event the last day of this time period falls on a Saturday, Sunday, or Federal or State holiday, the period shall run to the end of the next work day. The State agency shall be restricted in its eligibility to request arbitration of an individual case if that case was not disposed of and the findings reported in accordance with the timeframes specified in § 275.21(b)(2). For each day late that a case was disposed of and the findings reported, the State agency shall have one less day to request arbitration of the case. (iv) When the State agency requests arbitration, it shall submit all required documentation to the appropriate FNS regional office addressed to the attention of the FNS Arbitrator. The FNS regional office QC staff may submit an explanation of the Federal position regarding a case to the FNS Arbitrator. (A) A complete request is one that contains all information necessary for the arbitrator to render an accurate, timely decision. (B) If the State agency's request is not complete the arbitrator shall make a decision based solely on the available documents. (v) The FNS Arbitrator shall have 20 calendar days from the date of receipt of a State agency's request for arbitration to review the case and make a decision. (5) Household cooperation. (e) Assessment of Corrective Action. (2) In addition, FNS will conduct on-site reviews of selected corrective actions as frequently as considered necessary to ensure that State agencies are implementing proposed corrective actions within the timeframes specified in the State agency and/or Project Area/Management Unit corrective action plans and to determine the effectiveness of the corrective action. The on-site reviews will provide State agencies and FNS with a mechanism for early detection of problems in the corrective action process to minimize losses to the program, participants, or potential participants. [Amdt. 160, 45 FR 15898, Mar. 11, 1980, as amended by Amdt. 237, 47 FR 57669, Dec. 28, 1982; Amdt. 260, 49 FR 6303, Feb. 17, 1984; Amdt. 266, 52 FR 3407, Feb. 4, 1987; 53 FR 1604, Jan. 21, 1988; 54 FR 23951, June 5, 1989; Amdt. 309, 55 FR 1672, Jan. 18, 1990; Amdt. 328, 56 FR 60051, Nov. 27, 1991; Amdt. 366, 62 FR 29658, June 2, 1997; Amdt. 373, 64 FR 38294, July 16, 1999; 68 FR 59523, Oct. 16, 2003; 75 FR 33436, June 11, 2010; 86 FR 44586, Aug. 13, 2021] § 275.4 Record retention. (a) The State agency shall maintain Performance Reporting System records to permit ready access to, and use of, these records. Performance Reporting System records include information used in data analysis and evaluation, corrective action plans, corrective action monitoring records in addition to ME review records and QC review records as explained in paragraphs (b) and (c) of this section. To be readily accessible, system records shall be retained and filed in an orderly fashion. Precautions should be taken to ensure that these records are retained without loss or destruction for the 3-year period required by these regulations. Information obtained on individual households for Performance Reporting System purposes shall be safeguarded in accordance with FNS policies on disclosure of information for SNAP. (b) ME review records consist of thorough documentation of review findings, sources from which information was obtained, procedures used to review SNAP requirements including sampling techniques and lists, and ME review plans. The State agency must submit documented evidence of review findings to the FNS Regional Office upon request for purposes of evaluating State corrective action plans. (c) QC review records consist of Forms FNS-380, Worksheet for Supplemental Nutrition Assistance Program, FNS-380-1, Quality Control Review Schedule, FNS-245, Negative Quality Control Review Schedule; other materials supporting the review decision, including all correspondence with the household and all case notes, digital or otherwise, taken or used by the eligibility worker that are applicable to the review period; sample lists; sampling frames; tabulation sheets; and reports of the results of all quality control reviews during each review period. [Amdt. 160, 45 FR 15898, Mar. 11, 1980, as amended by Amdt. 260, 49 FR 6304, Feb. 17, 1984; Amdt. 262, 49 FR 50597, Dec. 31, 1984; 75 FR 33436, June 11, 2010; 86 FR 44586, Aug. 13, 2021] Subpart B—Management Evaluation (ME) Reviews § 275.5 Scope and purpose. (a) Objectives. (1) Provide a systematic method of monitoring and assessing program operations in the project areas; (2) Provide a basis for project areas to improve and strengthen program operations by identifying and correcting deficiencies; and (3) Provide a continuing flow of information between the project areas, the States, and FNS, necessary to develop the solutions to problems in program policy and procedures. (b) Frequency of review. (2) A request for an alternate review schedule shall be submitted for approval in writing with a proposed schedule and justification. In any alternate schedule, each project area must be reviewed at least once every three years. Approval of an alternate schedule is dependent upon a State agency's justification that the project areas that will be reviewed less frequently than required in paragraph (b)(1) of this section are performing adequately and that previous reviews indicate few problems or that known problems have been corrected. FNS retains the authority for approving any alternate schedule and may approve a schedule in whole or in part. Until FNS approval of an alternate schedule is obtained, the State agency shall conduct reviews in accordance with paragraph (b)(1) of this section. (3) FNS may require the State agency to conduct additional on-site reviews when a serious problem is detected in a project area which could result in a substantial dollar or service loss. (4) State agencies shall also establish a system for monitoring those project areas' operations which experience a significant influx of migratory workers during such migrations. This requirement may be satisfied by either scheduling ME reviews to coincide with such migrations or by conducting special reviews. As part of the review the State agency shall contact local migrant councils, advocate groups, or other organizations in the project area to ensure that migrants are receiving the required services. [Amdt. 160, 45 FR 15900, Mar. 11, 1980, as amended by Amdt. 262, 49 FR 50597, Dec. 31, 1984; Amdt. 266, 52 FR 3408, Feb. 4, 1987] § 275.6 Management units. (a) Establishment of management units. (b) FNS approval of management units. (1) The following minimum criteria must be met prior to requesting FNS approval: (i) The proposed management unit must correspond with existing State-established welfare districts, regions, or other administrative structures; and (ii) The unit must have supervisory control over SNAP operations within that geographic area and have authority for implementation of corrective action. (2) In submitting the request for FNS approval, the State agency shall include the following information regarding the proposed management unit: (i) That the proposed management unit meets the minimum criteria described in paragraphs (b)(1) (i) and (ii) of this section; (ii) Geographic coverage, including the names of the counties/project areas within the unit and the identification (district or region number) and location (city) of the office which has supervisory control over the management unit; (iii) SNAP participation, including the number of persons and number of households; (iv) The number of certification offices; (v) The number of issuance units; (vi) The dollar value of allotments issued as reflected in the most recent available data; and (vii) Any other relevant information. [Amdt. 160, 45 FR 15900, Mar. 11, 1980; 45 FR 23637, Apr. 8, 1980, as amended by Amdt. 266, 52 FR 3408, Feb. 4, 1987] § 275.7 Selection of sub-units for review. (a) Definition of sub-units. (b) Selection of Sub-units for Review. [Amdt. 160, 45 FR 15900, Mar. 11, 1980; 45 FR 23638, Apr. 8, 1980; 45 FR 46784, July 11, 1980, as amended by Amdt. 266, 52 FR 3408, Feb. 4, 1987; 81 FR 2741, Jan. 19, 2016] § 275.8 Review coverage. (a) During each review period, State agencies shall review the national target areas of program operation specified by FNS. FNS will notify State agencies of the minimum program areas to be reviewed at least 90 days before the beginning of each annual review period, which is the Federal fiscal year. FNS may add additional areas during the review period if deemed necessary. The FNS headquarters office will add national target areas during the review period only for deficiencies of national scope. State agencies have 60 days in which to establish a plan schedule for such reviews. (b) State agencies shall be responsible for reviewing each national target area or other program requirement based upon the provisions of the regulations governing SNAP and the FNS-approved Plan of Operation. If FNS approves a State agency's request for a waiver from a program requirement, any different policy approved by FNS would also be reviewed. When, in the course of a review, a project area is found to be out of compliance with a given program requirement, the State agency shall identify the specifics of the problem including: the extent of the deficiency, the cause of the deficiency, and, as applicable, the specific procedural requirements the project area is misapplying. [Amdt. 266, 52 FR 3408, Feb. 4, 1987, as amended by Amdt. 356, 59 FR 29713, June 9, 1994] § 275.9 Review process. (a) Review procedures. (b) ME review plan. (i) Identification of the project area to be reviewed, program areas to be reviewed, the dates the review will be conducted, and the period of time that the review will cover; (ii) Information secured from the project area regarding its caseload and organization; (iii) Identification of the sub-units selected for review and the techniques used to select them; (iv) At State agency option it may also indicate whether the State agency is using the ME review process to perform non-discrimination reviews; and (v) A description of the review method(s) the State agency plans to use for each program area being reviewed. (2) ME review plans shall be maintained in an orderly fashion and be made available to FNS upon request. (c) Review methods. (2) State agencies shall ensure that the method used to review a program requirement does not bias the review findings. Bias can be introduced through leading questions, incomplete reviews, incorrect sampling techniques, etc. (d) Review worksheet. (i) The sub-unit being reviewed; (ii) Each program requirement reviewed in the sub-unit; (iii) The method used to review each program requirement; (iv) A description of any deficiency detected; (v) The cause(s) of any deficiency detected, if known; (vi) The number of casefiles and/or program records selected and examined within the sub-unit, identification of those selected (record case number, household name, etc.), the proportion which were not subject to review, as well as the method used to select the sample; (vii) Where applicable, the numerical extent of any deficiency detected through examination of program records; and (viii) Any pertinent comments concerning the sub-unit's operation. (2) State agencies shall promptly forward review findings to the appropriate State office for analysis, evaluation, and corrective action planning. Review worksheets shall be retained in an orderly fashion and made available to FNS upon request. [Amdt. 160, 45 FR 15900, Mar. 11, 1980; 45 FR 25375, Apr. 15, 1980, as amended by Amdt. 266, 52 FR 3409, Feb. 4, 1987; Amdt. 356, 59 FR 29713, June 9, 1994; 81 FR 2741, Jan. 19, 2016] Subpart C—Quality Control (QC) Reviews § 275.10 Scope and purpose. (a) As part of the Performance Reporting System, each State agency is responsible for conducting quality control reviews. For SNAP quality control reviews, a sample of households shall be selected from two different categories: Households which are participating in SNAP (called active cases) and households for which participation was denied, suspended or terminated (called negative cases). Reviews shall be conducted on active cases to determine if households are eligible and receiving the correct allotment of SNAP benefits. The determination of whether the household received the correct allotment will be made by comparing the eligibility data gathered during the review against the amount authorized on the master issuance file. Reviews of negative cases shall be conducted to determine whether the State agency's decision to deny, suspend or terminate the household, as of the review date, was correct. Quality control reviews measure the validity of SNAP cases at a given time (the review date) by reviewing against SNAP standards established in the Food and Nutrition Act of 2008 and the Regulations, taking into account any FNS authorized waivers to deviate from specific regulatory provisions. FNS and the State agency shall analyze findings of the reviews to determine the incidence and dollar amounts of errors, which will determine the State agency's liability for payment errors in accordance with the Food and Nutrition Act of 2008, as amended, and to plan corrective action to reduce excessive levels of errors for any State agency. (b) The objectives of quality control reviews are to provide: (1) A systematic method of measuring the validity of the SNAP caseload; (2) A basis for determining error rates; (3) A timely continuous flow of information on which to base corrective action at all levels of administration; and (4) A basis for establishing State agency liability for errors that exceed the National performance measure. (c) The review process is the activity necessary to complete reviews and document findings of all cases selected in the sample for quality control reviews. The review process shall consist of: (1) Case assignment and completion monitoring; (2) Case reviews; (3) Supervisory review of completed worksheets and schedules; and (4) Transmission of completed worksheets and schedules to the State agency for centralized data compilation and analysis. [Amdt. 149, 44 FR 45893, Aug. 3, 1979, as amended by Amdt. 260, 49 FR 6304, Feb. 17, 1984; 54 FR 7016, Feb. 15, 1989; Amdt. 328, 56 FR 60051, Nov. 27, 1991; Amdt. 373, 64 FR 38294, July 16, 1999; 75 FR 33436, June 11, 2010] § 275.11 Sampling. (a) Sampling plan. (1) Content. (2) Criteria. (i) Conform to principles of probability sampling; (ii) Specify and explain the basis for the sample sizes chosen by the State agency; (iii) If the State agency has chosen an active sample size as specified in paragraph (b)(1)(iii) of this section, include a statement that, whether or not the sample size is increased to reflect an increase in participation as discussed in paragraph (b)(3) of this section, the State agency will not use the size of the sample chosen as a basis for challenging the resulting error rates. (iv) If the State agency has chosen a negative sample size as specified in paragraph (b)(2)(ii) of this section, include a statement that, whether or not the sample size is increased to reflect an increase in negative actions as discussed in paragraph (b)(3) of this section, the State agency will not use the size of the sample chosen as a basis for challenging the resulting error rates. (3) Design. (4) FNS review and approval. (b) Sample size. (1) Active cases. (ii) Unless a State agency chooses to select and review a number of active cases determined by the formulas provided in paragraph (b)(1)(iii) of this section and has included in its sampling plan the reliability certification required by paragraph (a)(2)(iii) of this section, the minimum number of active cases to be selected and reviewed by a State agency during each annual review period shall be determined as follows: Average monthly reviewable caseload (N) Minimum annual sample size (n) 60,000 and over n = 2400 10,000 to 59,999 n = 300 + [0.042(N−10,000)] Under 10,000 n = 300 (iii) A State agency which includes in its sampling plan the statement required by paragraph (a)(2)(iii) of this section may determine the minimum number of active cases to be selected and reviewed during each annual review period as follows: Average monthly reviewable caseload (N) Minimum annual sample size (n) 60,000 and over n = 1020 12,942 to 59,999 n = 300 + [0.0153(N−12,941)] Under 12,942 n = 300 (iv) In the formulas in paragraphs (b)(1)(ii) and (iii) of this section n is the required active case sample size. This is the minimum number of active cases subject to review which must be selected each review period. Also in the formulas, N is the average monthly participating caseload subject to quality control review (i.e., households which are included in the active universe defined in paragraph (e)(1) of this section) during the annual review period. (2) Negative cases. Average monthly reviewable negative caseload (N) Minimum annual sample size (n) 5,000 and over n = 800 500 to 4,999 n = 150 + [0.144(N−500)] Under 500 n = 150 (ii) A State agency which includes in its sampling plan the statement required by paragraph (a)(2)(iv) of this section may determine the minimum number of negative cases to be selected and reviewed during each annual review period as follows: Average monthly reviewable negative caseload (N) Minimum annual sample size (n) 5,000 and over n = 680 684 to 4,999 n = 150 + [ 0.1224(N−683)] Under 684 n = 150 (iii) In the formulas in this paragraph (b)(2), n is the required negative sample size. This is the minimum number of negative cases subject to review which must be selected each review period. (iv) In the formulas in this paragraph (b)(2), N is the average monthly number of negative cases which are subject to quality control review (i.e., households which are part of the negative universe defined in paragraph (e)(2) of this section) during the annual review period. (3) Unanticipated changes. (4) Alternative designs. (i) Demonstrate that the alternative design provides payment error rate estimates with equal-or-better predicted precision than would be obtained had the State agency reviewed simple random samples of the sizes specified in paragraphs (b)(1) and (b)(2) of this section. (ii) Describe all weighting, and estimation procedures if the sample design is non-self-weighted, or uses a sampling technique other than systematic sampling. (iii) Demonstrate that self-weighting is actually achieved in sample designs claimed to be self-weighting. (c) Sample selection. (1) Substitutions. (2) Corrections. (d) Required sample size. (e) Sample frame. (1) Active cases. (2) Negative cases. (i) All actions to deny an application in the sample month except those excluded from the universe in paragraph (f)(2) of this section. If a household is subject to more than one denial action in a single sample month, each action shall be listed separately in the sample frame; and (ii) All actions to suspend or terminate a household in the sample month except those excluded from the universe in paragraph (f)(2) of this section. Each action to suspend or terminate a household in the sample month shall be listed separately in the sample frame. (3) Unwanted cases. (f) Sample universe. (1) Active cases. (i) A household in which all the members had died or had moved out of the State before the review could be undertaken or completed; (ii) A household receiving SNAP benefits under a disaster certification authorized by FNS; (iii) A household which is under investigation for intentional Program violation, including a household with a pending administrative disqualification hearing; (iv) A household appealing an adverse action when the review date falls within the time period covered by continued participation pending the hearing; or (v) A household receiving restored benefits in accordance with § 273.17 but not participating based upon an approved application. Other households excluded from the active case universe during the review process are identified in § 275.12(g). (2) Negative cases. (i) A household which had its case closed due to expiration of the certification period; (ii) A household denied SNAP benefits under a disaster certification authorized by FNS; (iii) A household which withdrew an application prior to the agency's determination; (iv) A household which is under active investigation for Intentional Program Violation; (v) A household which has been sent a notice of pending status but which was not actually denied participation; (vi) A household which was terminated for failure to file a complete monthly report by the extended filing date, but reinstated when it subsequently filed the complete report before the end of the issuance month; (vii) Other households excluded from the negative case universe during the review process as identified in § 275.13(e). (g) Demonstration projects. [Amdt. 260, 49 FR 6304, Feb. 17, 1984; 49 FR 14495, Apr. 12, 1984, as amended by Amdt. 262, 49 FR 50598, Dec. 31, 1984; Amdt. 266, 52 FR 3409, Feb. 4, 1987; Amdt. 328, 56 FR 60051, Nov. 27, 1991; Amdt. 366, 62 FR 29658, June 2, 1997; Amdt. 373, 64 FR 38295, July 16, 1999; 68 FR 59523, Oct. 16, 2003; 75 FR 33436, June 11, 2010; 86 FR 44586, Aug. 13, 2021] § 275.12 Review of active cases. (a) General. (b) Household case record review. (c) Field investigation. (1) Personal interviews. (i) Explore with the head of the household, spouse, authorized representative, or any other responsible household member, household circumstances as they affect each factor of eligibility and basis of issuance; (ii) Establish the composition of the household; (iii) Review the documentary evidence in the household's possession and secure information about collateral sources of verification; and (iv) Elicit from the participant names of collateral contacts. The reviewer shall use, but not be limited to, these designated collateral contacts. If required by the State, the reviewer shall obtain consent from the head of the household to secure collateral information. If the participant refuses to sign the release of information form, the reviewer shall explain fully the consequences of this refusal to cooperate (as contained in paragraph (g)(1)(ii) of this section), and continue the review to the fullest extent possible. (2) Collateral contacts. (d) Variance identification. (1) Variances included in error analysis. (2) Variances excluded from error analysis. (i) Any variance resulting from the nonverified portion of a household's gross nonexempt income where there is conclusive documentation (a listing of what attempts were made to verify and why they were unsuccessful) that such income could not be verified at the time of certification because the source of income would not cooperate in providing verification and no other sources of verification were available. If there is no conclusive documentation as explained above, then the reviewer shall not exclude any resulting variance from the error determination. This follows certification policy outlined in § 273.2(f)(1)(i) of this chapter. (ii) Any variance in cases certified under expedited certification procedures resulting from postponed verification of an element of eligibility as allowed under § 273.2(i)(4)(i) of this chapter. Verification of gross income, deductions, resources, household composition, alien status, or tax dependency may be postponed for cases eligible for expedited certification. However, if a case certified under expedited procedures contains a variance as a result of a residency deficiency, a mistake in the basis of issuance computation, a mistake in participant identification, or incorrect expedited income accounting, the variance shall be included in the error determination. This exclusion shall only apply to those cases which are selected for QC review in the first month of participation under expedited certification. (iii) Any variance subsequent to certification in an element of eligibility or basis of issuance which was not reported and was not required to have been reported as of the review date. The elements participants are required to report and the time requirements for reporting are specified in §§ 273.12(a) and 273.21(h) and (i) of this chapter, as appropriate. If, however, a change in any element is reported, and the State agency fails to act in accordance with §§ 273.12(c) and 273.21(j) of this chapter, as appropriate, any resulting variance shall be included in the error determination. (iv) Any variance in deductible expenses which was not provided for in determining a household's benefit level in accordance with § 273.2(f)(3)(i)(B) of this chapter. This provision allows households to have their benefit level determined without providing for a claimed expense when the expense is questionable and obtaining verification may delay certification. If such a household subsequently provides the needed verification for the claimed expense and the State agency does not redetermine the household's benefits in accordance with § 273.12(c) of this chapter, any resulting variance shall be included in the error determination. (v) Any variance resulting from use by the State agency of information concerning households or individuals from an appropriate Federal source, provided that such information is correctly processed by the State agency. An appropriate Federal source is one which verifies: Income that it provides directly to the household; deductible expenses for which it directly bills the household; or other household circumstances which it is responsible for defining or establishing. To meet the provisions for correct processing, the eligibility worker must have appropriately acted on timely information. In order to be timely, information must be the most current that was available to the State agency at the time of the eligibility worker's action. (vi) Two variances relating to the Immigration and Naturalization Service's (INS) Systematic Alien Verification for Entitlements (SAVE) Program. (A) A variance based on a verification of alien documentation by INS. The reviewer shall exclude such variance only if the State agency properly used SAVE and the State agency provides the reviewer with: ( 1 ( 2 ( 3 (B) A variance based on the State agency's wait for the response of INS to the State agency's request for official verification of the alien's documentation. The reviewer shall exclude such variance only if the State agency properly used SAVE and the State agency provides the reviewer with either: ( 1 ( 2 (vii) Subject to the limitations provided in paragraphs (d)(2)(vii)(A) through (d)(2)(vii)(F) of this section, any variance resulting from application of a new Program regulation or implementing memorandum of a mandatory or optional change in Federal law that occurs during the first 120 days from the required implementation date. The variance exclusion shall apply to any action taken on a case directly related to implementation of a covered provision during the 120-day exclusionary period until the case is required to be recertified or acted upon for some other reason. (A) When a regulation allows a State agency an option to implement prior to the required implementation date, the date on which the State agency chooses to implement may, at the option of the State, be considered to be the required implementation date for purposes of this provision. The exclusion period would be adjusted to begin with this date and end on the 120th day that follows. States choosing to implement prior to the required implementation date must notify the appropriate FNS Regional Office, in writing, prior to implementation that they wish the 120 day variance exclusion to commence with actual implementation. Absent such notification, the exclusionary period will commence with the required implementation date. (B) A State agency shall not exclude variances which occur prior to the States implementation. (C) A State agency which did not implement until after the exclusion period shall not exclude variances under this provision. (D) Regardless of when the State agency actually implemented the regulation, the variance exclusion period shall end on the 120th day following the required implementation date, including the required implementation date defined in paragraph (d)(2)(vii)(A) of this section. (E) For purposes of this provision, implementation occurs on the effective date of State agency's written statewide notification to its eligibility workers. (F) This variance exclusion applies to changes occasioned by final regulations or interim regulations. In the case of a final regulation issued following an interim regulation, the exclusion applies only to significant changes made to the earlier interim regulation. A significant change is one which the final regulation requires the State agency to implement on or after publication of a final rule. (viii) Any variance resulting from incorrect written policy that a State agency acts on that is provided by a Departmental employee authorized to issue SNAP policy and that the State agency correctly applies. For purposes of this provision, written Federal policy is that which is issued in regulations, notices, handbooks, category three and four Policy Memoranda under the Policy Interpretation Response System, and regional policy memoranda issued pursuant to these. Written Federal policy is also a letter from the Food and Nutrition Service to a State agency which contains comments on the State agency's SNAP manual or instructions. (ix) Any variance in a child support deduction which was the result of an unreported change subsequent to the most recent certification action shall be excluded from the error determination. (3) Other findings. (e) Error analysis. (f) Reporting of review findings. (1) Eligibility errors. (2) Basis of issuance of errors. (g) Disposition of case reviews. (1) Cases reported as not complete. (i) If the reviewer is unable to locate the participant either at the address indicated in the case record or in the issuance record and the State agency is not otherwise aware of the participant's current address, the reviewer shall attempt to locate the household by contacting at least two sources which the State agency determines are most likely to be able to inform the reviewer of the household's current address. Such sources include but are not limited to: (A) The local office of the U.S. Postal Service; (B) The State Motor Vehicle Department; (C) The owner or property manager of the residence at the address in the case record; and (D) Any other appropriate sources based on information contained in the case record, such as public utility companies, telephone company, employers, or relatives. Once the reviewer has attempted to locate the household and has documented the response of each source contacted, if the household still cannot be located and the State agency has documented evidence that the household did actually exist, the State agency shall report the active case as not subject to review. In these situations documented evidence shall be considered adequate if it either documents two different elements of eligibility or basis of issuance, such as a copy of a birth certificate for age and pay status for income; or documents the statement of a collateral contact indicating that the household did exist. FNS Regional Offices will monitor the results of the contacts which State agencies make in attempting to locate households. (ii) If a household refuses to cooperate with the quality control reviewer and the State agency has taken other administrative steps to obtain that cooperation without obtaining it, the household shall be notified of the penalities for refusing to cooperate with respect to termination and reapplication, and of the possibility that its case will be referred for investigation for willful misrepresentation. If a household refuses to cooperate after such notice, the reviewer must- attempt to complete the case and shall report the household's refusal to the State agency for termination of its participation without regard for the outcome of that attempt. For a determination of refusal to be made, the household must be able to cooperate, but clearly demonstrate that it will not take actions that it can take and that are required to complete the quality control review process. In certain circumstances, the household may demonstrate that it is unwilling to cooperate by not taking actions after having been given every reasonable opportunity to do so, even though the household or its members do not state that the household refuses to cooperate. Instances where the household's unwillingness to cooperate in completing a quality control review has the effect of a refusal to cooperate shall include the following: (A) The household does not respond to a letter from the reviewer sent Certified Mail-Return Receipt Requested within 30 days of the date of receipt; (B) The household does not attend an agreed upon interview with the reviewer and then does not contact the reviewer within 10 days of the date of the scheduled interview to reschedule the interview; or (C) The household does not return a signed release of information statement to the reviewer within 10 days of either agreeing to do so or receiving a request from the reviewer sent Certified Mail-Return Receipt Requested. However, in these and other situations, if there is any question as to whether the household has merely failed to cooperate, as opposed to refused to cooperate, the household shall not be reported to the State agency for termination. (2) Cases not subject to review. (i) Death of all members of a household if they died before the review could be undertaken or completed; (ii) The household moved out of State before the review could be undertaken or completed; (iii) The household, at the time of the review, is under active investigation for intentional SNAP violation, including a household with a pending administrative disqualification hearing; (iv) A household receiving restored benefits in accordance with § 273.17 of this chapter but not participating based upon an approved application for the sample month; (v) A household dropped as a result of correction for oversampling; (vi) A household participating under disaster certification authorized by FNS for a natural disaster; (vii) A case incorrectly listed in the active frame; (viii) A household appealing an adverse action when the review date falls within the time period covered by continued participation pending the hearing; (ix) A household that did not receive benefits for the sample month; or (x) A household that still cannot be located after the reviewer has attempted to locate it in accordance with paragraph (g)(1)(i) of this section. (h) Demonstration projects. [Amdt. 260, 49 FR 6306, Feb. 17, 1984; 49 FR 14495, Apr. 12, 1984] Editorial Note: For Federal Register www.govinfo.gov. § 275.13 Review of negative cases. (a) General. (b) Household case record review. (c) Error analysis. (2) The reviewer shall exclude a variance when the State agency erroneously denied, suspended or terminated a household's participation based on an erroneous verification of alien documentation by the Immigration and Nationalization Services (INS) Systematic Alien Verification for Entitlements (SAVE) Program. The reviewer shall exclude the variance only if the State agency properly used SAVE, and the State agency provides the reviewer with: (i) The alien's name; (ii) The alien's status; and (iii) Either the Alien Status Verification Index (ASVI) Query Verification Number or the INS Form G-845, as annotated by INS. (d) Reporting of review findings. (e) Disposition of case review. (1) Cases reported as not complete. (2) Cases not subject to review. (i) A household which was dropped as a result of a correction for oversampling; (ii) A household which was listed incorrectly in the negative frame. (f) Demonstration projects. [Amdt. 260, 49 FR 6309, Feb. 17, 1984, as amended at 53 FR 39443, Oct. 7, 1988; Amdt. 373, 64 FR 38296, July 16, 1999; 75 FR 33437, June 11, 2010; 86 FR 44587, Aug. 13, 2021] § 275.14 Review processing. (a) General. (b) Handbooks. (c) Worksheets. (d) Schedules. [Amdt. 260, 49 FR 6310, Feb. 17, 1984, as amended by Amdt. 262, 49 FR 50598, Dec. 31, 1984; 75 FR 33438, June 11, 2010] Subpart D—Data Analysis and Evaluation § 275.15 Data management. (a) Analysis. (b) Evaluation. (c) Each State agency must analyze and evaluate at the State and project area levels all management information sources available to: (1) Identify all deficiencies in program operations and systems; (2) Identify causal factors and their relationships; (3) Identify magnitude of each deficiency, where appropriate (This is the frequency of each deficiency occurring based on the number of program records reviewed and where applicable, the amount of loss either to the program or participants or potential participants in terms of dollars. The State agency shall include an estimate of the number of participants or potential participants affected by the existence of the deficiency, if applicable); (4) Determine the geographic extent of each deficiency (e.g., Statewide/individual project area or management unit); and, (5) Provide a basis for management decisions on planning, implementing, and evaluating corrective action. (d) In the evaluation of data, situations may arise where the State agency identifies the existence of a deficiency, but after reviewing all available management information sources sufficient information is not available to make a determination of the actual causal factor(s), magnitude, or geographic extent necessary for the development of appropriate corrective action. In these situations, the State agency shall be responsible for gathering additional data necessary to make these determinations. This action may include, but is not limited to, conducting additional full or partial ME reviews in one or more project areas/management units or discussions with appropriate officials. (e) Deficiencies identified from all management information sources must be analyzed and evaluated together to determine their causes, magnitude, and geographic extent. Causes indicated and deficiencies identified must be examined to determine if they are attributable to a single cause and can be effectively eliminated by a single action. Deficiencies and causes identified must also be compared to the results of past corrective action efforts to determine if the new problems arise from the causal factors which contributed to the occurrence of previously identified deficiencies. (f) Data analysis and evaluation must be an ongoing process to facilitate the development of effective and prompt corrective action. The process shall also identify when deficiencies have been eliminated through corrective action efforts, and shall provide for the reevaluation of deficiencies and causes when it is determined that corrective action has not been effective. (g) Identification of High Error Project Areas/Counties/Local Offices. [Amdt. 160, 45 FR 15909, Mar. 11, 1980, as amended by Amdt. 266, 52 FR 3409, Feb. 4, 1987; Amdt. 320, 55 FR 6240, Feb. 22, 1990] Subpart E—Corrective Action § 275.16 Corrective action planning. (a) Corrective action planning is the process by which State agencies shall determine appropriate actions to reduce substantially or eliminate deficiencies in program operations and provide responsive service to eligible households. (b) The State agency and project area(s)/management unit(s), as appropriate, shall implement corrective action on all identified deficiencies. Deficiencies requiring action by the State agency or the combined efforts of the State agency and the project area(s)/management unit(s) in the planning, development, and implementation of corrective action are those which: (1) Result from a payment error rate of 6 percent or greater (actions to correct errors in individual cases, however, shall not be submitted as part of the State agency's corrective action plan); (2) Are the causes of other errors/deficiencies detected through quality control, including error rates of 1 percent or more in negative cases (actions to correct errors in individual cases, however, shall not be submitted as part of the State agency's corrective action plan); (3) Are identified by FNS reviews, GAO audits, contract audits, reports to FNS regarding the implementation of major changes (as discussed in § 272.15) or USDA audits or investigations at the State agency or project area level (except deficiencies in isolated cases as indicated by FNS); and, (4) Result from 5 percent or more of the State agency's QC sample being coded “not complete” as defined in § 275.12(g)(1) of this part. This standard shall apply separately to both active and negative samples. (5) Result in underissuances, improper denials, improper suspensions, improper termination, or improper systemic suspension of benefits to eligible households where such errors are caused by State agency rules, practices, or procedures. (c) The State agency shall ensure that appropriate corrective action is taken on all deficiencies including each case found to be in error by quality control reviews and those deficiencies requiring corrective action only at the project area level. Moreover, when a substantial number of deficiencies are identified which require State agency level and/or project area/management unit corrective action, the State agency and/or project area/management unit shall establish an order of priority to ensure that the most serious deficiencies are addressed immediately and corrected as soon as possible. Primary factors to be considered when determining the most serious deficiencies are: (1) Magnitude of the deficiency as defined in § 275.15(c)(3) of this part; (2) Geographic extent of the deficiency (e.g., Statewide/project area or management unit); (3) Anticipated results of corrective actions; and (4) High probability of errors occurring as identified through all management evaluation sources. (d) In planning corrective action, the State agency shall coordinate actions in the areas of data analysis, policy development, quality control, program evaluation, operations, administrative cost management, civil rights, and training to develop appropriate and effective corrective action measures. [Amdt. 160, 45 FR 15909, Mar. 11, 1980, as amended by Amdt. 169, 46 FR 7263, Jan. 23, 1981; Amdt. 262, 49 FR 50598, Dec. 31, 1984; Amdt. 266, 52 FR 3409, Feb. 4, 1987; Amdt. 328, 56 FR 60052, Nov. 27, 1991; 68 FR 59523, Oct. 16, 2003; 75 FR 33438, June 11, 2010; 81 FR 2741, Jan. 19, 2016] § 275.17 State corrective action plan. (a) State agencies shall prepare corrective action plans addressing those deficiencies specified in § 275.16(b) requiring action by the State agency or the combined efforts of the State agency and the project area(s)/management unit(s). This corrective action plan is an open-ended plan and shall remain in effect until all deficiencies in program operations have been reduced substantially or eliminated. State agencies shall provide updates to their corrective action plans through regular, semiannual updates. These semiannual updates shall be received by FNS by May 1st and November 1st respectively. Such updates must contain: (1) Any additional deficiencies identified since the previous corrective action plan update; (2) Documentation that a deficiency has been corrected and is therefore being removed from the plan; and (3) Any changes to planned corrective actions for previously reported deficiencies. (b) Content. (1) Specific description and identification of each deficiency; (2) Source(s) through which the deficiency was detected; (3) Magnitude of each deficiency, if appropriate, as defined in § 275.15(c)(3) of this part; (4) Geographic extent of the deficiency (e.g., Statewide/project area or management unit—specific project areas in which the deficiency occurs); (5) Identification of causal factor(s) contributing to the occurrence of each deficiency; (6) Identification of any action already completed to eliminate the deficiency; (7) For each deficiency, an outline of actions to be taken, the expected outcome of each action, the target date for each action, and the date by which each deficiency will have been eliminated; and (8) For each deficiency, a description of the manner in which the State agency will monitor and evaluate the effectiveness of the corrective action in eliminating the deficiency. (c) FNS will provide technical assistance in developing corrective action plans when requested by State agencies. (d) State agencies will be held accountable for the efficient and effective operation of all areas of the program. FNS is not precluded from issuing a warning as specified in part 276 because a deficiency is included in the State agency's corrective action plan. [Amdt. 160, 45 FR 15909, Mar. 11, 1980, as amended by Amdt. 266, 52 FR 3409, Feb. 4, 1987] § 275.18 Project area/management unit corrective action plan. (a) The State agency shall ensure that corrective action plans are prepared at the project area/management unit level, addressing those deficiencies not required to be included in the State corrective action plan. State agencies may elect to prepare these plans for or in cooperation with the project area. These project area/management unit corrective action plans shall be open-ended and shall remain in effect until all deficiencies in program operations have been reduced substantially or eliminated. Any deficiencies detected through any source not previously reported to the State agency which require incorporation into the Project Area/Management Unit Corrective Action Plan shall be submitted to the State agency within 60 days of identification. As deficiencies are reduced substantially or eliminated, the project area/management unit shall notify the State agency in writing. The project area/management unit shall be responsible for documenting why each deficiency is being removed from the Plan. The removal of any deficiency from the Plan will be subject to State agency and FNS review and validation. (b) Content. (1) Specific description and identification of each deficiency; (2) Source(s) through which the deficiency was detected; (3) Magnitude of each deficiency, if appropriate, as defined in § 275.15(c)(3) of this part; (4) Geographic extent of the deficiency (throughout the project area/management unit or only in specific offices); (5) Identification of causal factor(s) contributing to the occurrence of each deficiency; (6) Identification of any action already completed to eliminate the deficiency; (7) For each deficiency, an outline of actions to be taken, the expected outcome of each action, the target date for each action, the date by which each deficiency will have been eliminated; and (8) For each deficiency, a description of the manner in which the project area/management unit will monitor and evaluate the effectiveness of the corrective action in eliminating the deficiency. [Amdt. 160, 45 FR 15909, Mar. 11, 1980] § 275.19 Monitoring and evaluation. (a) The State agency shall establish a system for monitoring and evaluating corrective action at the State and project area levels. Monitoring and evaluation shall be an ongoing process to determine that deficiencies are being substantially reduced or eliminated in an efficient manner and that the program provides responsive service to eligible households. (b) The State agency shall ensure that corrective action on all deficiencies identified in the State Corrective Action Plan and Project Area/Management Unit Corrective Action Plan is implemented and achieves the anticipated results within the specified time frames. The State agency shall monitor and evaluate corrective action at the State and project levels through a combination of reports, field reviews, and examination of current data available through program management tools and other sources. (c) In instances where the State agency and/or the project area/management unit determines that the proposed corrective action is not effective in reducing substantially or eliminating deficiencies, the State agency and/or the project area/management unit shall promptly reevaluate the deficiency, causes, and the corrective action taken, and develop and implement new corrective actions. [Amdt. 160, 45 FR 15909, Mar. 11, 1980] Subpart F—Responsibilities for Reporting on Program Performance § 275.20 ME review schedules. (a) Each State agency shall submit its review schedule to the appropriate FNS regional office at least 60 days prior to the beginning of the next year's review period (the Federal fiscal year). These schedules must ensure that all project areas/management units will be reviewed within the required time limits. Each schedule shall identify the project areas/management units in each classification and list each project area to be reviewed by month or by quarter. A State agency may submit a request to use an alternate review schedule at any time. The alternate schedule shall not be effective until approved by FNS in accordance with § 275.5(b)(2). (b) State agencies shall notify the appropriate FNS regional office of all changes in review schedules. [Amdt. 266, 52 FR 3410, Feb. 4, 1987] § 275.21 Quality control review reports. (a) General. (b) Individual cases. (1) The State agency shall utilize SNAPQCS, FNS' automated, web-based QC System, to report all required QC forms, supporting evidence, and information necessary to understand the disposition and final findings for active and negative sampled cases to FNS. Upon State agency request, FNS will consider approval of any technical changes in the review results after they have been reported to FNS. (2) The State agency shall have at least 115 days from the end of the sample month to dispose of and report the findings of all cases selected in a sample month. FNS may grant additional time as warranted upon request by a State agency for cause shown to complete and dispose of individual cases. (3) The State agency shall supply the FNS Regional Office with individual household case records and the pertinent information contained in the individual case records, or legible copies of that material, as well as legible hard copies of individual Forms FNS-380, FNS-380-1, and FNS-245 or other FNS-approved report forms, within 10 days of receipt of a request for such information. (4) For each case that remains pending 115 days after the end of the sample month, the State agency shall immediately submit a report that includes an explanation of why the case has not been disposed of, documentation describing the progress of the review to date, and the date by which it will be completed. If FNS extends the time frames in paragraph (b)(2) of this section, this date will be extended accordingly. If FNS determines that the report in the first sentence of this paragraph (b)(4) does not sufficiently justify the case's pending status, the case shall be considered overdue. Depending upon the number of overdue cases, FNS may find the State agency's QC system to be inefficient or ineffective and suspend and/or disallow the State agency's Federal share of administrative funds in accordance with the provisions of § 276.4. (c) Monthly status. (d) Demonstration projects. i.e., [Amdt. 260, 49 FR 6310, Feb. 17, 1984, as amended by Amdt. 262, 49 FR 50598, Dec. 31, 1984; Amdt. 266, 52 FR 3410, Feb. 4, 1987; 75 FR 33438, June 11, 2010; 86 FR 44857, Aug. 13, 2021; 86 FR 49229, Sept. 2, 2021] § 275.22 Administrative procedure. Reports on program performance are intended to provide the State an opportunity to determine compliance with program requirements, identify and resolve emerging problems, and assess the effectiveness of actions that have been taken to correct existing problems. States' reports enable FNS to assess the nationwide status of eligibility and basis of issuance determinations, to ensure State compliance with Federal requirements, to assist States in improving and strengthening their programs, and to develop Federal policies. Reports must be submitted in duplicate to the appropriate FNS Regional Office according to the time frames established in §§ 275.20, 275.21, and 275.22 of this part. [Amdt. 160, 45 FR 15911, Mar. 11, 1980. Redesignated at 52 FR 3410, Feb. 4, 1987] Subpart G—Program Performance § 275.23 Determination of State agency program performance. (a) Determination of efficiency and effectiveness. (1) Reports submitted to FNS by the State; (2) FNS reviews of State agency operations; (3) State performance reporting systems and corrective action efforts; and (4) Other available information such as Federal audits and investigations, civil rights reviews, administrative cost data, complaints, and any pending litigation. (b) State agency error rates. (1) Demonstration projects. (2) Determination of payment error rates. (i) Once the Federal case reviews have been completed and all differences with the State agency have been identified, FNS shall calculate regressed error rates using the following linear regression equations. (A) y 1 y 1 b 1 X 1 x 1 y 1 y 1 b 1 x 1 X 1 Y 1 X 1 x 1 b 1 (B) y 2 y 2 b 2 X 2 x 2 y 2 y 2 b 2 x 2 X 2 y 2 X 2 x 2 b 2 (C) The regressed error rates are given by r 1 y 1 u r 2 y 2 u u (D) After application of the adjustment provisions of paragraph (b)(2)(iii) of this section, the adjusted regressed payment error rate shall be calculated to yield the State agency's payment error rate. The adjusted regressed payment error rate is given by r 1 r 2 (ii) If FNS determines that a State agency has sampled incorrectly, estimated improperly, or has deficiencies in its QC data management system, FNS will correct the State agency's payment and negative case error rates based upon a correction to that aspect of the State agency's QC system which is deficient. If FNS cannot accurately correct the State agency's deficiency, FNS will assign the State agency a payment error rate or negative case error rate based upon the best information available. After consultation with the State agency, the assigned payment error rate will then be used in the liability determination. After consultation with the State agency, the assigned negative case error rate will be the official State negative case error rate for any purpose. State agencies shall have the right to appeal assessment of an error rate in this situation in accordance with the procedures of Part 283 of this chapter. (iii) Should a State agency fail to complete 98 percent of its required sample size, FNS shall adjust the State agency's regressed error rates using the following equations: (A) r 1 r 1 C S 1 r 1 r 1 C S 1 r 1 r 1 (B) r 2 r 2 C S 2 r 2 r 2 C S 2 r 2 r 2 (c) FNS Time frames for completing case review process, arbitration, and issuing error rates. (d) State agencies' liabilities for payment error rates. (1) National performance measure. (2) Liability. (3) Right to appeal payment error rate liability. (4) Relationship to warning process and negligence. (ii) FNS shall not determine negligence (as described in § 276.3 of this chapter) based on the overall payment error rate for issuances to ineligible households and overissuances to eligible households in a State or political subdivision thereof. FNS may only establish a claim under § 276.3 of this chapter for dollar losses from failure to comply, due to negligence on the part of the State agency (as defined in § 276.3 of this chapter), with specific certification requirements. Thus, FNS will not use the result of States' QC reviews to determine negligence. (iii) Whenever a State is assessed a liability amount for an excessive payment error rate, the State shall have the right to request an appeal in accordance with procedures set forth in part 283 of this chapter. While FNS may determine a State to be liable for dollar loss under the provisions of this section and the negligence provisions of § 276.3 of this chapter for the same period of time, FNS shall not bill a State for the same dollar loss under both provisions. If FNS finds a State liable for dollar loss under both the QC liability system and the negligence provisions, FNS shall adjust the billings to ensure that two claims are not made against the State for the same dollar loss. (e) Liability amount determinations. (i) Require the State agency to invest up to 50 percent of the liability in activities to improve program administration (new investment money shall not be matched by Federal funds) and (ii) Designate up to 50 percent of the liability as “at-risk” for repayment if a liability is established based on the State agency's payment error rate for the subsequent fiscal year, or (iii) Choose any combination of these options. (2) Once FNS determines the percentages in accordance with paragraphs (e)(1)(i) through (e)(1)(iv) of this section, the amount assigned as at-risk is not subject to settlement negotiation between FNS and the State agency and may not be reduced unless an appeal decision revises the total dollar liability. FNS and the State agency shall settle any waiver percentage amount or new investment percentage amount before the end of the fiscal year in which the liability amount is determined. The determination of percentages for waiver, new investment, and/or at-risk amounts by the Department is not appealable. Likewise, a settlement of the waiver and new investment amounts cannot be appealed. (f) Good cause. (1) Natural disasters and civil disorders. (i) When submitting a request for good cause relief based on this example, the State agency shall provide the following information: (A) The nature of the disaster(s) ( e.g., (B) The date(s) of the occurrence; (C) The date(s) after the occurrence when program operations were affected; (D) The geographic extent of the occurrence ( i.e., (E) The proportion of the Supplemental Nutrition Assistance Program caseload whose management was affected; (F) The reason(s) why the State agency was unable to control the effects of the disaster on program administration and errors. (G) The identification and explanation of the uncontrollable nature of errors caused by the event (types of errors, geographic location of the errors, time period during which the errors occurred, etc.). (H) The percentage of the payment error rate that resulted from the occurrence and how this figure was derived; and (I) The degree to which the payment error rate exceeded the national performance measure in the subject fiscal year. (ii) (A) The following criteria and methodology will be used to assess and evaluate good cause in conjunction with the appeals process, and to determine that portion of the error rate/liability amount attributable to the uncontrollable effects of a disaster or civil disorder: ( 1 ( 2 ( 3 ( 4 (B) Adjustments for these factors may result in a waiver of all, part, or none of the liability amount for the applicable period. As appropriate, the waiver amount will be adjusted to reflect States' otherwise effective administration of the program based upon the degree to which the error rate exceeds the national performance measure. For example, a reduction in the waiver amount may be made when a State agency's recent error rate history indicates that even absent the events described the State agency would have exceeded the national performance measure in the review period. (iii) If a State agency has provided insufficient information to determine a waiver amount for the uncontrollable effects of a natural disaster or civil disorder using factual analysis, the waiver amount shall be evaluated using the following formula and methodology which measures both the duration and intensity of the event. Duration will be measured by the number of months the event had an adverse impact on program operations. Intensity will be a proportional measurement of the issuances for the counties affected to the State's total issuance. This ratio will be determined using issuance figures for the first full month immediately preceding the disaster. This figure will not include issuances made to households participating under disaster certification authorized by FNS and already excluded from the error rate calculations under § 275.12(g)(2)(vi). The counties considered affected will include counties where the disaster/civil disorder occurred, and any other county that the State agency can demonstrate had program operations adversely impacted due to the event (such as a county that diverted significant numbers of Supplemental Nutrition Assistance Program certification or administrative staff). The amount of the waiver of liability will be determined using the linear equation W = Ia/Ib × [M/12 or Mp/18] × L, where Ia is the issuance for the first full month immediately preceding the unusual event for the county affected; Ib is the State's total issuance for the first full month immediately preceding the unusual event; M/12 is the number of months in the subject fiscal year that the unusual event had an adverse impact on program operations; Mp/18 is the number of months in the last half (April through September) of the prior fiscal year that the unusual event had an adverse impact on program operations; L is the total amount of the liability for the fiscal year. Mathematically this formula could result in a waiver of more than 100 percent of the liability amount; however, no more than 100 percent of a State's liability amount will be waived for any one fiscal year. Under this approach, unless the State agency can demonstrate a direct uncontrollable impact on the error rate, the effects of disasters or civil disorders that ended prior to the second half of the prior fiscal year will not be considered. (2) Strikes. (i) When submitting a request for good cause relief based on this example, the State agency shall provide the following information: (A) Which workers ( i.e., (B) The date(s) and nature of the strike ( i.e., (C) The date(s) after the occurrence when program operations were affected; (D) The geographic extent of the strike ( i.e., (E) The proportion of the Supplemental Nutrition Assistance Program caseload whose management was affected; (F) The reason(s) why the State agency was unable to control the effects of the strike on program administration and errors; (G) Identification and explanation of the uncontrollable nature of errors caused by the event (types of errors, geographic location of the errors, time period during which the errors occurred, etc.); (H) The percentage of the payment error rate that resulted from the strike and how this figure was derived; and (I) The degree to which the payment error rate exceeded the national performance measure in the subject fiscal year. (ii) (A) The following criteria shall be used to assess, evaluate and respond to claims by the State agency for a good cause waiver of a liability amount in conjunction with the appeals process, and to determine that portion of the error rate/liability amount attributable to the uncontrollable effects of the strike: ( 1 ( 2 ( 3 ( 4 (B) Adjustments for these factors may result in a waiver of all, part, or none of the liability amount for the applicable period. For example, the amount of the waiver might be reduced for a strike that was limited to a small area of the State. As appropriate, the waiver amount will be adjusted to reflect States' otherwise effective administration of the program based upon the degree to which the error rate exceeded the national performance measure. (iii) If a State agency has provided insufficient information to determine a waiver amount for the uncontrollable effects of a strike using factual analysis, a waiver amount shall be evaluated by using the formula described in paragraph (f)(1) of this section. Under this approach, unless the State agency can demonstrate a direct uncontrollable impact on the error rate, the effects of strikes that ended prior to the second half of the prior fiscal year will not be considered. (3) Caseload growth. (i) When submitting a request for good cause relief based on this example, the State agency shall provide the following information: (A) The amount of growth (both actual and percentage); (B) The time the growth occurred (what month(s)/year); (C) The date(s) after the occurrence when program operations were affected; (D) The geographic extent of the caseload growth ( i.e. (E) The impact of caseload growth; (F) The reason(s) why the State agency was unable to control the effects of caseload growth on program administration and errors; (G) The percentage of the payment error rate that resulted from the caseload growth and how this figure was derived; and (H) The degree to which the error rate exceeded the national performance measure in the subject fiscal year. (ii) (A) The following criteria and methodology shall be used to assess and evaluate good cause in conjunction with the appeals process, and to determine that portion of the error rate/liability amount attributable to the uncontrollable effects of unusual caseload growth: ( 1 ( 2 ( 3 ( 4 (B) Adjustments for these factors may result in a waiver of all, part, or none of the liability amount for the applicable period. As appropriate, the waiver amount will be adjusted to reflect States' otherwise effective administration of the program based upon the degree to which the error rate exceeded the national performance measure. For example, a reduction in the waiver amount may be made when a State agency's recent error rate history indicates that even absent the events described the State agency would have exceeded the national performance measure in the review period. Under this approach, unless the State agency can demonstrate a direct uncontrollable impact on the error rate, the effects of caseload growth that ended prior to the second half of the prior fiscal year will not be considered. (iii) If the State agency has provided insufficient information to determine a waiver amount for the uncontrollable effects of caseload growth using factual analysis, the waiver amount shall be evaluated using the following five-step calculation: (A) Step 1—determine the average number of households certified to participate Statewide in the Supplemental Nutrition Assistance Program for the base period consisting of twelve consecutive months ending with March of the prior fiscal year; (B) Step 2—determine the percentage of increase in caseload growth from the base period (Step 1) using the average number of households certified to participate Statewide in the Supplemental Nutrition Assistance Program for any twelve consecutive months in the period beginning with April of the prior fiscal year and ending with June of the current year; (C) Step 3—determine the percentage the error rate for the subject fiscal year, as calculated under paragraph (b)(2) of this section, exceeds the national performance measure determined in accordance with paragraph (d)(1) of this section; (D) Step 4—divide the percentage of caseload growth increase arrived at in step 2 by the percentage the error rate for the subject fiscal year exceeds the national performance measure as determined in step 3; and (E) Step 5—multiply the quotient arrived at in step 4 by the liability amount for the current fiscal year to determine the amount of waiver of liability. (iv) Under this methodology, caseload growth of less than 15% and/or occurring in the last three months of the subject fiscal year will not be considered. Mathematically this formula could result in a waiver of more than 100 percent of the liability amount; however, no more than 100 percent of a State's liability amount will be waived for any one fiscal year. (4) Program changes. (i) When submitting a request for good cause relief based on unusual changes in the Supplemental Nutrition Assistance Program or other Federal or State programs, the State agency shall provide the following information: (A) The type of changes(s) that occurred; (B) When the change(s) occurred; (C) The nature of the adverse effect of the changes on program operations and the State agency's efforts to mitigate these effects; (D) Reason(s) the State agency was unable to adequately handle the change(s); (E) Identification and explanation of the uncontrollable errors caused by the changes (types of errors, geographic location of the errors, time period during which the errors occurred, etc.); (F) The percentage of the payment error rate that resulted from the adverse impact of the change(s) and how this figure was derived; and (G) The degree to which the payment error rate exceeded the national performance measure in the subject fiscal year. (ii) (A) The following criteria will be used to assess and evaluate good cause in conjunction with the appeals process and to determine that portion of the error rate/liability amount attributable to the uncontrollable effects of unusual changes in the Supplemental Nutrition Assistance Program or other Federal and State programs: ( 1 ( 2 ( 3 (B) Adjustments for these factors may result in a waiver of all, part, or none of the liability amount for the applicable period. As appropriate, the waiver amount will be adjusted to reflect States' otherwise effective administration of the program based upon the degree to which the error rate exceeded the national performance measure. (5) Significant circumstances beyond the control of a State agency. (i) The State agency shall provide the following information when submitting a request for good cause relief based on significant circumstances, the State agency shall provide the following information: (A) The significant circumstances that the State agency believes uncontrollably and adversely affected the payment error rate for the fiscal year in question; (B) Why the State agency had no control over the significant circumstances; (C) How the significant circumstances had an uncontrollable and adverse impact on the State agency's error rate; (D) Where the significant circumstances existed ( i.e. (E) When the significant circumstances existed (provide specific dates whenever possible); (F) The proportion of the Supplemental Nutrition Assistance Program caseload whose management was affected; (G) Identification and explanation of the uncontrollable errors caused by the event (types of errors, geographic location of the errors, time period during which the errors occurred, etc.); (H) The percentage of the payment error rate that was caused by the significant circumstances and how this figure was derived; and (I) The degree to which the payment error rate exceeded the national performance measure in the subject fiscal year. (ii) (A) The following criteria shall be used to assess and evaluate good cause in conjunction with the appeals process, and to determine that portion of the error rate/liability amount attributable to the uncontrollable effects of a significant circumstance beyond the control of the State agency, other than those set forth in paragraph (f)(5) of this section: ( 1 ( 2 ( 3 ( 4 (B) Adjustments for these factors may result in a waiver of all, part, or none of the liability amount for the applicable period. As appropriate, the waiver amount will be adjusted to reflect States' otherwise effective administration of the program based upon the degree to which the error rate exceeded the national performance measure. (6) Adjustments. (7) Evidence. (8) Finality. (g) Results of appeals on liability amount determinations. (2) If FNS wholly prevails on a State agency's appeal, FNS will require the State agency to invest all or a portion of the amount designated for new investment to be invested or to be paid to the Federal government. (3) If neither the State agency nor FNS wholly prevails on a State agency's appeal, FNS shall apply the original waiver, new investment, and at-risk percentage determinations to the liability amount established through the appeal. If the State agency began new investment prior to the appeal decision and has already expended more than the amount produced for new investment as a result of the appeal decision, the Department will match the amount of funds expended in excess of the amount now required by the Department for new investment. (h) New investment requirements. (1) The State agency's investment plan activity or activities must meet the following conditions to be accepted by the Department: (i) The activity or activities must be directly related to error reduction in the ongoing program, with specific objectives regarding the amount of error reduction, and type of errors that will be reduced. The costs of demonstration, research, or evaluation projects under sections 17(a) through (c) of the Act will not be accepted. The State agency may direct the investment plan to a specific project area or implement the plan on a Statewide basis. In addition, the Department will allow an investment plan to be tested in a limited area, as a pilot project, if the Department determines it to be appropriate. A request by the State agency for a waiver of existing rules will not be acceptable as a component of the investment plan. The State agency must submit any waiver request through the normal channels for approval and receive approval of the request prior to including the waiver in the investment plan. Waivers that have been approved for the State agency's use in the ongoing operation of the program may continue to be used. (ii) The program administration activity must represent a new or increased expenditure. The proposed activity must also represent an addition to the minimum program administration required by law for State agency administration including corrective action. Therefore, basic training of eligibility workers or a continuing correction action from a Corrective Action Plan shall not be acceptable. The State agency may include a previous initiative in its plan; however, the State agency would have to demonstrate that the initiative is entirely funded by State money, represents an increase in spending and there are no remaining Federal funds earmarked for the activity. (iii) Investment activities must be funded in full by the State agency, without any matching Federal funds until the entire amount agreed to is spent. Amounts spent in excess of the settlement amount included in the plan may be subject to Federal matching funds. (2) The request shall include: (i) A statement of the amount of money that is a quality control liability claim that is to be offset by investment in program improvements; (ii) A detailed description of the planned program administration activity; (iii) Planned expenditures, including time schedule and anticipated cost breakdown; (iv) Anticipated impact of the activity, identifying the types of error expected to be affected; (v) Documentation that the funds would not replace expenditures already earmarked for an ongoing effort; and (vi) A statement that the expenditures are not simply a reallocation of resources. (3) A State agency may choose to begin expending State funds for any amount of the liability designated as “new investment” in the liability amount determination prior to any appeal. FNS reserves the right to approve whether the expenditure meets the requirements for new investment. Expenditures made prior to approval by the Department will be subject to approval before they are accepted. Once a new investment plan is approved, the State agency shall submit plan modifications to the Department for approval, prior to implementation. (4) Each State agency which has part of a liability designated for new investment shall submit periodic documented reports according to a schedule in its approved investment plan. At a minimum, these reports shall contain: (i) A detailed description of the expenditure of funds, including the source of funds and the actual goods and services purchased or rented with the funds; (ii) A detailed description of the actual activity; and (iii) An explanation of the activity's effect on errors, including an explanation of any discrepancy between the planned effect and the actual effect. (5) Any funds that the State agency's reports do not document as spent as specified in the new investment plan may be recovered by the Department. Before the funds are withdrawn, the State agency will be provided an opportunity to provide the missing documentation. (6) If the funds are recovered, the Department shall charge interest on the funds not spent according to the plan in accordance with paragraph (j) of this section. (i) At-risk money. (j) Interest charges. (2) A State agency may choose to pay the amount designated as at-risk prior to resolution of any appeals. If the State agency pays such claim (in whole or in part) and the claim is subsequently overturned or adjusted through administrative or judicial appeal, any amounts paid by the State agency above what is actually due shall be promptly returned with interest, accruing from the date the payment was received until the date the payment is returned. (3) Any interest assessed under paragraph (j)(1) of this section shall be computed at a rate determined by the Secretary based on the average of the bond equivalent of the weekly 90-day Treasury bill auction rates during the period such interest accrues. The bond equivalent is the discount rate ( i.e., i.e., i.e., [75 FR 33438, June 11, 2010, as amended at 80 FR 53243, Sept. 3, 2015; 86 FR 44587, Aug. 13, 2021] § 275.24 High performance bonuses. (a) General rule. (2) FNS will award the bonuses no later than September 30th of the fiscal year following the performance measurement year. (3) A State agency is not eligible for a bonus payment in any fiscal year for which it has a liability amount established as a result of an excessive payment error rate in the same year. If a State is disqualified from receiving a bonus payment under this paragraph (a)(3), and the State is not tied for a bonus, the State with the next best performance will be awarded a bonus payment. (4) The determination whether, and in what amount, to award a performance bonus payment is not subject to administrative or judicial review. (5) In determining the amount of the award, FNS will first award a base amount of $100,000 to each State agency that is an identified winner in each category. Subsequently, FNS will divide the remaining money among the States in each category (see paragraph (b) of this section) in proportion to the size of their caseloads (the average number of households per month for the fiscal year for which performance is measured). (6) A State cannot be awarded two bonuses in the same category; the relevant categories are payment accuracy (which is outlined in paragraph (b)(1) of this section), negative error rate (which is outlined in paragraph (b)(2) of this section), or program access index (which is outlined in paragraph (b)(3) of this section). If a State is determined to be among the best and the most improved in a category, it will be awarded a bonus only for being the best. The next State in the best category will be awarded a bonus as being among the best States. (7) Where there is a tie to the fourth decimal point for the categories outlined in paragraphs (b)(1) through (b)(4) of this section, FNS will add the additional State(s) into the category and the money will be divided among all the States in accordance with paragraph (a)(5) of this section. (8) Bonus award money shall be used only on SNAP-related expenses including, but not limited to, investments in technology; improvements in administration and distribution; and actions to prevent fraud, waste and abuse. (i) Bonus payments shall not be used for household benefits, including incentive payments. (ii) State agency awardees shall submit their intended spending plans of bonus payments to FNS to verify appropriate use. (b) Performance measures. (1) Payment accuracy. (i) Excellence in payment accuracy. (ii) Most improved in payment accuracy. (2) Negative error rate. (i) Lowest negative error rate. (ii) Most improved negative error rate. (3) Program access index (PAI). (i) High program access index. (ii) Most improved program access index. (iii) Data. (4) Application processing timeliness. (i) Data. (ii) Timely processed applications. (iii) Evaluation of applications. [70 FR 6322, Feb. 7, 2005, as amended at 80 FR 53243, Sept. 3, 2015]