PART 1924—CONSTRUCTION AND REPAIR Authority: 5 U.S.C. 301; 7 U.S.C 1989; 42 U.S.C 1480. Editorial Note: Nomenclature changes to part 1924 appear at 80 FR 9870, Feb. 24, 2015. Subpart A—Planning and Performing Construction and Other Development Source: 52 FR 8002, Mar. 13, 1987, unless otherwise noted. § 1924.1 Purpose. This subpart prescribes the basic Agency policies, methods, and responsibilities in the planning and performing of construction and other development work for insured Rural Housing (RH), single unit Labor Housing (LH). It also provides supplemental requirements for Rural Rental Housing (RRH) loans, Rural Cooperative Housing (RCH) loans, multi-unit (LH) loans and grants, and Rural Housing Site (RHS) loans. This subpart is inapplicable to Farm Service Agency, Farm Loan Programs. [53 FR 35679, Sept. 14, 1988, as amended at 72 FR 64122, Nov. 15, 2007] § 1924.2 [Reserved] § 1924.3 Authorities and responsibilities. The County Supervisor and District Director are authorized to redelegate, in writing, any authority delegated to them in this subpart to the Assistant County Supervisor and Assistant District Director, respectively, when determined to be qualified. Agency Construction Inspectors, District Loan Assistants, and County Office Assistants are authorized to perform duties under this subpart as authorized in their job descriptions. § 1924.4 Definitions. (a) Construction. (b) Contract documents. (c) Contractor. (d) County Supervisor and District Director. (e) Date of commencement of work. (f) Date of substantial completion. (g) Development. (h) Development standards. (1) A standard adopted by the Agency for each state in accordance with § 1924.5(d)(1)(i)(E) of this subpart. (2) Voluntary national model building codes (model codes). (3) Minimum Property Standards (MPS). (i) Identity of interest. (1) When there is any financial interest of the party of the first part in the party of the second part. The providing of normal professional services by architects, engineers, attorneys or accountants with a client-professional relationship shall not constitute an identity of interest. (2) When one or more of the officers, directors, stockholders or partners of the party of the first part is also an officer, director, stockholder, or partner of the party of the second part. (3) When any officer, director, stockholder or partner of the party of the first part has any financial interest whatsoever in the party of the second part. (4) Between the spouse, significant other, relatives, and step-relatives of the principal owners of the party of the first part and its management, such as Grandmother, Aunt, Daughter, Granddaughter, Grandfather, Uncle, Son, Grandson, Mother, Sister, Niece, Cousin, Father, Brother, Nephew; (5) When the party of the second part advances any funds to the party of the first part. (6) When the party of the second part provides and pays on behalf of the party of the first part the cost of any legal services, architectural services or engineering services other than those of a surveyor, general superintendent, or engineer employed by a general contractor in connection with obligations under the construction contract. (7) When the party of the second part takes stock or any interest in the party of the first part as part of the consideration to be paid them. (8) When there exist or come into being any side deals, agreements, contracts or undertakings entered into thereby altering, amending, or cancelling any of the required closing documents except as approved by the Agency. (9) An identity of interest will also exist when another party can significantly influence the management or operating policies of the transacting parties or if it has an ownership interest in one of the transacting parties and can significantly influence the other to an extent that one or more of the transacting parties might be prevented from fully pursuing its own separate interests. (j) Land development. (k) Manufactured housing. (l) Mechanic's and materialmen's liens. (m) Modular/panelized housing. (n) Project representative. (o) Technical services. (1) Architectural services. The services of a professionally qualified person or organization, duly licensed and qualified in accordance with state law to perform architectural services. (2) Engineering services. The services of a professionally qualified person or organization, duly licensed and qualified in accordance with State law to perform engineering services. (p) Warranty. [52 FR 8002, Mar. 13, 1987, as amended at 59 FR 6882, Feb. 14, 1994] § 1924.5 Planning development work. (a) Extent of development. (b) Funds for development work. (c) Scheduling of development work. (2) Development for farm program loans will be scheduled for completion as quickly as practicable and no later than 15 months from the date of loan closing unless more time is needed to establish land developnent practices in the area. (d) Construction. (i) The development standard applicable to a proposal will be selected by the loan applicant or recipient of an RH Conditional Commitment in accordance with the following. The standard selected must: (A) Relate to the type(s) of building proposed. (B) Meet or exceed any applicable local or state laws, ordinances, codes and regulations. (C) Include all referenced codes and standards. (D) Exclude inapplicable administrative requirements. (E) Be the current edition(s) of either paragraph (d)(1)(i)(E)( 1 2 ( 1 ( i ( ii ( iii ( 2 (ii) Guide 2, “ Rural Development Design Guide,” of this subpart (available in any Rural Development office), includes guidelines for the evaluation of the design features which are not fully addressed in the development standards. (iii) In new housing, all design, materials and construction will meet or exceed the applicable development standard as provided in paragraph (d)(1)(i) of this section. (iv) For multi-family residential rehabilitation, as defined in exhibit K of this subpart, all substantial rehabilitation work on existing buildings will meet or exceed the applicable development standard. All moderate rehabilitation work should comply with Guide 3, “Quality and Performance Criteria for Moderate Rehabilitation,” of this subpart (available in any Agency office). (v) The design and construction of housing repairs made with Agency loan or grant funds will, as near as possible, comply with the applicable development standard. (vi) Farm LH design and construction will comply with the following: (A) Family projects, where the length of occupancy will be: ( 1 ( 2 ( 3 (B) Dormitory and other nonfamily type projects, where the length of occupancy will be: ( 1 ( 2 (vii) Farm service buildings should be designed and constructed for adaptation to the local area. In designing and locating farm service buildings, consideration will be given to practices recommended by agriculture colleges, the Extension Service (ES), Soil Conservation Service (SCS) and other reliable sources. (2) Drawings, specifications, and estimates will fully describe the work. Technical data, tests, or engineering evaluations may be required to support the design of the development. The “Guide for Drawings and Specifications,” exhibit C of this subpart, describes the drawings and specifications that are to be included in the application for building construction, and subpart C of part 1924 of this chapter describes the drawings that should be included for development of building sites. The specific development standard being used, if required under paragraph (d)(1) of this section will be identified on all drawings and specifications. (3) Materials acceptance shall be the same as described in paragraph X of exhibit B to this subpart. (4) Except as provided in paragraphs (d)(4)(i) through (iii) of this section, new building construction and additions shall be designed and constructed in accordance with the earthquake (seismic) requirements of the applicable Agency's development standard (building code). The analysis and design of structural systems and components shall be in accordance with applicable requirements of an acceptable model building code. (i) Agricultural buildings that are not intended for human habitation are exempt from these earthquake (seismic) requirements. (ii) Single family conventional light wood frame dwellings of two stories or 35 feet in height maximum shall be designed and constructed in accordance with the 1992 Council of American Building Officials (CABO) One and Two Family Dwelling Code or the latest edition. (iii) Single family housing of masonry design and townhouses of wood frame construction and additions financed (either directly or through a guarantee) under title V of the Housing Act of 1949 are recommended to be designed and constructed in accordance with the earthquake (seismic) requirements of one of the building codes that provides an equivalent level of safety to that contained in the latest edition of the National Earthquake Hazard Reduction Program's (NEHRP) Recommended Provisions for the Development of Seismic Regulations for New Building (NEHRP Provisions). (iv) Acknowledgment of compliance with the applicable seismic safety requirements for new construction will be contained in the certification of final plans and specification on the appropriate Agency Form. (e) Land development. (2) Site and subdivision planning and development must meet the requirements of subpart C of part 1924 of this chapter. (3) Plans and descriptive material will fully describe the work. (4) The site planning design, development, installation and set-up of manufactured home sites, rental projects and subdivisions shall meet the requirements of exhibit J of this subpart and subpart C of part 1924 of this chapter. (i) Plans for land leveling, irrigation, or drainage should include a map of the area to be improved showing the existing conditions with respect to soil, topography, elevations, depth of topsoil, kind of subsoil, and natural drainage, together with the proposed land development. (ii) When land development consists of, or includes, the conservation and use of water for irrigation or domestic purposes, the information submitted to the County Supervisor will include a statement as to the source of the water supply, right to the use of the water, and the adequacy and quality of the supply. (f) Responsibilities for planning development. (1) Responsibility of the applicant. (ii) When items of construction or land development require drawings and specifications, they will be sufficiently complete to avoid any misunderstanding as to extent, kind, and quality of work to be performed. The applicant will provide the Agency with one copy of the drawings and specifications. Approval will be indicated by the applicant and acceptance for the purposes of the loan indicated by the County Supervisor or District Director on all sheets of the drawings and at the end of the specifications, and both instruments will be a part of the loan docket. After the loan is closed, the borrower will retain a conformed copy of the approved drawings and specifications, and provide another conformed copy to the contractor. Items not requiring drawings and specifications may be described in narrative form. (iii) The Agency will accept final drawings and specifications and any modifications thereof only after the documents have been certified in writing as being in conformance with the applicable development standard if required under paragraph (d)(1) of this section. Certification is required for all Single Family Housing (SFH) thermal designs (plans, specifications, and calculations). (A) Certifications may be accepted from individuals or organizations who are trained and experienced in the compliance, interpretation or enforcement of the applicable development standards for drawings and specifications. Plan certifiers may be any of the following: ( 1 ( 2 ( 3 ( 4 ( 5 (B) The license or authorization of the individual must be current at the time of the certification statement. A building permit (except as noted in paragraph (f)(1)(iii)(C)( 2 (C) For Single Family Housing (one to four family dwelling units) the Agency may also accept drawings and specifications that have been certified by: ( 1 ( 2 ( 3 1 2 ( 4 ( 5 (D) The modifications of certified drawings or specifications must be certified by the same individual or organization that certified the original drawings and specifications. If such individual or organization is not available, the entire set of modified drawings and specifications must be recertified. (E) The certification of modifications for single family housing (SFH) construction may be waived if the builder or original author of the drawings and specifications provides a written statement that the modifications are not regulated by the applicable development standard. The County Supervisor may consult with the State Office Architect/Engineer as to acceptance of the statement and granting a waiver. (F) All certifications of final drawings, specifications, and calculations shall be on Form RD 1924-25, “Plan Certification.” (2) Responsibility of the County Supervisor or District Director. (i) Visit each farm or site on which the development is proposed. For an FO loan, the County Supervisor and the applicant will determine the items of development necessary to put the farm in a livable and operable condition at the outset. Prepare Form RD 1924-1, when applicable in accordance with the Forms Manual Insert (FMI) for the form, after a complete understanding has been reached between the applicant and the County Supervisor regarding the development to be accomplished, including the dates each item of development will be started and completed. (ii) Notify the loan or grant applicant in writing immediately if, after reviewing the preliminary proposal and inspecting the site, the proposal is not acceptable. If the proposal is acceptable, an understanding will be reached with the applicant concerning the starting date for each item of development. (iii) Discuss with the applicant the Agency requirements with respect to good construction and land development practices. (iv) Advise the applicant regarding drawings, specifications, cost estimates, and other related material which the applicant must submit to the Agency forreview before the loan can be developed. Advise the applicant of the information necessary in the drawings, how the cost estimates should be prepared, the number of sets of drawings, specifications, and cost estimates required, and the necessity for furnishing such information promptly. Advise the applicant that the Agency will provide appropriate specification forms, Form RD 1924-2, “Description of Materials,” and Form RD 1924-3, “Service Building Specifications.” The applicant may, however, use other properly prepared specifications. (v) Advise the applicant regarding publications, plans, planning aids, engineering data, and other technical advice and assistance available through local, state, and Federal agencies, and private individuals and organizations. (vi) Review the information furnished by the applicant to determine the completeness of the plans, adequacy of the cost estimates, suitability and soundness of the proposed development. (vii) When appropriate, offer suggestions as to how drawings and specifications might be altered to improve the facility and better serve the needs of the applicant. The County Supervisor or District Director may assist the applicant in making revisions to the drawings. When appropriate, the contract documents will be forwarded to the State architect/engineer for review. For revisions requiring technical determinations that the Agency is not able to make, the applicant will be requested to obtain additional technical assistance. (viii) Provide the applicant with a written list of changes required in the contract documents. The applicant will submit two complete revised (as requested) sets of contract documents, for approval. On one set, the County Supervisor or District Director will indicate acceptance on each sheet of the drawings, and on the cover of the specifications and all other contract documents. At least the date and the initials of the approval official must be shown. On projects where a consulting architect or engineer has been retained, this acceptance will be indicated only after the State Director has given written authorization. The marked set of documents shall be available at the job site at all times for review by the Agency. The second set will become part of the loan docket. (ix) Review the proposed method of doing the work and determine whether the work can be performed satisfactorily under the proposed method. (x) Instruct the applicant not to incur any debts prior to loan closing for materials or labor or make any expenditures for such purposes with the expectation of being reimbursed from loan funds. (xi) Instruct the applicant not to commence any construction nor cause any supplies or materials to be delivered to the construction site prior to loan closing. (xii) Under certain conditions prescribed in exhibit H of this subpart, provide the applicant with a copy of the leaflet, “Warning—Lead-Based Paint Hazards,” which is attachment 1 of exhibit H (available in any Agency office), and the warning sheet, “Caution Note on Lead-Based Paint Hazard,” which is attachment 2 of exhibit H (available in any Agency office). (g) Surplus structures and use or sale of timber, sand, or stone. (1) An agreement will be recorded in the narrative of Form RD 1924-1 which as a minimum will: (i) Identify the property to be sold, the estimated net proceeds to be received, and the approximate date by which the property will be sold. (ii) Provide that the borrower will deposit the net proceeds in the supervised bank account and apply any funds remaining after the development is complete as an extra payment on the loan, or in accordance with § 1965.13(f) of subpart A of part 1965 of this chapter for farm program loans. (2) The agreement will be considered by the Government as modifying the mortgage contract to the extent of authorizing and requiring the Government to release the identified property subject to the conditions stated in the agreement without payment or other consideration at the time of release, regardless of whether or not the mortgage specifically refers to Form RD 1924-1 or the agreement to release. (3) If the Agency loan will be secured by a junior lien, all prior lienholders must give written consent to the proposed sale and the use of the net proceeds before the loan is approved. (4) Releases requested by the borrower or the buyer will be processed in accordance with applicable release procedures in 7 CFR part 3550, as appropriate. (h) Review prior to performing development work. (i) Time of starting development work. (1) It is necessary in the area to provide the water supply prior to loan closing, (2) The applicant agrees in writing to pay with personal funds all costs incurred if a satisfactory water supply is not obtained, (3) Any contractors and suppliers understand and agree that loan funds may not be available to make the payment, (4) Such action will not result under applicable State law in the giving of priority to mechanics and materialmen's liens over the later recorded Agency mortgage, and (5) The Agency does not guarantee that the cost will be paid. [52 FR 8002, Mar. 13, 1987, as amended at 52 FR 19283, May 22, 1987; 52 FR 48391, Dec. 22, 1987; 52 FR 48799, Dec. 28, 1987; 53 FR 43676, Oct. 28, 1988; 59 FR 43723, Aug. 25, 1994; 61 FR 65156, Dec. 11, 1996; 67 FR 78326, Dec. 14, 2002] § 1924.6 Performing development work. All construction work will be performed by one, or a combination, of the following methods: Contract, borrower, mutual self-help, or owner-builder. All development work must be performed by a person, firm or organization qualified to provide the service. The mutual self-help method is performance of work by a group of families by mutual labor under the direction of a construction supervisor, as described in 7 CFR part 3550. (a) Contract method. (1) Forms used. (2) Contract provisions. (i) The contract sum. (ii) The dates for starting and completing the work. (iii) The amount of liquidated damages to be charged. (iv) The amount, method, and frequency of payment. (v) Whether or not surety bonds will be provided. (vi) The requirement that changes or additions must have prior written approval of the Agency. (3) Surety requirements. (A) The contract exceeds the applicable Rural Development Single Family Housing area loan limit as per 7 CFR 3550.63. (Loan limits are available at the local Rural Development field office.) (B) The loan approval official determines that a surety bond appears advisable to protect the borrower against default of the contractor. (C) The applicant requests a surety bond. (D) The contract provides for partial payments in excess of the amount of 60 percent of the value of the work in place. (E) The contract provides for partial payments for materials suitably stored on the site. (ii) If surety bonds are required the construction contract must indicate that the contractor will furnish properly executed surety bonds prior to the start of any work. Exhibits F and G of this subpart as revised by OGC if necessary to comply with local or state statutory requirements will be used as the forms of payment bond and performance bond to be provided. Unless noncorporate surety is provided, the surety bonds may only be obtained from a corporate bonding company listed on the current Department of the Treasury Circular 570 (published annually in the Federal Register (iii) When an experienced and reliable contractor cannot obtain payment and performance bonds meeting the surety requirements of paragraph (a)(3)(ii) of this section, the State Director may entertain a request from the applicant for an exception to the surety requirements. The applicant's request must specifically state why the proposed contractor is unable to obtain payment and performance bonds meeting the surety requirements, and why it is financially advantageous for the applicant to award the contract to the proposed contractor without the required bonds. If the applicant's request is reasonable and justified, and if the proposed contractor is reliable and experienced in the construction of projects of similar size, design, scope, and complexity, the State Director may grant an exception to the surety requirements for loans or grants within the State Director's approval authority and accept one or a combination of the following: (A) An unconditional and irrevocable letter of credit issued by a lending institution which has been reviewed and approved by OGC. In such cases, the construction contract must indicate that the contractor will furnish a properly executed letter of credit from a lending institution acceptable to the Agency prior to the start of any work. The letter of credit must remain in effect until the date of final acceptance of work by the owner and the Agency. In addition, the letter of credit must stipulate that the lending institution, upon written notification by the Agency of the contractor's failure to perform under the terms of the contract, will advance funds up to the amount of the contract (including all Agency approved contract change orders) to satisfy all prior debts incurred by the contractor in performing the contract and all funds necessary to complete the work. Payments may be made to the contractor in accordance with paragraph (a)(12)(i)(C) of this section as if full surety bonds were being provided. (B) If a letter of credit satisfying the conditions of paragraph (a)(3)(iii)(A) of this section cannot be obtained, the State Director may accept a deposit in the amount of the contract, into an interest or non-interest bearing supervised bank account. In such cases, the construction contract must indicate that the contractor will furnish the required deposit prior to the start of any work and that the funds shall remain on deposit until final acceptance of work by the owner and the Agency. Payments may be made to the contractor in accordance with paragraph (a)(12)(i)(C) of this section as if full surety bonds were being provided. (C) When the provisions of paragraph (a)(3)(iii) (A) or (B) of this section can be met except that a surety bond, a letter of credit, and/or deposits are not obtainable in full amount of the contract, the State Director may accept an amount less than the full amount of the contract provided all of the following conditions are met: ( 1 ( 2 ( 3 ( 4 Example: Contractor has a surety bond which guarantees payment and performance in an amount of $150,000 which represents 75 percent of the total contract amount of $200,000. The contractor's first request for payment appears thus: —Value of work in place is $10,000. —Payment for work guaranteed by surety is 75 percent times $10,000 times 90 percent is $6,750. —Payment for work not guaranteed by surety is 25 percent times $10,000 times 60 percent is $1,500. —Authorized payment is $8,250. (Each partial payment shall reflect values for work guaranteed by surety, letter of credit, or deposits, and work not so guaranteed). (iv) In cases where the contractor does not obtain payment and performance bonds in accordance with the surety requirements of paragraph (a)(3)(ii) of this section, or where an exception to the surety requirements is granted by the State Director, the following steps will be taken to protect the borrower and the government against latent obligations or defects in connection with the construction: (A) The contractor will furnish a properly executed corporate latent defects bond or a maintenance bond in the amount of 10 percent of the construction contract; or (B) An unconditional and irrevocable letter of credit in the amount of 10 percent of the construction contract issued by a lending institution which has been reviewed and approved by OGC; or (C) A cash deposit into an interest or non-interest bearing supervised bank account in the amount of 10 percent of the construction contract; (D) The period of protection against latent obligations and/or defects shall be one year from the date of final acceptance of work by the owner and the Agency; (E) Final payment shall not be rendered to the contractor until the provisions of paragraph (a)(3)(iv) (A), (B) or (C) of this section have been met; (F) The contract will contain a clause indicating that the contractor agrees to provide surety or guarantee acceptable to the owner and the Agency against latent obligations and/or defects in connection with the construction. (4) Equal opportunity. (5) Labor standards provisions. (6) Historical and archaeological preservation. (7) Air and water acts. (i) To notify the owner of the receipt of any communication from Environmental Protection Agency (EPA) indicating that a facility to be utilized in the performance of the contract is under consideration to be listed on the EPA list of Violating Facilities. Prompt notification is required prior to contract award. (ii) To certify that any facility to be utilized in the performance of any nonexempt contractor subcontract is not listed on the EPA list of Violating Facilities as of the date of contract award. (iii) To include or cause to be included the above criteria and requirements of paragraphs (a)(7) (i) and (ii) of this section in every nonexempt subcontract, and that the contractor will take such action as the Government may direct as a means of enforcing such provisions. (8) Architectural barriers. (9) National Environmental Policy Act. (10) Obtaining bids and selecting a contractor. (ii) When a price has already been negotiated by an applicant and a contractor, the County Supervisor, District Director or other appropriate Agency official will review the proposed contract. If the contractor is qualified to perform the development and provide a warranty of the work and the price compares favorably with the cost of similar construction in the area, further negotiation is unnecessary. If the Agency official determines the price is too high or otherwise unreasonable, the applicant will be requested to negotiate further with the contractor. If a reasonable price cannot be negotiated or if the contractor is not qualified, the applicant will be requested to obtain competitive bids. (iii) When an applicant has a proposed development plan and no contractor in mind, competitive bidding will be encouraged. The applicant should obtain bids from as many qualified contractors, dealers or tradespeople as feasible depending on the method and type of construction. (iv) If the award of the contract is by competitive bidding, Form RD 1924-5, “Invitation for Bid (Construction Contract),” or another similar invitation bid form containing the requirements of subpart E of part 1901 of this chapter, may be used. All contractors from whom bids are requested should be informed of all conditions of the contract including the time and place of opening bids. Conditions shall not be established which would give preference to a specific bidder or type of bidder. When applicable, copies of Forms RD 1924-6 and RD 400-6, “Compliance Statement,” also should be provided to the prospective bidders. (11) Awarding the contract. (i) Before work commences, the County Supervisor, District Director or other Agency employee having knowledge of contracts and construction practices will hold a preconstruction conference with the borrower(s), contractor and architect/engineer (if applicable). The purpose of the conference is to reach a mutual understanding of each party's responsibilities under the terms and conditions of the contract documents and the loan agreement during the construction and warranty periods. Form RD 1924-16, “Record of Preconstruction Conference,” may be used as a guide for an agenda. (ii) A summary of the items covered will be entered in the running case record. (iii) The contract will then be prepared, signed and copies distributed in accordance with the FMI for Form RD 1924-6. (iv) After a borrower/contractor's contract or subcontract in excess of $10,000 is received in the Agency County or District Office, the responsible Agency official will send within 10 calendar days of the date of the contract or subcontract, a report similar in form and content to exhibit C of subpart E of part 1901 of this chapter to the Area Director, Office of Federal Contract Compliance Programs, U.S. Department of Labor, at the applicable address listed in exhibit E, subpart E of part 1901 of this chapter. The report must contain, at least, the following information: contractor's name, address and telephone number; employer's identification number; amount, starting date and planned completion date of the contract; contract number; and city and DOL region of the contract site. The information for this report should be obtained from the contractor when the contract is awarded. (12) Payments for work done by the contract method. (A) The “One-Lump-Sum” payment method will be used when the payment will be made in one lump-sum for the whole contract. (B) The “Partial payments not to exceed 60 percent of the value of the work in place” payment method will be used when the contractor does not provide surety bond, a letter of credit, or deposits. (C) The “Partial payments in the amount of 90 percent of the value of the work in place and of the value of the materials suitably stored at the site” payment method will be used when the contractor provides a surety bond equal to the total contract amount. (D) The “Partial payments which reflect the portions of the contract amount which is guaranteed” method will be used when the contractor provides surety bonds, a letter of credit, or deposits less than the total amount of the contract in accordance with the provisions of paragraph (a)(3)(iii)(C) of this section. (ii) When Form RD 1924-6 is used, the appropriate payment clause will be checked and the other payment clauses not used will be effectively crossed out. (iii) When a contract form other than Form RD 1924-6 is used, the payment clause must conform with paragraph (a)(12)(i) of this section and the appropriate clause as set forth in Form RD 1924-6. (iv) The borrower and FmHA or its successor agency under Public Law 103-354 must take precautionary measures to see that all payments made to the contractor are properly applied against bills for materials and labor procured under the contract. Prior to making any partial payment on any contract where a surety bond is not used, the contractor will be required to furnish the borrower and the FmHA or its successor agency under Public Law 103-354 with a statement showing the total amount owed to date for materials and labor procured under the contract. The contractor also may be required to submit evidence showing that previous partial payments were applied properly. When the borrower and the County Supervisor or District Director have reason to believe that partial payments may not be applied properly, checks may be made jointly to the contractor and persons who furnished materials and labor in connection with the contract. (v) When partial payments are requested by the contractor and approved by the owner, the amount of the partial payment will be determined by one of the following methods: (A) Based upon the percentage completed as shown on a recently completed and properly executed Form RD 1924-12, “Inspection Report.” (B) When the structure will be covered by an insured 10-year warranty, the insurer's construction inspector must provide the Agency with any available copies of inspection reports showing percentage of completion immediately after the inspections are completed. To make partial payments when copies of inspection reports are not available, the responsible Agency official will make the inspections or will be guided by the provisions of § 1924.6(a)(12)(v)(C) of this subpart. If further assurance is deemed necessary to justify partial payments, the Agency official may make onsite inspections or require additional information. (C) Based upon an application for payment containing an estimate of the value of work in place which has been prepared by the contractor and accepted by the borrower and the Agency. When the contract provides for partial payments for materials satisfactorily stored at the site, the application for payment may include these items. Prior to receiving the first partial payment, the contractor should be required to submit a list of major subcontractors and suppliers and a schedule of prices or values of the various phases of the work aggregating the total sum of the contract such as excavation, foundations, framing, roofing, siding, mill work, painting, plumbing, heating, electric wiring, etc., made out in such form as agreed upon by the borrower, the Agency, and the contractor. In applying for payments, the contractor should submit a statement based upon this schedule. See exhibit A of this subpart for guidance in reviewing the contractor's schedule of prices and estimating the value of the work in place. (vi) Final payment. (B) Final payment of the amount due on the contract or disbursal of the Agency loan funds where an interim loan was used will be made only upon completion of the entire contract, final inspection by the Agency, acceptance of the work by the Agency and the borrower, issuance of any and all final permits and approvals for the use and occupancy of the structure by any applicable state and local governmental authorities, and compliance by the contractor with all terms and conditions of the contract. In the event the work of construction is delayed or interrupted by reason of fire, flood unusually stormy weather, war, riot, strike, an order, requisition or regulation of any governmental body (excluding delays related to possible defects in the contractor's performance and excluding delays caused by the necessity of securing building permits or any required inspection procedures connected therewith) or other contingencies reasonably unforeseeable and beyond the reasonable control of the contractor, then with the written consent of the Agency, the date of completion of the work may be extended by the owner by the period of such delay, provided that the contractor shall give the owner and the Agency written notice within 72 hours of the occurrence of the event causing the delay or interruption. (C) Prior to making final payment on the contract when a surety bond is not used or disbursing Agency loan funds when an interim loan was used, the Agency will be provided with a Form RD 1924-9, “Certificate of Contractor's Release,” and Form RD 1924-10, “Release by Claimants.” executed by all persons who furnished materials or labor in connection with the contract. The borrower should furnish the contractor with a copy of the “Release by Claimants” form at the beginning of the work in order that the contractor may obtain these releases as the work progresses. ( 1 ( i ( ii ( iii ( 2 ( i ( ii (b) Borrower method. (1) Ways of performing the work. (i) Purchase the material and equipment and do the work. (ii) Utilize lump-sum agreements for (A) minor items or minor portions of items of development, the total cost of which does not exceed $5,000 per agreement, such as labor, material, or labor and material for small service buildings, repair jobs, or land development; or (B) material and equipment which involve a single trade and will be installed by the seller, such as the purchase and installation of heating facilities, electric wiring, wells, painting, liming, or sodding. All agreements will be in writing, however, the County Supervisor may make an exception to this requirement when the agreement involves a relatively small amount. (2) Acceptance and storage of material on site. (3) Payment for work done by the borrower method Payments for labor. (ii) Payment for equipment, materials or lump-sum agreements. (B) When an invoice is available at the time the check is drawn, the check will include a reference to the invoice number, the invoice date if unnumbered and, if necessary, the purpose of the expenditure. (C) The check number and date of payment will be indicated on the appropriate Form RD 1924-11, invoice, itemized statement of equipment or materials and/or lump-sum agreement. (D) Ordinarily, checks for equipment or materials will be made payable to the seller. Under justifiable circumstances, when the borrower has paid for equipment or materials with personal funds and furnished a paid invoice, the County Supervisor may countersign a check made payable to the borrower for reimbursement of these expenses. (E) When an invoice includes equipment or materials for more than one item of development, the appropriate part of the cost to be charged against each item of development will be indicated on the invoice by the borrower, with the assistance of the County Supervisor. (F) Payment made under lump-sum agreements will be made only when all items of equipment and materials have been furnished, labor has been performed as agreed upon, and the work has been accepted by the borrower and the Agency. (G) Each paid Form RD 1924-11, invoice, itemized statement for equipment or material and/or lump-sum agreement will be given to the borrower in accordance with the FMI. (c) Mutual self-help method. (1) The grantee acts in the same capacity as a construction manager in the group purchase of material and services. (2) The grantee has an adequate bookkeeping system approved by the District Director to assure that funds in each RH account are properly distributed and maintained. (3) The grantee receives no compensation in the way of profit or overhead for this service and all discounts and rebates received in connection with the purchase of materials or services are passed on to the participating families. (4) The grantee has a record-keeping system which shows that the costs of the materials and services were prorated to each borrower's account in relation to the actual material and service used by each borrower. (d) Owner-builder method. [52 FR 8002, Mar. 13, 1987, as amended at 55 FR 41833, Oct. 16, 1990; 60 FR 55122, Oct. 27, 1995; 61 FR 56116, Oct. 31, 1996; 71 FR 25740, May 2, 2006; 81 FR 11029, Mar. 2, 2016] § 1924.7 [Reserved] § 1924.8 Development work for modular/panelized housing units. (a) Exhibit B of this subpart applies to all loans involving modular/panelized housing units. (b) Complete drawings and specifications will be required as prescribed in exhibit C of this subpart. Each set of drawings will contain the design of the foundation system required for the soil and slope conditions of the particular site on which the modular/panelized house is to be placed. (c) The manufacturer will provide a certification (exhibit B, attachment 5 of this subpart), stating that the building has been built substantially in accordance with the drawings and specifications. The builder will also provide a certification that the onsite work complies with drawings, specifications, and the applicable development standard (eExhibit B, attachment 5 of this subpart). (d) Responsibility for field inspections will be in accordance with § 1924.9(a) of this subpart. Frequency and timing of inspections will be in accordance with § 1924.9(b) of this subpart, except that the Stage 2 inspection should be made during the time and in no case later than two working days after the crews commence work on the site and the house is being erected or placed on the foundation, to determine compliance with the accepted drawings and specifications. (e) Periodic plant inspections will be performed in accordance with paragraphs II and III of exhibit B of this subpart. Agency employees responsible for inspections in the area in which the manufacturing plant or material supply yard is located will perform such inspections as deemed necessary under paragraph III of exhibit B of this subpart. (1) Plant inspections will be made if the type construction method used could restrict adequate inspections on the building site. (2) Plant inspections will be made as often as necessary; however, after initial inspection and acceptance of the unit, only when it appears advisable to ascertain the performance and continuing stability of accepted materials and construction. (f) Only one contract will be accepted for the completed house on the site owned or to be bought by the borrower. The manufacturer of the house or the manufacturer's agent may be the prime contractor for delivery and erection of the house on the site or a builder may contract with the borrower for the complete house in place on the site. Such contracts should provide that payments will be made only for work in place on the borrower's site. (g) Payments for modular/panelized units will be made in accordance with the terms of the contract and in compliance with § 1924.6(a)(12) of this subpart. § 1924.9 Inspection of development work. The following policies will govern the inspection of all development work. (a) Responsibility for inspection. The borrower will be responsible for making inspections necessary to protect the borrower's interest. Agency inspectionsare not to assure the borrower that the house is built in accordance with the plans and specifications. The inspections create or imply no duty or obligation to the particular borrower. Agency inspections are for the dual purpose of determining that the Agency has adequate security for its loan and is achieving the statutory goal of providing adequate housing. If difficult technical problems are encountered, the County Supervisor or District Director should request the assistance of the State Office or a qualified technician from SCS or the State University Cooperative Extension Service. (b) Frequency of inspections. (1) For new buildings and additions to existing buildings, inspections will be made at the following stages of construction and at such other stages of construction as determined by the County Supervisor or District Director except as modified by paragraph (b)(3) of this section. (i) Stage 1. (ii) Stage 2. (iii) Stage 3. (2) For rehabilitation of existing buildings, inspections will be made in accordance with paragraphs (b)(1) (ii) and (iii) of this section, and at such other stages of construction to assure that construction is being performed in a professional manner and in accordance with Agency approved drawings and specifications. (3) For new construction when the structure will be covered by an insured 10-year warranty plan as described in exhibit L of this subpart, only the final inspection is required, except in cases when partial payments are required when the provisions of § 1924.6(a)(12)(v) of this subpart will be followed. (4) Arrangements should be made to have the borrower join the County Supervisor or the District Director in making periodic inspections as often as necessary to provide a mutual understanding with regard to the progress and performance of the work. (5) The Borrower should make enough periodic visits to the site to be familiar with the progress and performance of the work, in order to protect the borrower's interest. If the borrower observes or otherwise becomes aware of any fault or defect in the work or nonconformance with the contract documents, the borrower should give prompt written notice thereof to the contractor with a copy to the County Supervisor or District Director responsible for servicing the type of loan or grant involved. (6) The borrower should, when practicable, join the County Supervisor or District Director in making all final inspections. (7) When irrigation equipment and materials are to be purchased and installed, a performance test under actual operating conditions by the person or firm making the installation should be required before final acceptance is made. The test should be conducted in the presence of the borrower, a qualified technician, and, when practicable, the County Supervisor or District Director. If the Agency official is not present at the performance test, he or she should request the technician to furnish a report as to whether or not the installation meets the requirements of the plans and specifications. (8) For irrigation and drainage construction or any dwelling construction where part or all of the work will be buried or backfilled, interim inspections should be made at such stages of construction that compliance with plans and specifications can be determined. (c) Recording inspections and correction of deficiencies. (d) Acceptance by responsible public authority. (e) Acceptance by project architect. [52 FR 8002, Mar. 13, 1987, as amended at 60 FR 55122, Oct. 27, 1995; 61 FR 2899, Jan. 30, 1996; 67 FR 78327, Dec. 24, 2002] § 1924.10 Making changes in the planned development. The borrower may request changes in the planned development in accordance with this section. (a) Authority of the County Supervisor. (1) The change is for an authorized purpose and within the scope of the original proposal. (2) Sufficient funds are deposited in the borrower's supervised bank account or with the interim lender, as appropriate, to cover the contemplated changes when the change involves additional funds to be furnished by the borrower. (3) The change will not adversely affect the soundness of the operation or the Agency's security. If uncertain as to the probable effect the change would have on the soundness of the operation or Agency security, the County Supervisor will obtain advice from the District Director on whether to approve the change. (4) If a surety bond has been provided on the full amount of the construction contract, the aggregate amount of all contract change orders on Form RD 1924-7, “Contract Change Order,” or other acceptable form will not exceed 20 percent of the original contract amount. Change orders for contracts on which a surety bond has been provided which increases the original contract amount by more than 20 percent may only be approved if additional surety is provided in the full revised amount of the contract. For purposes of this paragraph, letters of credit and deposits are not considered surety. (5) Change orders for contracts on which letters of credit or deposits have been provided on the full amount of the contract which will increase the original contract amount are approved only if additional letters of credit or deposits are provided in the full revised amount of the contract. (6) Modifications have been certified in accordance with § 1924.5(f)(1)(iii) or certification has been waived in accordance with § 1924.5(f)(1)(iii)(C) of this subpart. (b) Authority of the District Director. (c) Recording changes in the planned development. (i) Any changes in labor and materials and their respective costs. (ii) Changes in facility design. (iii) Any decrease or increase in unit-price on final measurements that are different from those shown in the bidding schedule. (iv) Any increase or decrease in the time to complete the project. (2) All changes shall be recorded in chronological order as follows: (i) Contract method. Changes shall be numbered in sequence as they occur using Form RD 1924-7 with necessary attachments. (ii) Borrower method. An increase or decrease in the cash cost, extension of time, transfer of funds between items, or an addition or deletion of items of development, will be summarized on the front of Form RD 1924-1 by striking through the original figures on items and writing in the changes. Changes made in the “Development Plan” in the working drawings, or in the plans and specifications will be dated and initialed by all parties. (iii) Mutual self-help method. [See paragraph (c)(2)(ii) of this section.] (iv) Owner-builder method. [See paragraph (c)(2)(i) of this section.] (3) All changes in facility design and/or materials must be certified in accordance with § 1924.5(f)(1)(iii) of this subpart. § 1924.11 District Director's review of incomplete development. During monthly District Office work organization meetings and during regular visits to the County Office, the District Director will review the progress that is being made in completing development financed with loans within the District Director's and County Supervisor's responsibility. (a) Once each year the District Director will make a comprehensive review of all development work not completed within the time scheduled. For incomplete development financed with loan or grant funds within the responsibility of the District Director, the District Director will take the necessary actions to assure that the borrower or grantee completes the planned development. For incomplete development financed with loan or grant funds within the responsibility of the County Supervisor, the District Director will give the necessary direction to the County Supervisor to assure completion of the work. In connection with these responsibilities, the District Director will consider: (1) The current farm and home operations with respect to the need for the development as originally planned. (2) Revisions to the development plan. (3) Funds remaining in the supervised bank account. (4) Need for additional funds. (5) Personal funds that could be furnished by the borrower. (6) Estimated completion dates. (7) The borrower's attitude with respect to completing the development. (b) After a complete review of the status of development in both the District and County Offices has been made, the District Director will make a written report to the State Director which will include observations and recommendations regarding incomplete development. The report may be included in the District Director's regular report, and will include: (1) The number of cases in which borrowers have not completed their development within 9, 15 or 24 months when authorized, and also the number of cases in which funds have been exhausted and the work is incomplete. (2) The number of borrowers who have not completed their development within 3 years from the loan closing, and indicate the action that was taken in each such case. (c) If the borrower has not completed development work within 3 years after the date of loan closing and the District Director has determined that the borrower cannot or will not complete the development, the District Director will so indicate on Form RD 1924-1 and request the State Director to withdraw, for application on the loan, any unused development funds remaining in the borrower's supervised bank account, if the borrower will not sign a check for a refund to the loan account. § 1924.12 Warranty of development work. (a) Form RD 1924-19, “Builder's Warranty,” or an insured 10-year home warranty as described in exhibit L of this subpart, and normal trade warranties on items of equipment will be issued to the borrower at the completion of new building construction, dwelling rehabilitation by the contract method, all cases of newly completed and previously unoccupied dwellings or construction under conditional commitments issued to builders and sellers. (b) If the warranty is not an insured 10-year warranty, a completed Form RD 1924-19, with warranty protection for 1 year, must be provided by the builder upon final acceptance of the work by the owner and the Agency. If an insured 10-year warranty is provided, the requirements of exhibit L of this subpart apply, and a copy of the warranty insurance policy or a binder must have been received by the Agency prior to disbursement of the final payment to the builder. (c) If, for some reason, the warranty insurance policy cannot be issued, the contractor will be required to execute Form RD 1924-19 and the case will be forwarded to the State Director for consideration of debarment under the provisions of subpart M of part 1940 (available in any Agency office). The County Supervisor will assist the borrower to the extent necessary under the provisions of the warranty and subpart F of part 1924 of this chapter. (d) The County Supervisor will take the following action prior to the expiration of the first year of the warranty period: (1) As soon as the warranty has been executed, the follow-up date for sending Form RD 1924-21, “Notice of Expiration of First Year of Warranty,” which will be used for the 1 year warranty or the first year of the insured 10-year warranty, will be posted to the “Servicing and Supervision” section of the Management System card. (2) Form RD 1924-21 is provided for use in notifying the borrower of the expiration date of the first year of the warranty. This letter will be mailed to the borrower early in the second month preceding the expiration date of the first year of the warranty period. (3) If the County Supervisor or District Director does not hear from the borrower within 30 days, it can reasonably be assumed that no complaint exists or that any complaint has been satisfied unless information to the contrary has been received. (4) If the borrower notifies the Agency that any complaint has not been satisfied, an onsite inspection shall be made as early as possible, but not later than 1 month preceding the expiration date of the first year of the warranty. The results of the inspection will be recorded on Form RD 1924-12. If the borrower has complaints, the case should be handled in accordance with the provisions of subpart F of part 1924 of this chapter, or as otherwise provided in this subpart. [52 FR 8002, Mar. 13, 1987, as amended at 54 FR 14334, Apr. 11, 1989] § 1924.13 Supplemental requirements for more complex construction. This section includes additional provisions that apply to planning and conduct of construction work on all multiple family housing projects and other projects that are more extensive in scope and more complex in nature than individual housing units or farm buildings. This section will apply in addition to all other requirements contained elsewhere in this subpart. (a) Architectural services. (1) Exception. (2) Selecting the architect. (3) Architectural fees. (4) Agreement between borrower and architect. (i) The services listed in paragraph (a)(5) of this section. (ii) The amount of the fee and how it will be determined and paid. (iii) That the agreement and any amendments to the agreement shall not be in full force and effect until concurred with in writing by the State Director or the State Director's delegate, and it will contain the following provision: The Agency, as potential lender or insurer of funds to defray the costs of this agreement and without liability for any payments thereunder, hereby concurs in the form, content and the execution of this agreement. Date Agency Approval Official Title (5) Specific services. (i) Schematic design phase. (A) Consult with the applicant to obtain available information pertinent to the project requirements. (B) Consult with Agency State architect/engineer about Agency requirements and procedures. (C) Assist in preparing the project design after analyzing engineering and survey data on the site selected by applicant. (D) Prepare schematic design studies consisting of drawings and other documents illustrating the scale and relationship of project components for the applicant's approval. (E) Submit estimates of current development costs based on current area, volume, or other unit costs. (F) When the applicant and the Agency have accepted the schematic design studies and estimated development costs, the project architect may be authorized to proceed with the next phase. (ii) Design development phase. (A) Prepare the design development exhibits from the accepted schematic design studies for approval by the applicant. These exhibits should consist of drawings and other documents to fix and describe the size and character of the entire project as to structural, mechanical, and electrical systems, materials, and other essentials as appropriate. (B) Submit a further statement of probable construction cost. (C) Obtain applicant and Agency approval of drawings, specifications, and authorization to proceed with next phase. (iii) Construction documents phase. (A) Prepare the working drawings and specifications from the approved design development drawings and set forth in detail the requirements for the construction of the entire project in accordance with applicable regulations and codes; for example, necessary bidding information, assistance in preparing bidding forms, conditions of the construction contract, and the form of agreement between applicant/owner and contractor. (B) Submit a final and more comprehensive statement of probable development cost. It should show a breakdown of the estimated total development cost of the project and the various trades in enough detail for an adequate review. (C) Obtain the acceptance of the applicant and the Agency for contract documents, including approval of the final drawings and specifications and authorization to proceed. (D) Discuss with the applicant various items as they develop. (iv) Bidding or negotiation phase. (A) Assist in review and selection of bidders and submission of contract documents to selected bidders. (B) Assist in the interpretation of drawings and specifications, and other contract documents. (C) Receive and tabulate all bids. (D) Review the bids and the negotiated proposals and assist in the award and preparation of construction contracts. (v) Construction phase. (A) Attend the preconstruction conference. Advise and consult with the borrower (or the borrower's representative) and issue the borrower's instructions to the contractor. (B) Prepare change orders. (C) Keep construction accounts and work as the general administrator of the project during construction. (D) Interpret the contract documents and have the authority to reject all work and materials which do not comply. (E) Review and approve shop drawings, samples, and other submissions of the contractor for conformance with the design concept and for compliance with the contract documents. (F) Conduct periodic inspections of all phases of construction to determine compliance with the contract documents and certify as to the amount is in place and materials suitably stored on site for partial payment estimates. These inspections will be augmented, when necessary, by inspections performed by structural, mechanical, and electrical representatives. Periodic inspections should be made as frequently as is necessary to verify that the work conforms with the intent of the contract documents and that a high quality of workmanship is maintained. The State Director may require a full-time project representative on projects with a total development cost of $750,000 or more, when in the opinion of the State Director there is a need for such representative, and the State Director states the reasons for such need to the borrower. (G) Determine, based on the inspections, the dates of substantial completion and final completion; receive on the borrower's behalf all written guarantees and related documents assembled by the contractor; and issue a final certificate for payment. (vi) Warranty phase. (b) Other professional services. (1) Professional services typically include soils engineering, structural engineering, civil engineering, surveying, land planning, or professional cost estimation or certification. Fees for these services may be paid directly by the borrower or by the architect as reimbursable expenses. (2) When a project representative is utilized, unless otherwise agreed, the representative will be provided by the consulting architect/engineer. Prior to the preconstruction conference, the architect/engineer will submit a resume of qualifications of the project representative to the applicant and to the Agency for acceptance in writing. If the applicant provided the project representative, the applicant must submit a resume of the representative's qualifications to the project architect/engineer and the Agency for acceptance in writing, prior to the preconstruction conference. The project representative will attend the preconstruction conference where duties and responsibilities will be fully discussed. The project representative will work under the general supervision of the architect/engineer. The project representative will maintain a daily diary in accordance with the following: (i) The diary shall be maintained in a hard-bound book. (ii) The diary shall have all pages numbered and all entries in ink. (iii) All entries shall be on daily basis, beginning with the date and weather conditions. (iv) Daily entries shall include daily work performed, number of men and equipment used in the performance of the work, and all significant happenings during the day. (v) The diary shall be made available to Agency personnel and will be reviewed during project inspections. (vi) The project representative's diary will become the property of the owner after the project is accepted and final payments are made. (c) Drawings. (1) The drawings must be clear, accurate, with adequate dimensions and of sufficient scale for estimating purposes. (2) Construction sections and large-scale details sufficient for accurate bidding and for the purpose of correlating all parts of the work should be part of the general drawings. This is particularly important where the size of a project makes necessary the preparation of the general drawings at a scale of 1/8 (3) Mechanical and electrical work should be shown on separate plans. (4) Schedules should be provided for doors, windows, finishes, electrical fixtures, finish hardware, and any other specialty items necessary to clarify drawings. (d) Specifications. (e) Methods of administering construction. (1) Contract method. (i) Competitive bidding methods. (B) A bid bond is required from each bidder in the amount of 5 percent of the bid price as assurance that the bidder will, upon acceptance of the bid, execute the required contract documents within the time specified. (C) The construction contract will be awarded based on the contract cost, and all conditions listed in the “Invitation to Bid.” (D) If advertising does not provide a satisfactory bid in the opinion of the applicant and the Agency, the applicant shall reject all bids and will then be free to negotiate with bidders on anyone else to obtain a satisfactory contract. The following conditions must be met: ( 1 ( 2 (E) If there is no agreement by the Agency and the applicant as to the construction cost, the State Director will cease any further action on the preapplication and inform the applicant of the right to appeal in accordance with subpart B of part 1900 of this chapter. (ii) Contract documents. Item I Invitation for Bids (Form RD 1924-5) Item II Information for Bidders Item III Bid Item IV Bid Bond Item V Agreement (Construction Contract) Item VI Compliance Statement (Form RD 400-6) Item VII General Conditions Item VIII Supplemental General Conditions Item IX Payment Bond (exhibit F of this subpart) Item X Performance Bond (exhibit G of this subpart) Item XI Notice of Award Item XII Notice of Proceed Item XIII Drawings and Specifications Item XIV Addenda Item XV Contract Change Order (Form RD 1924-7) Item XVI Labor Standards Provisions [Where applicable] Item XVII Monthly Employment Utilization Report (Form CC-257) Item XVIII Partial Payment Estimate (Form RD 1924-18) Item XIX Builder's Warranty (Form RD 1924-19) (A) Substitution of term “architect” for “engineer” may be necessary on some of the forms. Other modifications may be necessary in some cases to conform to the nature and extent of the project. All such contract documents and related items will be concurred with by the State Director, with the assistance of OGC prior to the release of invitations to bid. (B) Items listed as I through IV and item XI of paragraph (e)(1)(ii) of this section may be omitted when an exception to the competitive bidding requirement is granted in accordance with paragraph (e)(1)(vii) of this section, thereby permitting a negotiated contract. (C) All negotiated contracts shall include a provision to the effect that the borrower, USDA, the Comptroller General of the United States, or any of their duly authorized representatives, shall have access to any books, documents, papers, and records of the contractor which are directly pertinent to a specific Federal loan program for the purpose of making audit, examination, excerpts, and transcriptions. (D) A provision of liquidated damages will (E) All contracts shall include a provision for compliance with the Copeland “Anti-Kickback” Act (18 U.S.C. 874) as supplemented in Department of Labor regulations (29 CFR part 3). This Act prohibits anyone from inducing any person in connection with the construction to give up any part of the compensation to which the person is otherwise entitled. (F) All contracts will contain a certification by the applicant indicating that there is not now nor will there be an identity of interest between the applicant and any of the following: Contractor, architect, engineer, attorney, subcontractors, material suppliers, equipment lessors, or any of their members, directors, officers, stockholders, partners, or beneficiaries unless specifically identified to the Agency in writing prior to the award of the contract. All contracts must also indicate that when any identity of interest exists or comes into being, the contractor agrees to have construction costs as reported to the Agency on Form 1924-13, “Estimate and Certificate of Actual Cost,” audited by a Certified Public Accountant (CPA) or Licensed Public Accountant (LPA) licensed prior to December 31, 1970, who will provide an opinion as to whether the Form RD 1924-13 presents fairly the costs of construction in conformity with eligible construction costs as prescribed in Agency regulations. (G) All contracts on any form other than Form RD 1924-6, must contain the language of clause (D) of Form RD 1924-6, which is available in all Agency offices. The language of clause (D) of Form RD 1924-6 sets forth the Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity required by Executive Order 11246, the Equal Opportunity clause published at 41 CFR 60-1.4 (a) and (b), and the Standard Federal Equal Employment Opportunity Construction Contract Specifications required by Executive Order 11246. For contract forms other than Form RD 1924-6, Form AD 767, “Equal Employment Opportunity Contract Compliance Notices,” which can be obtained from the Finance Office, should be attached and made a part of the contract. (H) All contracts will contain a provision that they are not in full force and effect until concurred with by the State Director or the State Director's delegate, in writing. Therefore, before loan closing or before the start of construction, whichever occurs first, the State Director or the State Director's delegate will concur in the contract form, content, and execution if acceptable, by including the following paragraph at the end of the contract: The Agency, as potential lender or insurer of funds to defray to costs of this contract, and without liability for any payments thereunder, hereby concurs in the form, content, and execution of this contract. Date Agency Official Title (I) The requirements of § 1924.6 (a)(11)(iv) of this subpart apply to all contracts or subcontracts in excess of $10,000. (iii) Surety. (A) In accordance with the guidance and recommendations of OMB Circulars A-102 and A-110, exceptions to the surety requirements of § 1924.6(a)(3)(ii) of this subpart will not be granted for nonprofit organization or public body applicants. (B) For loans or grants to applicants other than non-profit organizations or public bodies that are within the State Director's approval authority, the State Director may, upon request of the borrower or grantee, grant exceptions to the surety requirements in accordance with the provisions of § 1924.6(a)(3)(iii) of this subpart. Before granting such an exception, however, the State Director should be provided the following information from the proposed contractor in order to fully evaluate the experience and capabilities of the contractor: ( 1 ( 2 ( 3 ( 4 ( 5 (C) For loans or grants to applicants other than non-profit organization or public bodies that are in excess of the State Director's approval authority, the State Director may request National Office authorization to grant one of the exceptions to the surety requirements as indicated in § 1924.6(a)(3)(iii) of this subpart. The following information must be submitted with the request to the National Office: ( 1 ( 2 ( 3 ( 4 ( 5 ( 6 ( 7 (D) Adequate steps will be taken to protect the interests of the borrower and the government in accordance with the payment provisions of § 1924.6(a)(12)(i) of this subpart and any alternative as outlined in § 1924.6(a)(3)(iii)(c) of this subpart. (iv) Contract cost breakdown. (v) Cost certification. (A) Prior to the start of construction, the borrower, contractor and any subcontractor, material supplier, or equipment lessor sharing an identity of interest must submit, to the CPA or LPA, the accounting system that the borrower, contractor, subcontractor, material supplier or equipment lessor and/or the CPA or LPA proposes to set up and use in maintaining a running record of the actual cost. In order to be acceptable, the borrower must provide a written assertion that it has an accounting system that is suitably designed to provide for a trade-item basis comparison of the actual cost as compared to the estimated cost submitted on Form RD 1924-13. Costs pertaining to a specific line item will be set up in the accounting system for that particular account. For instance, only costs of materials, supplies, equipment, and labor associated with concrete will be shown in the concrete account. The accounting system must also restrict costs to those pertaining to a specific project so that costs from multiple projects will not be co-mingled. The independent CPA or LPA shall report on the borrower's assertion in accordance with the Standards for Attestation Engagements of the American Institute of Certified Public Accountants (AICPA). The borrower's and the CPA or LPA's reports on the accounting system shall be provided to the Agency by the borrower. (B) Prior to final payment to anyone required to cost certify, a trade-item breakdown showing the actual cost compared to the estimated cost must be provided to the owner and the Agency. Form RD 1924-13 is the form of comparative breakdown that must be used, and contains the certifications required of the applicant and contractor prior to final payment. The amounts for builder's general overhead, builder's profit, and general requirements, respectively, shall not exceed the amounts represented on the estimate of cost breakdown provided in accordance with paragraph (e)(1)(iv) of this section for any contractor, subcontractor, material supplier, or equipment lessor having or sharing an identity of interest with the borrower. The amounts for general overhead, builder's profit, and general requirements must be established prior to the Agency approving the construction contract and will not be changed during the course of construction. This applies to all contractors, subcontractors, material suppliers, or equipment lessors having or sharing an identity of interest with the applicant. Contract change orders will be processed to adjust the contract amount downward prior to the final payment to the contractor, if necessary, to assure that the amounts shown in the certificate of actual costs do not exceed the amounts represented in the contract cost breakdown. Reduction in the builder's profit, and general overhead if needed, will counterbalance any increase reflected in the contract costs. Any funds remaining as a result of hard cost savings will be applied to the account as an extra payment or used for eligible loan purposes approved by the Agency as long as the improvements are genuinely needed and will enhance marketability of the project. All increases or decreases of 15 percent or more in line item costs will require documentation as to the reason for the increases and/or decreases. The State Director may require documentation for increases and/or decreases of less than 15 percent, if he/she determines it necessary. This information will be required with the cost certification. (C) The CPA or LPA audit, performed in accordance with Government Auditing Standards, will include such tests of the accounting records and such other auditing procedures of the borrower and the contractor (and any subcontractor, material supplier or equipment lessor sharing an identity of interest) concerning the work performed, services rendered, and materials supplied in accordance with the construction contract he/she considers necessary to express an opinion on the construction costs as reported on Form RD 1924-13. The CPA or LPA shall also perform the additional agreed upon procedures specified by the Agency (available in any Agency office), performed in accordance with Attestation Standards, for the applicant and the contractor (and any subcontractor, material supplier, or equipment lessor sharing an identity of interest) concerning the work performed, services rendered, and materials supplied in accordance with the construction contract. (D) Upon completion of construction and prior to final payment, the CPA or LPA will provide an opinion concerning whether the construction costs, as reported on Form RD 1924-13, present fairly the costs of construction in conformity with eligible construction costs as prescribed in Agency regulations. (E) In some cases, cost certification will be obtained by the Agency through direct contract with the CPA or LPA. The borrower and his/her CPA or LPA will cooperate fully with the contract CPA or LPA by providing all documentation necessary to conduct the certification. The Agency reserves the right to determine, upon receipt of the certified Form RD 1924-13 and the auditor's report, whether they are satisfactory to the Agency. If not satisfactory to the Agency, the borrower will be responsible for providing additional information. (F) There will exist no business relationship between the CPA or LPA and the borrower except for the performance of the examination of the cost certification, accounting systems work, and tax preparation. Any CPA or LPA who acts as the borrower's accountant (performing manual or automated bookkeeping services or maintains the official accounting records) will not be the same CPA or LPA who cost certifies the project. (G) Forms RD 1944-30, “Identity of Interest (IOI) Disclosure Certificate” and RD 1944-31, “Identity of Interest (IOI) Qualification Form,” provide written notification to the borrower that willful and intentional falsification of cost certification documents will result in debarment of all violators in accordance with the provisions of RD Instruction 1940-M (available in any Agency office). These forms require the disclosure of all identities of interest associated with project construction, certify the entity's ability to provide the contracted service, and cite the penalties for failure to disclose or falsify such certification. Each applicant/borrower will be required to complete and sign the forms (available in any Agency office). (H) ( Subcontracting development work. 1 ( i ( ii ( 2 Note: ( 3 ( i ( ii (I) ( Qualified contracting entities. (vi) Method of payments. (A) If interim financing is available at reasonable rates and terms for the construction period, such financing shall be obtained. exhibit B of subpart E of part 1944 of this chapter shall be used to inform the interim lender that the Agency will not close its loan until the project is substantially complete, ready for occupancy, evidence is furnished indicating that all bills have been paid or will be paid at loan closing for work completed on the project, all inspections have been completed and all required approvals have been obtained from municipal and governmental authorities having jurisdiction over the project. Upon presentation of proper partial payment estimates approved by the applicant and accepted by the Agency, the interim lender may advance construction funds in accordance with the payment terms of the contract. It is suggested that partial payments not exceed 90 percent of the value of work in place and materials suitably stored on site. (B) When interim financing is not available, payments will be made in accordance with § 1924.6(a)(12) of this subpart. (vii) Exception to competitive bidding For all applicants. ( 1 ( 2 ( 3 ( 4 ( 5 ( 6 (B) In considering an exception to competitive bidding, the following additional steps will be taken in all cases. ( 1 ( 2 ( 3 (C) Any requests for exceptions to competitive bidding that are not covered in this section may be submitted to the National Office for consideration. (viii) Exception to contract method—public body. (A) The loan or grant is for repair or rehabilitation of existing facilities and it is not practicable to perform all work by the contract method. (B) The applicant has the managerial ability and qualified employees necessary to complete the work successfully. (C) That applicant submits a written request to the District Director indicating: ( 1 ( 2 ( 3 ( 4 ( 5 ( 6 ( 7 (D) The request, recommendations of the District Director, appropriate members of the State Office staff and the State Director and the application file will be sent to the National Office. (2) Owner-builder method. (i) The applicant's request to construct a project by the owner-builder method of construction shall be in the form of a letter giving specific and detailed information concerning the owner-builder's proposal, and the qualifications and past experience of the owner-builder. The following information must be included with the request: (A) A resume indicating the owner-builder's history, ability, and experience. (B) Dated and signed financial statements on the owner-builder's operation (including balance sheets and statements of income and expense) from current and prior years indicating the payment status of the owner-builder's accounts and any contingent liabilities that may exist. Agency personnel will be responsible for analyzing the financial statement as to the sufficiency of the owner-builder's financial capability to carry out construction. The financial strength must demonstrate the ability of the owner-builder to pay all bills prior to receiving periodic draws of funds from the lender. (C) A written, dated, and signed statement agreement to provide any funds necessary in excess of the applicant's contribution and the loan amount to complete the project. (D) A credit report (obtained at no expense to the Agency) attesting to the owner-builder's credit standing. (E) A listing of trade references that could be contacted to substantiate the owner-builder's experience and good standing. (F) Statements from other persons for whom the owner-builder has done similar work, indicating the scope of the work and that person's evaluation of the owner-builder's performance. (G) A current, dated, and signed trade-item cost breakdown of the estimated total development cost of the project which has been prepared by the applicant/owner-builder. Form RD 1924-13 will be used for this purpose. If cost certification services are required by the Agency, the cost of such services may be included in the total development cost of the project. Any subcontractor, material supplier, or equipment lessor sharing an identity of interest with the applicant/owner-builder as defined in § 1924.4(i) of this subpart must also provide a trade-item cost breakdown of the proposed amount. (H) Prior to the start of construction, the owner-builder and any subcontractor, material supplier, or equipment lessor sharing an identity of interest must submit, to the CPA or LPA, the accounting system that the owner-builder, subcontractor, material supplier or equipment lessor and/or the CPA or LPA proposes to set up and use in maintaining a running record of the actual cost. In order to be acceptable, the owner-builder must provide a written assertion that it has an accounting system that is suitably designed to provide for a trade-item basis comparison of the actual cost as compared to the estimated cost submitted on Form RD 1924-13. Costs pertaining to a specific line item will be set up in the accounting system for that particular account. For instance, only costs of materials, supplies, equipment, and labor associated with concrete will be shown in the concrete account. The accounting system must also restrict costs to those pertaining to a specific project so that costs from multiple projects will not be co-mingled. The independent CPA or LPA shall report on the owner-builder's assertion in accordance with the Standards for Attestation Engagements of the AICPA. The owner-builder's and the CPA or LPA's reports on the accounting system shall be provided to the Agency by the owner-builder. (I) A written, dated, and signed statement agreeing to permit U.S. Department of Agriculture, the Comptroller General of the United States, or any of their duly authorized representatives, to have access to any books, documents, papers, and records which are directly pertinent to the specific Federal program for the purpose of making audit, examination, excerpts and transcriptions. (ii) In order to grant an exception to the contract method of construction and proceed with the owner-builder method of construction, the State Director must determine that the following conditions exist: (A) The applicant or at least one of its principals is a fully qualified and licensed (if necessary under applicable local law) builder by profession, has adequate experience in constructing the type of units proposed as well as projects of similar size, scope, and complexity and will be able to complete the work in accordance with the Agency approved drawings and specifications. (B) Based upon the information presented in the applicant's financial statements, the applicant is presently able and is likely to continue to be able to provide any funds necessary in excess of the applicant's contribution and the loan amount to complete the project. (C) The total development cost of the project does not exceed that which is typical for similar type projects in the area. The total development cost recognized by the Agency for each individual case will be determined by the MFH Coordinator with the advice of the State Architect. (D) The owner-builder has provided sufficient information on all contracts or subcontracts in excess of $10,000 to permit compliance with § 1924.6(a)(11)(iv) of this subpart. (iii) In addition to the requirements for the State Director to authorize the owner-builder method of construction as indicated in § 1924.13(e)(2) (i) and (ii) of this subpart, the following additional steps will be taken by the State Director. (A) If, after a full review of the case documents by the appropriate members of the State Office staff, the State Director determines that the requirements have been met and the construction cost is reasonable, an exception to competitive bidding may be granted. Written documentation of the State Office review results will be placed in the application file. (B) If, after the full review by the State Office staff, the State Director determines that the construction cost is not competitive with other similar projects in construction and design being built in the area, the applicant will be requested to competitively bid the construction of the project in accordance with paragraph (e)(1)(i) of this section. (C) If there is no agreement by the Agency and the applicant as to construction cost and the applicant is not agreeable to any of the aforementioned alternatives, the State Director will cease any further action on the preapplication and inform the applicant of the right to appeal, in accordance with subpart B of part 1900 of this chapter. (iv) The development cost of the project may include a typical allowance for general overhead, general requirements and a builder's profit. These amounts may be determined by local investigation and also from HUD data for the area. The applicant/owner-builder and any subcontractors, material suppliers and equipment lessors having or sharing an identity of interest with the applicant/owner-builder may not be permitted a builder's profit, general overhead, and general requirements which exceed the amounts represented on their cost breakdown. (v) Under no circumstances will loan funds be used to pay the owner/builder or its stockholders, members, directors or officers, directly or indirectly, any profits from the construction of the project except a typical builder's fee for performing the services that would normally be performed by a general contractor under the contract method of construction. Discounts and rebates given the owner-builder in advance must be deducted before the invoices are paid. If discounts or rebates are given after the invoices are paid, the funds must be returned to the supervised bank account or applied on the interim construction loan, as appropriate. Under no circumstances will the dollar amount be placed in the reserve account. (vi) The plan and specifications must be specific and complete so that there is a clear understanding as to how the facility will be constructed and the materials that will be used. (vii) When architectural services are required by § 1924.13(a) during the construction and warranty phases they must be provided by an architect who has no identity of interest with the applicant/owner-builder. The services to be rendered during the construction and warranty phases include, but are not limited to inspections, changes in the scope of project or work to be done, administration of construction accounts, rejection of work and materials not conforming to the Agency approved drawings and specifications, and other appropriate service listed in § 1924.13(a)(5) (v) and (vi) of this subpart. (viii) The applicant/owner-builder and any subcontractor, material supplier, or equipment lessor sharing an identity of interest as defined in § 1924.4(i) of this subpart must each provide certification as to the actual cost of the work performed in connection with the construction of the project on Form RD 1924-13 prior to final payment. The construction costs, as reported on Form RD 1924-13, must be audited by a CPA, or LPA licensed on or before December 31, 1970, in accordance with Government Auditing Standards, and certain agreed upon procedures (available in any Agency office) performed in accordance with Attestation Standards. In some cases, FmHA or its successor agency under Public Law 103-354 will contract directly with a CPA or LPA for the cost certification. In that event, documentation necessary to have the costs of construction certified by an Agency contractor that they were the actual costs of the work performed, as reported on Form RD 1924-13, will be provided. Funds which were included in the loan for cost certification and which are ultimately not needed because Agency contracts for the cost certification will be returned on the loan. (A) The CPA or LPA's audit, performed in accordance with Government Auditing Standards, will include such tests of the accounting records and such other auditing procedures of the applicant/owner-builder (and any subcontractor, material supplier, or equipment lessor sharing an identity of interest) concerning the work performed, services rendered, and materials supplied in connection with the construction of the project he/she considers necessary to express an opinion on the construction costs as reported on Form RD 1924-13. Upon completion of construction and prior to final payment, the CPA or LPA will provide an opinion as to whether the construction costs as reported on Form RD 1924-13 present fairly the costs of construction in conformity with eligible construction costs as prescribed in Agency regulations. The Agency reserves the right to determine, upon receipt of the certified Form RD 1924-13 and the auditor's report, whether they are satisfactory to the Agency. At a minimum, the CPA or LPA shall also perform any additional agreed upon procedures (available in any Agency office) specified by the Agency, performed in accordance with Attestation Standards, of the owner-builder (and any subcontractor, material supplier, or equipment lessor sharing an identity of interest) concerning the work performed, services rendered, and materials supplied in connection with the construction. There will exist no business relationship between the CPA or LPA and the borrower except for the performance of the examination of the cost certification, accounting systems work, and tax preparation. Any CPA or LPA who acts as the borrower's accountant (performing manual or automated bookkeeping services or maintains the official accounting records) will not be the same CPA or LPA who cost certifies the project. (B) Prior to final payment to anyone required to cost certify, the Agency must be provided with a certification and a trade-item breakdown showing the actual cost compared to the estimated cost furnished in accordance with paragraph (e)(2)(i)(G) of this section. Form RD 1924-13 is the form of comparative breakdown that must be used, and contains the certification required of the applicant/owner-builder prior to final payment. The amounts for builder's general overhead, general requirements, and builder's profit shall not exceed the amounts represented on the estimate of cost breakdown provided in accordance with paragraph (e)(2)(i)(G) of this section for the owner-builder or any subcontractor, material supplier, or equipment lessor having or sharing an identity of interest with the applicant/owner-builder. Final payment to the owner-builder will be adjusted, if necessary, to assure that the amounts shown on the certificate of actual cost do not exceed the amounts represented on the cost breakdown. Any funds remaining as a result of hard cost savings will be applied to the account as an extra payment or used for eligible loan purposes approved by the Agency as long as the improvements are genuinely needed and will enhance marketability of the project. All increases or decreases of 15 percent or more in line item costs will require documentation as to the reason for the increases or decreases. The State Director may require documentation for increases or decreases of less than 15 percent, if he/she determines it necessary. This information will be required with the cost certification. (C) Subcontracting development work. ( 1 ( i ( ii ( 2 Note: ( 3 ( i ( ii (D) Qualified contracting entities. Contractors, subcontractors, material suppliers, and any other individual or organization sharing an identity of interest and providing materials or services for the project must certify that it is a viable, ongoing trade or business qualified and properly licensed to undertake the work for which it intends to contract. Form RD 1944-31 will be prepared and executed by the contracting entities. The form provides notification to the entities of the penalty, under law, for erroneously certifying to the statements contained therein. Debarment actions will be instituted against entities who fail to disclose an identity of interest in accordance with the provisions of RD Instruction 1940-M (available in any Agency office). (ix) Requests for payment for work performed by the owner-builder method, shall be permitted to the Agency District Director for review and approval prior to each advance of funds in order to insure that funds are used for authorized purposes. Requests for payment shall be made on Form RD 1924-18 or other professionally recognized form containing the following certification to the Agency: The undersigned certifies that the work has been carefully inspected and to the best of their knowledge and belief, the quantities shown in this estimate are correct and the work has been performed in accordance with the contract documents. (Name of Architect) By: (Title (Date) Approved by Owner's Representative: By: (Title) Accepted by Agency Representative: By: (Title) The review and acceptance of partial payment estimates by the Agency does not attest to the correctness of the quantities shown or that the work has been performed in accordance with the plans and specifications. (A) If interim financing is available at reasonable rates and terms for the construction period, such financing shall be obtained. Exhibit B of subpart E of part 1944 of this chapter shall be used to inform the interim lender that the Agency will not close its loan until the project is complete, ready for occupancy, evidence is furnished indicating that all bills have been paid for work completed on the project, all inspections have been completed and all required approvals have been obtained from any governmental authorities having jurisdiction over the project. Upon presentation of proper partial payment estimates containing an estimate of the value of work in place which has been prepared and executed by the owner-builder, certified by the applicant's architect, and accepted by the Agency, the interim lender may advance construction funds in accordance with the provisions of this section. It is suggested that the partial payment not exceed 90 percent of the value of work in place and material suitably stored on site. (B) If interim financing is not available, partial payments not to exceed 90 percent of the value of work in place and materials suitably stored on site may be made to the owner-builder for that portion of the estimated cost of development guaranteed by a letter of credit or deposits meeting the requirements of § 1924.6(a)(3)(iii) (A), (B) or (C) of this subpart. Partial payments may not exceed 60 percent of the value of work in place in all other cases. The determination of the value of work in place will be based upon an application for payment containing an estimate of the value of work in place which has been prepared and executed by the owner-builder, certified by the borrower's architect, and accepted by the Agency. Prior to receiving the first partial payment, the owner-builder must submit a schedule of prices or values of the various trades or phases of the work aggregating the total development cost of the project as required in § 1924.13(e)(2)(i) (G) and (H) of this subpart. Each application for payment must be based upon this schedule, and show the total amount owed and paid to date for materials and labor procured in connection with the project. With each application for payment, the owner-builder must also submit evidence showing how the requested partial payment is to be applied, evidence showing that previous partial payments were properly applied, and a signed statement from the applicant's attorney, title insurance company, or local official in charge of recording documents certifying that the public records have been searched and that there are no liens of record. When the District Director has reason to believe that partial payments may not be applied properly, checks will be made payable to persons who furnish materials and labor for eligible purposes in connection with the project. (x) Under no circumstances shall funds be released for final payment or to pay any items of the builder's profit until the project is 100 percent complete, ready for occupancy, and the owner-builder has completed and properly executed Form RD 1924-13 or complied with the cost certification procedures of § 1924.13(e)(2)(viii) of this subpart. [52 FR 8002, Mar. 13, 1987; 52 FR 26139, July 13, 1987, as amended at 53 FR 2155, Jan. 26, 1988; 59 FR 6882, Feb. 14, 1994; 61 FR 56116, Oct. 31, 1996] §§ 1924.14-1924.48 [Reserved] § 1924.49 State supplements. State Supplements or policies will not be issued or adopted to either supplement or set requirements different from those of this subpart, unless specifically authorized in this subpart, without prior written approval of the National Office. § 1924.50 OMB control number. The reporting and recordkeeping requirements contained in this regulation have been approved by the Office of Management and Budget (OMB) and have been assigned OMB control number 0575-0042. Public reporting burden for this collection of information is estimated to vary from 5 minutes to 4 hours per response, with an average of 37 minutes per response, including time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to U.S. Department of Agriculture, Clearance Officer, OIRM, AG Box 7630, Washington, DC 20250; and to the Office of Management and Budget, Paperwork Reduction Project (OMB #0575-0042), Washington, DC 20503. [59 FR 6885, Feb. 14, 1994] Exhibit A to Subpart A of Part 1924—Estimated Breakdown of Dwelling Costs for Estimating Partial Payments [In percent] With slab on grade With crawl space With basement 1. Excavation 3 5 6 2. Footings, foundations columns 8 8 11 3. Floor slab or framing 6 4 4 4. Subflooring 0 1 1 5. Wall framing, sheathing 7 7 6 6. Roof and ceiling framing, sheathing 6 6 5 7. Roofing 5 5 4 8. Siding, exterior trim, porches 7 7 6 9. Windows and exterior doors 9 9 8 10. Plumbing—roughed in 3 2 3 11. Sewage disposal 1 1 1 12. Heating—roughed in 1 1 1 13. Electrical—roughed in 2 2 2 14. Insulation 2 2 2 15. Dry wall or plaster 8 8 7 16. Basement or porch floor, steps 1 1 6 17. Heating—finished 3 3 3 18. Flooring 6 6 5 19. Interior carpentry, trim, doors 6 6 5 20. Cabinets and counter tops 1 1 1 21. Interior painting 4 4 3 22. Exterior painting 1 1 1 23. Plumbing—complete fixtures 4 4 3 24. Electrical—complete fixtures 1 1 1 25. Finish hardware 1 1 1 26. Gutters and downspouts 1 1 1 27. Grading, paving, landscaping 3 3 3 Total 100 100 100 Exhibit B to Subpart A of Part 1924—Requirements for Modular/Panelized Housing Units For the benefit of the Agency this exhibit prescribes evaluation, acceptance, inspection and certification procedures formodular/panelized housing units proposed for use in Agency Rural Housing programs. It applies to proposed development packages provided either under a contract between an Agency borrower and a single contractor or under a conditional commitment. This exhibit also describes the use of background information available through the Department of Housing and Urban Development (HUD) for analysis of manufactured products. This exhibit also applies to the evaluation of manufactured farm service buildings in paragraph XI, below. For the purpose of this exhibit, County Supervisor and County Office also mean District Director and District Office, respectively. I. Applicable Standards and Manuals. A. The HUD Handbook 4950.1, Technical Suitability of Products Program Technical and Processing Procedures, must be followed by housing manufacturers to obtain acceptance of their products. Acceptance documents issued by HUD include: Structural Engineering Bulletins (SEB) on a national basis, Area Letters of Acceptance (ALA) which when accepted by all Area HUD Offices in a HUD region will, in essence, become Regional Letters of Acceptance (RLA), Truss Connector Bulletins (TCB): and, Mechanical Engineering Bulletins (MEB). These documents as well as the Use of Material Bulletins (UM) and Materials Release Bulletins (MR) are addendums to the HUD Minimum Property Standards (MPS), Under handbook guidelines, HUD also examines state agency regulations concerning design, construction and labeling of modular/panelized housing units and designates those states having procedures acceptable for use under HUD programs. Modular/panelized housing produced in these states is called Category III B. All Agency Offices should maintain a close working relationship with each HUD office in their jurisdiction to assure coordination. Any deviations in structure, materials or design from HUD acceptance documents must comply with one of the other applicable development standards. II. Modular Housing Units that Require Factory Inspections. Only those types which cannot be completely inspected on site are required to obtain acceptance from HUD. Those that receive acceptance will be periodically factory inspected by HUD or HUD's designated agency, usually about every 6 months. III. Panelized Housing Units that Do Not Require Factory Inspections. A. Housing completely assembled on the building site does not require HUD acceptance. This includes housing that is manufactured but is assembled on the site such as: Precut pieces, log wall houses, trussed roof rafters or floor trusses; open panel walls, and other types that can be completely inspected on site. B. Housing that is assembled in local materials dealers' yards for moving to local sites and to be purchased by an Agency applicant, will be inspected during construction in the yard by the local Agency County representative. These units must be constructed according to the applicable development standard and not transported out of the local Agency County Office jurisdiction. The inspection must be recorded on Form RD 1924-12, “Inspection Report.” IV. Manufacturer's Actions Required for Submissions to the Agency are listed in attachment 1 to this exhibit B. V. State Agency Office Actions when Manufacturing Facilities are in its Jurisdiction. The State Office, upon receipt of manufacturer's submission, must: A. Determine that the unit structural system has been accepted by HUD as appropriate under HUD Handbook 4950.1 requirements. B. Review the thermal characteristics and approach of the calculations to determine actions to be taken in compliance with paragraph IV C of exhibit D of this subpart. C. Review the proposal for compliance with § 1924.5(d)(1) of this subpart. D. Determine that the prerequisites for consideration of acceptance by the Agency are met. The prerequisites include all of the following: 1. A current acceptance document from HUD (SEB, RLA, ALA), except for Category III housing (modular/panelized housing that does not have to have a Structural Engineering Bulletin as designated by HUD). In Category III states, the state government requirements for manufactured housing must be followed. 2. A current HUD Factory Inspection Report, Form No. 2051m, or in the case of Category III housing, a copy of the inspection report from the state government or accepted third party performing the factory inspection. Each report must be made by HUD or a HUD authorized agency, and must be no older than 6 months. 3. A letter from the manufacturer requesting a review for acceptance. Enclosed with the letter shall be all the information listed in attachment 1 to this exhibit B. E. Issue acceptance letters to the manufacturer stating the conditions of acceptance in the format of attachment 2 to this exhibit B. The letter shall have an attachment listing all models accepted in the format of attachment 3 to this exhibit B. A copy of the acceptance letter and list of models shall be sent to each County Office in the state and, when requested by the manufacturer, to each other Agency State Office in which the product is to be marketed. F. After initial review of a submission, maintain a master file of accepted manufacturers and models and review the file twice yearly to determine the currency of the factory inspection reports and HUD or state government acceptance documents. G. Notify manufacturers of overdue factory inspection reports, for acceptance of documents review and updating, using the format of attachment 4 to this exhibit B. Accompanying the notification will be a temporary acceptance sheet (Attachment 3 to this exhibit B) indicating to the manufacturer that the company models have temporary acceptance for 60 days. If the manufacturer provides evidence that a review is being processed by HUD, a maximum of an additional 90 days may be granted. Otherwise, the acceptance shall terminate on the last extension date and it will be necessary for the manufacturer to resubmit as if for initial acceptance. H. Distribute a list of added models, deleted models, or notice of deletion of any manufacturer's product to the County Offices and other State Agency Offices as necessary. I. Issue an initial supply of Manufacturer's and Builder's Certification forms (Attachment 5 to this exhibit B) to each existing and newly accepted manufacturer. Manufacturers are to duplicate this form as necessary in their market areas. J. Resolve any problems with the manufacturer, as reported by the County Office. Action may include coordination, Agency plant inspections or cancellation of acceptance letters when problems persist. VI. County Office Actions: A. When an application is received involving any of the manufacturer's products on the accepted list, the County Office Agency authorized personnel will: 1. Review the drawings and description of materials described in paragraphs A and B of attachment 1 to this exhibit B. The floor plans and elevations must be identifiable with the model listed in the accepted list issued by the State Office. 2. Require the builder/dealer or manufacturer to provide any drawings necessary to adapt the house to the site conditions where the house will be located. 3. Require site plan drawing such as those illustrated in attachments 1 and 2 to exhibit C of this subpart (available in any Agency office). 4. Inspect and identify the model delivered against the manufacturer's certification and the accepted drawings and description of materials before the unit has been set on the foundation. 5. Require the builder/dealer to certify that the work for which the builder/dealer is responsible has been erected in compliance with the applicable development standard. This certification will be completed on a copy of attachment 5 to this exhibit B, and filed in County Office case file. 6. Observe any noncompliance with the applicable development standard or with paragraphs IV and V of this exhibit B. In this respect: a. Minor noncompliance will be resolved by the manufacturer through the builder/dealer. In cases where there is no builder/dealer, the County Office may resolve such issues with the manufacturer directly. b. Noncompliance that cannot be resolved at the County Office level will be reported to the State Office. 7. Inspect manufactured housing according to § 1924.8(d) of this subpart. 8. Be aware that the accepted list may include many models from which loan applicants may choose. No changes from accepted model designs are permitted. The model selected by an applicant should be appropriate to the needs of that particular family in accordance with 7 CFR part 3550. VII. Noncompliance Issues. A. When minor issues are noted, the County Office will attempt to resolve them as described above. If they cannot be resolved locally, they will be referred to the State Office. When any issues cannot be resolved at State Office level, the National Office Program Support Staff (PSS) will be contacted for guidance. B. The National Office PSS coordinating with HUD, will take the appropriate actions to resolve the issues reported. C. Manufacturers and builder/dealers must be aware that if the Agency inspector finds any of the following conditions, the inspector may refuse to accept the construction until corrections have been made: 1. Evidence of noncompliance with any option of the method described in the HUD—SEB, RLA, or ALA. 2. Faulty shop fabrication, including surface defects. 3. Damage to shop fabricated items or materials due to transportation, improper storage, handling or assembly operation. 4. Unsatisfactory field or site workmanship. VIII. Actions by Other State Offices. When a State Office receives a copy of the accepted list from the State Office in which a manufacturing plant is located, it will: A. Maintain a file, by manufacturer, of each accepted list of models. B. Provide copies of the accepted list of models to each County Office in the State. C. Request a copy of the drawings, description of materials, and thermal calculations to determine compliance with the thermal requirements for the county in which the house is to be located according to exhibit D of this subpart. D. Check to see that County Offices within the state will act as prescribed in paragraph VI of this exhibit B. E. When two or more State Offices have different interpretations of the acceptability of a particular model, there must be an agreement between the states so that they will have the same requirements. If the states cannot agree, the National Office PSS will be consulted for guidance. IX. Subsequent Review. The Agency will make periodic reviews of houses, both site-built and houses manufactured offsite, to determine acceptability of the finished product. If, in the judgment of the Agency, the product has failed to perform satisfactorily, acceptance may be withdrawn. The State Director will notify the manufacturer and/or the builder/dealer of the reasons for the withdrawal no later than the time of withdrawal. Negotiations for corrections will be carried out by the County Office with the assistance of the State Office or National Office, as necessary. X. Materials and Products Acceptance—Material Release Bulletins, Use of Materials Bulletins, Manufacturer's Instructions. A. The Materials Release (MR) and Use of Materials Bulletins (UM) provide for the national acceptance of specific nonstandard materials and products not covered in the current HUD MPS. B. When contractors or builders intend to use products or materials not listed as approved in the MPS, the Agency personnel reviewing or concerned with the approval of construction in which the product is to be used, will require the contractor or builder to furnish a Materials Release Bulletin or Use of Materials Bulletin on the materials or products. If the product has been accepted, the supplier should be able to obtain the bulletin for the contractor or builder from the manufacturer. These bulletins describe the products or materials limitations to use, method of installing or applying, approved type of fasteners, if used, etc. and will provide the contractor with instructions as to proper installation or application. C. When Agency personnel are unfamiliar with any materials or products which have been accepted in the MPS, they will request the contractor or builder to furnish the manufacturer's instructions to assure that the materials or products are properly installed or applied. Any questions on any product that cannot be resolved in the County Office should be referred to the State Office. When the question cannot be resolved at the State Office level, the National Office PSS should be consulted for guidance. XI. Manufactured Farm Service Buildings. A. When a loan application is received that involves a manufactured building or special equipment that cannot be completely inspected on the site, the local State Land Grant University recommendations should be requested. B. When the County Office questions the advisability of making a loan on a manufactured building, the State Office should also be consulted. C. The State Office should review and make recommendations to the County Office. If doubt still exists, the National Office PSS should be consulted for guidance. Attachment 1—Required Information for Acceptance of Modular/Panelized Housing Units The manufacturer or sponsor of modular/panelized housing units wishing to participate in the Agency Rural Housing programs shall submit to the Agency State Director having jurisdiction over the state in which the proposed housing is to be manufactured, two complete sets of the information listed below for evaluation. Submissions not including all the information requested will be returned. A. Statements: 1. Name and location of organization, including titles and names of its principal officers. 2. A brief description of plant facilities. 3. Extent of intended market distribution, including a list of any other states in which units will be marketed. 4. The method of quality control during site installation. 5. A copy of the applicable current HUD Structural Engineering Bulletin (SEB), Regional Letter of Acceptance (RLA), or Area Letter of Acceptance (ALA). 6. A current factory inspection report made within 6 months by HUD or HUD authorized agency. 7. Name and address of any third party inspection agency. 8. Location of nearest assembled product for inspection. 9. Field manuals for site installation and/or set-up procedures. 10. Specifications or descriptions of materials using either Form RD 1924-2, (HUD-FHA Form 2005), “Description of Materials,” including sizes, species and grade of all building and finishing materials. All blanks should be filled and additional sheets may be attached as well as equipment manufacturer's brochures. Use an asterisk (*) to denote all items of onsite construction that will be provided by the builder-dealer. The builder-dealer must complete a form for the builder-dealer's portion of the work. Use N/A in any blank which is not applicable. 11. Names and addresses of other public and private agencies which have rendered or been asked to render a technical suitability or acceptance determination with respect to the products or structural methods employed. 12. Written certification that construction drawings and specifications conform with the applicable development standard. 13. Any other pertinent information. 14. An index of all documents submitted. B. Working Drawings. 1/2 1. Foundation and/or Basement Plan. This plan shall include anchorage details, exterior and interior dimensions, typical footings, wall thickness, pilaster sizes and locations, column or pier sizes and locations and girders required to support the structures. Show location of all equipment (furnace, water heater, laundry tubs, sump, etc.) floor drains, electrical outlets, electrical entrance panels, and all doors and windows or crawl space vents with all sizes indicated. 2. Floor Plans of all levels. Show square footage of each habitable room with square footage of each area of natural light and ventilation. In addition, a design sketch scaled properly to illustrate a typical furniture arrangement for all habitable levels is required to indicate intended occupancy functions of the design. A window and door schedule should also be provided indicating glazed size, sash size, and thermal conductance of each type. 3. All exterior elevations including opening and sizes; wall finish materials, flashing, finish grades intended, depth of footings when known, finish floor, ceiling heights, roof slope, location of downspouts, gutters, vents for both structural spaces and for equipment. Indicate construction joint locations and details of connections between sections, modules or components. 4. Building cross sections showing size and spaces of all framing members from lowest member (bottom of footing) to highest point of roof (ridge) plus; (a) Type of material and method of application of all covering materials, such as subflooring, combination subflooring and underlayment, sheathing, interior and exterior finishes; (b) Complete details including computations of trussed rafter systems with the architect/engineer's stamp of those responsible for the design. (c) Details of insulation and vapor barrier installation and attic ventilation. If the thermal characteristics to be provided are determined according to optional method for overall structure performance allowed in exhibit D of this subpart, the submission and complete engineering calculations with all details of construction shall be sent to Administrator, Attn. PSS, U.S. Department of Agriculture, Washington, DC 20250, for analysis as prescribed in paragraph IV C of exhibit D of this subpart. (d) Special details as necessary to show any special features of construction, including method of fabricating, erection, joining, and finishing of all elements; and (e) Details and sections of stairways including all critical dimensions, such as, riser, run and headroom. 5. Interior elevations of kitchen cabinets and bathroom elevations with schedule of all shelf, counter-top and drawer footage. Indicate whether kitchen cabinets are to be custom made for each model or made for any model by a cabinet manufacturing company. 6. Plumbing schematics, including pipe materials, sizes and plumbing code compliance. 7. Heating plan, including heat loss of each room, is needed for heating systems, sizings and capacities, forced air, electric baseboard, or electric space heaters and, if applicable, heat gain. For forced air systems, include supply and return duct layout and location of appropriate diffusers. 8. Electrical plan, including circuit chart or diagram. 9. Any other pertinent facts or drawings that will better explain why and how certain unusual materials or structural methods are employed. Attachment 2 John Dough Manufacturing Company, 3444 Residence Avenue, Elkton, Indiana 00051. Dear Sirs: Athough the documents submitted to this office have only received a cursory review, they appear to be in substantial compliance to qualify your firm for the type of acceptance indicated on the attached list. The acceptance being issued is subject to this letter of conditions, compliance with HUD Handbook 4950.1 Technical Suitability of Products Program Technical and Processing Procedures, compliance with Agency) Thermal Performance Construction Standards, and compliance with the conditions set forth in the HUD acceptance document, if applicable, whose number appears on the acceptance. The manufacturer and the authorized builder-dealer bear the responsibility of complying with the above, the exhibits submitted and the applicable development standards. The manufacturer and/or builder-dealer also shall: 1. Provide positive identification of the modular unit by model, date of manufacture and factory in which the unit was manufactured. 2. Furnish with each home to be financed by the Agency in ______(State)______, a written certificate (Attachment 5 to this exhibit B) endorsed by the builder-dealer certifying that all requirements have been satisfied. 3. Furnish the local Agency County Supervisor with a complete set of drawings including site plans, description of materials, structural engineering bulletins when applicable in the state, and documentation relating to the manufacture, transportation, erection, and installation for each model of modular/panelized housing to be financed in the county. Electrical, plumbing and heating plans must be furnished for each model in addition to the basic drawings. Floor plans and elevation drawings may vary from those listed in attachment 1 of exhibit B to RD Instruction 1924-A to reflect each of the manufacturer's models provided they are in compliance with the applicable development standard and the Agency Thermal Performance Construction Standards and provided they have been accepted and listed in this state's approval of manufactured structures. No field alterations to the accepted models will be allowed. 4. Furnish, when required by the County Supervisor, foundation drawings (including special foundation design considerations when the unit is to be erected in seismic zones 1, 2 or 3) adapting the modular home to any unusual site conditions needing information additional to that furnished by the standard drawings. 5. Furnish the County Office with a copy of inspection reports of the manufacturing facilities immediately after the inspection reports have been completed. 6. Allow RD personnel to inspect the manufacturing facilities at any time and furnish all Agency State Offices, where acceptance has been obtained, with a copy of any Agency inspection reports immediately after the inspection reports have been completed. 7. In the event there are major changes to the submitted drawings, obtain approval under the HUD Technical Suitability of Products Program and submit verification of this approval to the County Office for listing on the state's accepted list. Any modular home shipped with major changes incorporated, without such changes on file at the County Office may be rejected. (Add state and local requirements appropriate to this letter of conditions.) This acceptance may be subject to corrective action when deficiencies are noted in the product, field inspections, manufacturing facilities, or when there is noncompliance with the provisions of the HUD Technical Suitability of Products Program. The inclusion of these models on the accepted list is based only on the material and structural aspects of the manufactured units. Final determination of acceptability rests with RD personnel. Other factors relating to the property in its entirety such as appraisal, location, sustained market acceptance, architectural planning and appeal, thermal qualities, mechanical and electrical equipment, etc., must be considered in the final determination. Your cooperation in this acceptance program is appreciated. Sincerely, State Director Attachment 3 Date ______ File No. ______ Acceptance of Modular/Panelized Housing Units (Based on HUD Handbook 4950.1) Manufacturer: ______ Acceptance Document ______ ______ Type of Acceptance: ______ ____ Regular ______ ____ Temporary, Expires ______ Plant Locations: Date of Latest Plans Reviewed Date of Latest Factory Inspection Acceptance Document Review Date FmHA or its successor agency under Public Law 103-354 Instruction 1924-A, exhibit D Thermal Performance Construction Standards State Office Review (Exh. D, IV, C, 1, a or b) National Office Review (Exh. D, IV, C, 2) Maximum Winter Degree Days for State ______ Walls R ______ Glazing/Gross Wall Area Ratio ______% Ceilings R ______ Glazing ______ Pane(s) Floor R ______ Glazing ______ Pane(s) Insulated Door ______ Wood and Storm ______ Insulated Door ______ Wood and Storm ______ Models Accepted: Attachment 4 John Dough Manufacturing Company, 3444 Residence Avenue, Elktown, Indiana 00051. Dear Sirs: As set forth in acceptance letters issued by this office, acceptance of modular/panelized homes in this state is based on HUD's Technical Suitability of Products Program and the conditions stated in the acceptance letter. Your file has been reviewed and the following has been noted. ____An inspection report of your manufacturing facilities is overdue. Inspections are required twice yearly. The last inspection report on file at this office is dated ______. ____Your Structural Engineering Bulletin No. ____ dated ____ has not been reviewed by HUD. Reviews are generally required every three years. Temporary acceptance will be considered when you provide evidence that the review documents have been submitted to HUD. ____The drawings being used for the construction of your homes are not listed in your Structural Engineering Bulletins. Drawings used in the field should be those upon which the Structural Engineering Bulletin was issued. ____There have been ____ revisions to the development standards since ______, the date of the last drawings we have on file for your homes. It is recommended that you review the revisions to ascertain whether your drawings need to be updated. Please submit a written response and appropriate documents for the above items within ____ days, or your product will be removed from the accepted list until your firm can again qualify. If you have any problems furnishing the above within the time stated, please contact this office. We look forward to receiving the materials indicated so that your firm's listing may be continued. Sincerely, State Director Attachment 5 Certification by Manufacturer Delivery location of structure for component This is to certify that Model: ____________, Serial # ____________, manufactured ______ (date) ______, 19 __ in ____ (location) ______ and being sold to ______ (name of ____________ builder-dealer or borrower) has been manufactured in accordance with drawings and specifications on file in the Agency State Office and that the construction complies with applicable development standards, except as modified by HUD Acceptance Document (SEB, RLA, ALA,) NO. ____________, dated ________, and in compliance with the Agency Thermal Performance Construction Standards. Date Signature of Authorized Official Title Certification by Builder-Dealer ______ (Name of builder-dealer) ______ certifies that the foundation and other on-site work has been constructed in accordance with the drawings and specifications and the above structure or component has been erected, installed or applied in compliance with the applicable development standards. It is understood that the manufacturer's certification does not relieve the builder/dealer of responsibility under the terms of the builder's warranty required by the National Housing Act. Date Signature of Authorized Official Title [52 FR 8002, Mar. 13, 1987, as amended at 67 FR 78327, Dec. 24, 2002; 80 FR 9872, Feb. 24, 2015] Exhibit C to Subpart A of Part 1924—Guide for Drawings and Specifications This exhibit applies to all new buildings to be constructed, including all single family housing and related facilities and, as applicable, farm housing and farm service buildings. I. General The documents recommended in this exhibit correspond with the list of exhibits in Chapter 3 of the Department of Housing and Urban Development (HUD) “Architectural Handbook for Building Single-Family Dwellings” No. 4145.2. This exhibit may be used as a public handout and shall be used as a guide for drawings and specifications to be submitted in support of any type of application involving construction of major new buildings or extensive rehabilitation, alterations or additions to existing buildings. Descriptions of work for minor alterations or repairs need pertain only to work to be done and may be in narrative form when acceptable to the County Supervisor. Complete and accurate drawings and specifications are necessary: A. To determine the acceptability of the proposed development, B. To determine compliance with the applicable standards and codes, C. To prepare a cost estimate, and D. To provide a basis for inspections and the builder's warranty. II. Drawings for a Specific Structure Drawings for individual single dwellings shall provide at least the following: A. Plot Plan. 1/16 1. Lot and block number. 2. Dimensions of plot and north point. 3. Dimensions of front, rear and side yards. 4. Location and dimensions of garage, carport and other accessory buildings. 5. Location and sizes of walks, driveways and approaches. 6. Location and sizes of steps, terraces, porches, fences and retaining walls. 7. Location and dimensions of easements and established setback requirements, if any. 8. Elevations at the following points: (a) first floor of dwelling and floor of garage, carport and other accessory building; (b) finish curb or crown of street at points of extension of lot lines; (c) finish grade elevation at each principal corner of structure; (d) finish grade at bottom of drainage swales at extension of each side of structure as feasible. 9. The following additional elevations, as applicable, if the topography of the site or the design of the structure is such that special grading, drainage or foundations may be necessary. Examples are irregular or steeply sloping sites, filled areas on sites, or multi-level structure designs; (a) finish and existing grade elevations at each corner of the plot; (b) existing and finish grade at each principal corner of dwelling; (c) finish grade at both sides of abrupt changes of grade such as retaining walls, slopes, etc.; (d) other elevations that may be necessary to show grading and drainage. 10. Indication of type and approximate location of drainage swales. 11. When an individual water supply and/or sewage system is proposed, drawings, specifications and other items prescribed in paragraph V of this exhibit. B. Floor Plans. 1. Scale, 1:50 ( 1/4 2. Floor plan of each floor and basement, if any. Show typical furniture locations to suggest intended use of each habitable space. 3. Plan of all attached terraces and porches, and of garage or carport. 4. If dwelling is of crawl-space type, a separate foundation plan. Slab-type foundation may be shown on sections. 5. Direction, size and spacing of all floor and ceiling framing members, girders, columns or piers. 6. Location of all partitions and indication of door sizes, and direction of door swing. 7. Location and size of all permanently installed construction and equipment such as kitchen cabinets, closets, storage shelving, plumbing fixtures, water heaters, etc. Details of kitchen cabinets may be on separate drawing. 8. Location and symbols of all electrical equipment, including switches, outlets, fixtures, etc. 9. Heating system on separate drawing, or when it may be shown clearly it may be part of the floor or basement plan showing: (a) layout of system; (b) location and size of ducts, piping, registers, radiators, etc.; (c) location of heating unit and room thermostat; (d) total calculated heat loss of dwelling including heat loss through all vertical surfaces, ceiling and floor. When a duct or piped distribution system is used, calculated heat loss of each heated space is required. 10. Cooling system, on separate drawings or, as part of heating plan, floor or basement plan showing: (a) layout of system; (b) location and size of ducts, registers, compressors, coils, etc.; (c) heat gain calculations, including estimated heat gain for each space conditioned; (d) model number and Btu capacity of equipment or units in accordance with applicable Air Conditioning and Refrigeration Institute (ARI) or American Society of Refrigerating Engineers (ASRE) Standard; (e) Btu capacity and total kilowatt (KW) input at stated local design conditions; (f) if room or zone conditioners are used, provide location, size and installation details. C. Exterior Elevations. 1. Scale, 1:50 ( 1/4 1/8 2. Front, rear and both side elevations, and elevations of any interior courts. 3. Windows and doors—indicate size unless separately scheduled or shown on floor plan. 4. Wall finish materials where more than one type is used. 5. Depth of wall footings, foundations, or piers, if stepped or at more than one level. 6. Finish floor lines. 7. Finish grade lines at buildings. D. Details and Sections. 1. Section through exterior wall showing all details of construction from footings to highest point of road. Where more than one type of wall material is used, show each type. Scale 1:25 ( 3/8 2. Section through any portion of dwelling where rooms are situated at various levels or where finished attic is proposed, Scale, 1:50 ( 1/4 3. Section through stair wells, landings, and stairs, including headroom clearances and surrounding framing. Scale, 1:50 ( 1/4 4. Details of roof trusses, if proposed, including connections and stress or test data with seal of architect or engineer responsible. Scale of connections, 1:25 ( 3/8 5. Elevation and section through fireplace. Scale, 1:25 ( 3/8 6. Elevations and section through kitchen cabinets, indicating shelving. Scale, 1:50 ( 1/4 7. Sections and details of all critical construction points, fastening systems, anchorage methods, special structural items or special millwork. Scale as necesaary to provide information, 1:25 ( 3/8 III. Master Drawings for Group Structures Drawings for a group of structures (such as for several conditional commitments) may be submitted in lieu of drawings for each individual property when a number of applications are simultaneously submitted involving repetition of the same type structure. A. Master plot plan 1. Scale which will provide the following information in a clear and legible manner. 2. North point. 3. Location and width of streets and rights-of-way. 4. Location and dimensions of all easements. 5. Dimensions of each lot. 6. Location of each dwelling on lot with basic dimensions. 7. Dimensions of front, rear and side yards. 8. Location and dimensions of garage, carports and other accessory buildings. 9. Identification of each lot by number and indication of basic plan and elevation type. 10. Location of walks, driveways and other permanent improvements. B. Typical plot plan 1. Information not shown on the typical plot plan shall be included on the master plot plan. 2. Typical plot plans shall not be used for corner lots, lots with irregular boundaries, lots involving pronounced topographic variations or other lots where individual detailing is necessary. 3. Location of dwelling on typical lot and full dimensions. 4. Location and dimensions of all typical improvements, such as garage, carport, accessory buildings, walks, drives, steps, porches, terraces, trees, shrubs, retaining walls, fences, etc. C. Grading 1. Contours of existing grade at intervals of not more than 1.524 m (5 feet). Intervals less the 1.524 m (5 feet) may be required when indicated by the character of the topography. 2. Location of house and accessory buildings on each lot. 3. Identification of each lot by number. 4. Elevations in accordance with individual plot plan including bench mark and datum or, in lieu of finish grade elevations, contours of proposed finish grading may be submitted. Contour intervals selected shall be appropriate to the topography of the site. 5. Lot grading shall be shown by indicating protective slopes and approximate location of drainage swales. 6. Location of drainage outfall, if any drainage is not to a street. D. Floor plans, elevations, sections and details 1/8 IV. Specifications Form RD 1924-2, “Description of Materials,” or other acceptable and comparable descriptions of all materials forms shall be submitted with the drawings. The forms shall be completed in accordance with the instructions on Form RD 1924-2 to describe the materials to be used in the construction. A. Form RD 1924-2 may be reproduced if size, format and printed text are identical to the current official form. When it is reproduced, the following deletions must be made: 1. All lines indicating RD form numbers or other Government agency initials and/or numbers, and 2. The United States Government Printing Office (GPO) imprint and reference number. B. The material identification shall be in sufficient detail to fully describe the material, size, grade and when applicable, manufacturer's model or identification numbers. When necessary, additional sheets must be attached as well as manufacturer's specification sheets for equipment and/or special materials, such as aluminum siding or carpeting. V. Individual Water Supply and Sewage Disposal Systems When an individual water and/or sewage disposal system is proposed, the following additional information must be submitted: A. Approval and recommendations of other authorities. 1. A written opinion by the health authority having jurisdiction that the site is suitable and acceptable for the proposed systems(s) and, 2. If available, a soils report from the local USDA-Soil Conservation Service and any recommendations they may have. 3. Approval of appropriate environmental control authority. 4. A signature of the health authority on the plot plan indicating approval of the design of the proposed system. B. Plot Plan. 1. Location and size of septic tank, distribution box, absorption field or bed, seepage pits and other essential parts of the sewage disposal system and distance to all individual wells, open streams or drainageways. 2. Location of well, service line and other essential parts of the water supply system and distance to other wells and/or sewage disposal systems. 3. Exact location of individual systems (water or sewage) on adjacent properties and description of system, if available. C. Construction details of all component parts of individual water supply and sewage disposal systems shall clearly indicate material, equipment and construction. Extra sheets and drawings should be added as necessary to fully explain the proposed installation. Exhibit D to Subpart A of Part 1924—Thermal Performance Construction Standards I. Purpose This exhibit prescribes thermal performance construction standards to be used in all housing loan and grant programs. These requirements shall supersede the thermal performance requirements in any of the development standards in § 1924.4(h) of this subpart. II. Policy All loan or grant applications involving new construction (except for new Single Family Housing (SFH)) and all applications for conditional commitments (except for new SFH) shall have drawings and specifications prepared to comply with paragraphs IV A or C and IV D of this exhibit. All new SFH construction shall have drawing and specifications prepared to comply with paragraph IV F of this exhibit. III. Definitions A. British thermal unit B. Glazing C. “R” value, D. “U” value E. Winter degree-day F. CABO Model Energy Code, 1992 Edition (MEC-92) IV. Minimum Requirements A. All multifamily dwellings to be constructed with Agency loan and/or grant funds and all repair, remodeling, or renovation work performed on single family and multifamily dwellings with Agency loan and/or grant funds shall be in conformance with the following, except as provided in paragraphs IV C 3 and IV D of this exhibit: New Construction—Maximum U Values for Ceiling, Wall And Floor Section of Various Construction Winter degree days 1 Ceilings 2 Walls Floors 3 Glazing 4 Doors 5 1000 or less 0.05 0.08 0.08 1.13 1001 to 2500 .04 .07 .07 .69 2501 to 4500 .03 .05 .05 .69 Storm door if hollow core door or if over 25% glass. 4501 to 6000 .03 .05 .05 .47 Storm Door. 6001 or more .026 .05 .05 .47 Storm Door. Note. 1 2 3 Where the walls of an unheated basement or crawl space are insulated in lieu of floor insulation, the total heat loss attributed to the floor from the heated area shall not exceed the heat loss calculated for floors with required insulation. Insulation may be omitted from floors over heated basement areas or heated crawl spaces if foundation walls are insulated. The U value of foundation wall sections shall not exceed the value shown. This requirement shall include all foundation wall area, including header joist (band joist), to a point 50 percent of the distance from a finish grade to the basement floor level. Equivalent Uo configurations are acceptable. Maximum U Values of the Foundation Wall Sections of Heated Basement Not Containing Habitable Living Area or Heated Crawl Space Winter degree-days (65 F base) Maximum U value Glazing* 2500 or less No requirement 1.13 2501 to 4500 0.17 1.13 4501 or more 0.10 .69 * Glazing in heated basement shall be limited to 5 percent of floor area unless alternative Uo combination is documented. 4 5 3 4 Minimum R Values of Perimeter Insulation for Slabs-on-Grade Winter degree-days (65 F base) Minimum R values* Heated slab Unheated slab 500 or less 2.8 1000 3.5 2000 4.0 2.5 3000 4.8 2.8 4000 5.5 3.5 5000 6.3 4.2 6000 7.0 4.8 7000 7.8 5.5 8000 8.5 6.2 9000 9.2 6.8 10000 or greater 10.0 7.5 * For increments between degree days shown, R values may be interpolated. B. [Reserved] C. Optional Standards Housing design not in compliance with the requirements of paragraph IV A of this exhibit may be approved in accordance with the provisions of this paragraph. Requests for acceptance proposed under paragraph C 1 of this exhibit, must be approved by the State Director. Requests for acceptance of site-built housing proposed under paragraph C 2 of this exhibit must be approved by the Administrator. Requests for acceptance of manufactured housing proposed under paragraph C 2 of this exhibit may be approved by the State Director. All submissions of proposed options to the State Director or Administrator shall contain complete descriptions of materials, engineering data, test data (when U values claimed are lower than the ASHRAE Handbook of Fundamentals), and calculations to document the validity of the proposal. All data and calculations will be based upon the current edition of the ASHRAE Handbook of Fundamentals or other universally accepted data sources. 1. Overall “U” values for enveloped components. a. Uo (gross wall)—Total exterior wall area (opaque wall and window and door) shall have a combined thermal transmittance value (Uo value) not to exceed the values shown in attachment 1 to this exhibit D (available in any Agency office). Equation 1 in attachment 1 shall be used to determine acceptable combinations to meet the requirements. b. Uo (gross ceiling)—Total ceiling area (opaque ceiling and skylights) shall have a combined thermal transmittance value (Uo value) not to exceed the values shown in attachment 2 to this exhibit D (available in any Agency office). Equation 2 in attachment 2 shall be used to determine acceptable combinations to meet the requirements. 2. Overall structure performance. a. The methodology must be cost effective to the energy user, and must not adversely affect the structural capacity, durability or safety aspects of the structure. b. All data and calculations must show valid performance comparisons between the proposed option and a structure comparable in size, configuration, orientation and occupant usage designed in accordance with paragraph IV A. Structures may be considered for Agency loan consideration which can be shown by accepted engineering practice to have energy consumption equal to or less than those which would be attained in a representative structure utilizing the requirements of paragraph IV A. 3. Special consideration for seasonally occupied farm labor housing. a. When the period of occupancy does not encounter 500 or more heating degree-days (HDD) as determined by an average of the previous 10 years based upon local climatological data published by the National Oceanic and Atmospheric Administration, Environmental Data Service, the standards of paragraph IV A will not apply. b. When the period of use exceeds 500 HDD, the 10-year average value for the period of occupancy shall be used to determine the degree to which the thermal insulation requirements of paragraph IV A shall apply. c. If mechanical cooling is provided and the period of occupancy encounters more than 700 cooling degree-days (CDD), as determined by an average of the previous 8 years based upon local climatological data published by the same source cited in paragraph IV C3a above, the thermal insulation requirements for 1,000 and less degree-days as stated in paragraph IV A shall apply. D. Energy efficient construction practices. 1. Infiltration. (i) Caulking and sealants. Exterior joints around windows and door frames, between wall cavities and window or door frames, between wall and foundation, between wall and roof, between wall panels, at penetrations of utility services through walls, floors and roofs, and all other openings in the exterior envelope shall be caulked, gasketed, weatherstripped, or otherwise sealed. Caulking shall be silicone rubber base or butyl rubber base, conforming to Federal Specifications TT-S-1543 and TT-S-1657 respectively, or materials demonstrating equivalent performance in resilience and durability. (ii) Windows shall comply with ANSI 134.1, NWMA 15-2; the air infiltration rate shall not exceed 0.5 ft 3/min per ft. of sash crack. (iii) Sliding glass doors shall comply with ANSI 134.2, NWM 15-3; the air infiltration rate shall not exceed .5 ft 3/min per square ft. of door area. (iv) All insulation placed in open cavity walls shall be installed so that all space behind electrical switches and receptacles, plumbing, ductwork and other obstructions in the cavity are insulated as completely as possible. Insulation shall be omitted on the side facing the conditioned area; however, the vapor barrier in walls must not be cut or destroyed. b. Recommendations: (i) Wrap outside corners of wall sheathing with 15 lb. asphalt impregnated building felt before siding application. (ii) Utilize vestibules for entry doors, especially those facing into the direction of winter wind. (iii) Install plumbing, mechanical and electrical components in interior partitions as much as possible. All water piping should be insulated from freezing temperatures. 2. Heating and/or Cooling Equipment. (i) All space heating equipment (including fireplaces) requiring combustion air shall be sealed combustion types, or be located in a nonconditioned area (such as unheated basements) or adequate combustion air must be provided from outside the conditioned space. (ii) All ductwork shall be designed and installed to minimize leakage. All metal to metal connections shall be mechanically joined and taped. b. Recommendations: (i) Whenever possible, locate ductwork inside of conditioned areas in dropped ceilings, interior partitions or other similar areas. (ii) Locate outside cooling units in areas not subject to direct sunlight or heat buildup. 3. Vapor Barrier. (i) A vapor barrier at the inside of the wall or other closed envelope component must have a permeability (perm) rating less than that of any other material in the component and in no case have a perm rating greater than one. All vapor barriers must be sealed around all openings in the interior surface. Vapor barriers are not required in ceilings and floors. Continuous vapor barriers on ceilings, walls, and floors require adequate moisture vapor control in the conditioned space. (ii) All vapor producing or exhaust equipment shall be ducted to the outside and equipped with dampers. This equipment includes rangehoods, bathroom exhaust fans and clothes dryers. If a dwelling design proposes the use of windows to satisfy the kitchen and/or bathroom ventilation requirements of the development standards, the incorporation of dehumidification equipment should be considered in accordance with paragraph IV D 3 b. Exhaust of any equipment shall not terminate in an attic or crawl space. b. Recommendation: Forced air heating/cooling systems should include humidification/dehumidification systems where conditions indicate. E. [Reserved] F. New SFH construction. G. New manufactured housing. The Uo Value Zone indicated on the “Heating Certificate” for comfort heating shall be equal to or greater than the HUD Zone listed in the following table: RHS climate zones (winter degree days) FMHCSS (HUD code) Uo value zones 0-1000 1 1001-2500 2 2501-4500 2 4501-6000 3 >6000 3 Example: If a manufactured home is to be located in a geographic area having between 2501 and 4500 RHS winter degree days, the Agency will accept a Uo value Zone 2 unit or Zone 3 unit constructed to the HUD FMHCSS. If a central air conditioning system is provided by the home manufacturer, a “Comfort Cooling Certificate” must be permanently affixed to an interior surface of the unit that is readily visible. This certificate may be combined with the heating certificate on the data plate. V. General Design Recommendations: A. Orient homes with greatest glass area facing south with adequate overhangs to control solar gain during non-heating periods. Examples of proper roof overhangs are given in attachment 3 to this exhibit D (available in any Agency office). B. Arrange plantings with evergreen wind buffers on north side and deciduous trees on south. C. Whenever possible, orient entry door away from winter winds. D. Design house with simple shape to minimize exterior wall area. E. Minimize glass areas within constraints of required light and ventilation, applicable safety codes and other appropriate consideration. F. Minimize the amount of paved surface adjacent to the structure where heat gain is not desirable. VI. State Supplements: [52 FR 8002, Mar. 13, 1987, as amended at 54 FR 6874, Feb. 15, 1989; 59 FR 43723, Aug. 25, 1994; 64 FR 48085, Sept. 2, 1999; 72 FR 70221, Dec. 11, 2007] Exhibit E to Subpart A of Part 1924—Voluntary National Model Building Codes The following documents address the health and safety aspects of buildings and related structures and are voluntary national model building codes as defined in § 1924.4(h)(2) of this subpart. Copies of these documents may be obtained as indicated below: Building code Plumbing code Mechanical code Electrical code BOCA Basic/National Building Code 1 BOCA Basic/National Plumbing Code 1 BOCA Basic/National Mechanical Code 1 National Electrical Code 5 Standard Building Code 2 Standard Plumbing Code 2 Standard Mechanical Code 2 Uniform Building Code 3 Uniform Plumbing Code 3 Uniform Mechanical Code 3 CABO One and Two Family Dwelling Code 4 1 2 3 4 5 Exhibit F to Subpart A of Part 1924—Payment Bond KNOW ALL PERSONS BY THESE PRESENTS: that (Name of Contractor) (Address of Contractor) a ________________, (Corporation, Partnership or Individual) hereinafter called PRINCIPAL and (Name of Surety) hereinafter called SURETY, are held and firm bound unto (Name of Owner) (Address of Owner) hereinafter called OWNER and the United States of America acting through the Farmers Home Administration or its successor agency under Public Law 103-354 hereinafter referred to as GOVERNMENT, and unto all persons, firms, and corporations who or which may furnish labor, or who furnish materials to perform as described under the contract and to their successors and assigns in the total aggregate penal sum of ______, ______ Dollars ($______) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION is such that whereas, the PRINCIPAL entered into a certain contract with the OWNER, dated the ______________ day of ________________19____, a copy of which is hereto attached and made a part hereof for the construction of: NOW, THEREFORE, if the PRINCIPAL shall promptly make payment to all persons, firms, and corporations furnishing materials for or performing labor in the prosecution of the WORK provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery; equipment and tools, consumed or used in connection with the construction of such WORK, and for all labor cost incurred in such WORK including that by a SUBCONTRACTOR, and to any mechanic or materialman lienholder whether it acquires its lien by operation of State or Federal law; then this obligation shall be void, otherwise to remain in full force and effect. PROVIDED, that beneficiaries or claimants hereunder shall be limited to the SUBCONTRACTORS, and persons, firms, and corporations having a direct contract with the PRINCIPAL or its SUBCONTRACTORS. PROVIDED, FURTHER, that the said SURETY for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the WORK to be performed thereunder or the SPECIFICATIONS accompanying the same shall in any way affect its obligation on this BOND, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of this contract or to the WORK or to the SPECIFICATIONS. PROVIDED, FURTHER, that no suit or action shall be commenced hereunder by any claimant: (a) Unless claimant, other than one having a direct contract with the PRINCIPAL (or with the GOVERNMENT in the event the GOVERNMENT is performing the obligations of the OWNER), shall have given written notice to any two of the following: The PRINCIPAL, the OWNER, or the SURETY above named within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed. Such notice shall be served by mailing the same by register mail or certified mail, postage prepaid, in an envelope addressed to the PRINCIPAL, OWNER, or SURETY, at any place where an office is regularly maintained for the transaction of business, or served in any manner in which legal process may be served in the state in which the aforesaid project is located, save that such service need not be made by a public officer. (b) After the expiration of one (1) year following the date of which PRINCIPAL ceased work on said CONTRACT, it being understood, however, that if any limitation embodied in the BOND is prohibited by any law controlling the construction hereof, such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law. PROVIDED, FURTHER, that it is expressly agreed that the BOND shall be deemed amended automatically and immediately, without formal and separate amendments hereto, upon amendment to the Contract not increasing the contract price more than 20 percent, so as to bind the PRINCIPAL and the SURETY to the full and faithful performance of the Contract as so amended. The term “Amendment”, wherever used in this BOND and whether referring to this BOND, the contract or the loan Documents shall include any alteration, addition, extension or modification of any character whatsoever. PROVIDED, FURTHER, that no final settlement between the OWNER or GOVERNMENT and the CONTRACTOR shall abridge the right of any benficiary hereunder, whose claim may be unsatisfied. IN WITNESS WHEREOF, this instrument is executed in [number] counterparts, each one of which shall be deemed an original, this the ____ day of ______. ATTEST: Principal (Principal) Secretary (SEAL) By ______(s) (Address) Witness as to Principal (Address) Surety ATTEST: Witness as to Surety (Address) By Attorney-in-Fact (Address) Note. Date of BOND must not be prior to date of Contract. If CONTRACTOR is partnership, all partners should execute BOND. Important: Surety companies executing BONDS must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the state where the project is located. Exhibit G to Subpart A of Part 1924—Performance Bond KNOW ALL PERSONS BY THESE PRESENTS: that (Name of Contractor) (Address of Contractor) (Corportion, Partnership, or Individual) hereinafter called PRINCIPAL, and (Name of Surety) (Address of Surety) hereinafter called SURETY, are held and firmly bound unto (Name of Owner) (Address of Owner) hereinafter called OWNER, and the United States of America acting through the Farmers Home Administration or its successor agency under Public Law 103-354 hereinafter referred to as the GOVERNMENT in the total aggregate penal sum of Dollars ($______) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION is such that whereas, the PRINCIPAL entered into a certain contract with the OWNER, dated the ____ day of ______ 19 __, a copy of which is hereto attached and made a part hereof for the construction of: NOW, THEREFORE, if the PRINCIPAL shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term thereof, and any extensions thereof which may be granted by the OWNER, or GOVERNMENT, with or without notice to the SURETY and during the guaranty period and if the PRINCIPAL shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless the OWNER and GOVERNMENT from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the OWNER and GOVERNMENT all outlay and expense which the OWNER and GOVERNMENT may incur in making good any default, then this obligation shall be void, otherwise to remain in full force and effect. PROVIDED, FURTHER, that the liability of the PRINCIPAL AND SURETY hereunder to the GOVERNMENT shall be subject to the same limitations and defenses as may be available to them against a claim hereunder by the OWNER, provided, however, that the GOVERNMENT may, at its option, perform any obligations of the OWNER required by the contract. PROVIDED, FURTHER, that the said SURETY, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to WORK to be performed thereunder or the SPECIFICATIONS accompanying same shall in any way affect its obligation on this BOND, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the WORK or to the SPECIFICATIONS. PROVIDED, FURTHER, that it is expressly agreed that the BOND shall be deemed amended automatically and immediately, without formal and separate amendments hereto, upon amendment to the Contract not increasing the contract price more than 20 percent, so as to bind the PRINCIPAL and the SURETY to the full and faithful performance of the CONTRACT as so amended. The term “Amendment”, wherever used in this BOND, and whether referring to this BOND, the Contract or the Loan Documents shall include any alteration, addition, extension, or modification of any character whatsoever. PROVIDED, FURTHER, that no final settlement between the OWNER or GOVERNMENT and the PRINCIPAL shall abridge the right of the other beneficiary hereunder, whose claim may be unsatisfied. The OWNER and GOVERNMENT are the only beneficiaries hereunder. IN WITNESS WHEREOF, this instrument is executed in [Number] counterparts, each one of which shall be deemed an original, this the ____ day of ______. ATTEST: Principal (Principal) Secretary (SEAL) Witness as to Principal (Address) By __________(s) (Address) Surety ATTEST: Witness as to Surety (Address) By Attorney-in Fact (Address) Exhibit H to Subpart A of Part 1924—Prohibition of Lead-Based Paints I. Purpose This exhibit prescribes the methods to be used to comply with the requirements of the Lead-Based Paint Poisoning Prevention Act, Public Law 91-695, as amended, (42 U.S.C. 4801 et seq. II. Policy The Agency shall not permit the use of lead-based paint on applicable surfaces of any housing or buildings purchased, repaired, or rehabilitated for human habitation with financial assistance provided by this agency. Paints used on applicable surfaces shall not contain more than 0.06 percent lead by weight calculated as lead metal in the total nonvolatile content of liquid paints or in the dried film of paint already applied. III. Definitions A. Housing and buildings mean any house, apartment, or structure intended for human habitation. This includes any institutional structure where persons reside, such as an orphanage, boarding school, dormitory, day care center or extended care facility, college housing, domestic or migratory labor housing, hospitals, group practice facilities, community facilities, and business or industrial facilities. B. Applicable surfaces means all interior surfaces, whether accessible or not, and those exterior surfaces which are readily accessible to children under 7 years of age, such as stairs, decks, porches, railings, windows, and doors. C. Lead-based paint means any paint containing more than .5 of 1 percentum lead by weight, or with respect to paint manufactured after June 22, 1977, lead-based paint containing more than six one-hundredths of 1 percentum lead by weight. IV. Requirements A. All new housing and buildings shall comply with paragraph II of this exhibit H. B. For all existing housing and buildings built after C. For all existing housing or buildings built before D. For all property transfers and inventory property sales, attachments 1 and 2 to this Exhibit H (available in any Agency office) shall be handed to the purchaser by the Agency representative. E. All inventory housing or buildings built before 1950 to be repaired, renovated, or rehabilitated shall have tests for lead content, and where found to be hazardous, shall have any interior lead-based paint removed entirely. Loose or cracked surfaces shall be cleaned down to the base surface before repainting with a paint containing not more than six one-hundredths of 1 percentum lead by weight in the total nonvolatile content of the paint or the equivalent measure of lead in the dried film of paint already applied or both. Contracting officers shall include the following provision prohibiting the use of lead-based paint in all contracts and subcontracts for construction or rehabilitation of housing or buildings: Lead-Based Paint Prohibition No lead-based paint containing more than .5 of 1 percentum lead by weight (calculated as lead metal) in the total nonvolatile content of the paint, or the equivalent measure of lead in the dried film of paint already applied, or both, or with respect to paint manufactured after June 22, 1977, no lead-based paint containing more than .06 of 1 percentum lead by weight (calculated as lead metal) in the total nonvolatile content of the paint, or the equivalent measure of lead in the dried film of paint already applied, or both, shall be used in the construction or rehabilitation of residential structures under this contract or any subsequent subcontractors. Authority: This amendment is made under provisions of 5 U.S.C. 301, 40 U.S.C. 486 (c). Done at ________________, ________ this ____________ day of ____________________, 19____. ____________________________ Agency Representative V. Summary Section 401 of the Lead-Based Paint Poisoning Prevention Act as amended by the National Consumer Health Information and Health Promotion Act of 1976, Pub. L. 94-317, provides a requirement that each federal agency issue regulations and to take such other steps necessary to prohibit the use of lead-based paint on all applicable surfaces in Federal and Federally-assisted construction or rehabilitation of residential structures. The Lead-Based Paint Poisoning Prevention Act, Pub. L. 91-695, January 13, 1971, provides for grants to units of general local government in any state for the purpose of detecting and treating incidents of lead-based paint poisoning. Title II of this Act also provides for grants to the same units to identify those areas of risk including testing to detect the presence of lead-based paint on surfaces of residential housing. Exhibit I to Subpart A of Part 1924—Guidelines for Seasonal Farm Labor Housing Section 100 General—This exhibit sets forth the guidelines and minimum standards for planning and construction of new Labor Housing (LH) that will be occupied on a seasonal basis. Rehabilitation LH projects will be in substantial conformance with these guidelines and standards. A “seasonal basis” is defined as 6 months or less per year. Seasonal housing for the farmworker need not be convertible to year-round occupancy; however, the living units shall be designed for the intended type of tenant, the time of occupancy, the location, the specific site, and the planned method of operation. It is important that the design of the LH site and buildings will help to create a pleasing lifestyle which will promote human dignity and pride among its tenants. Section 200 Codes and Regulations—Compliance is required with National, state and local codes or regulations affecting design, construction, mechanical, electrical, fire prevention, sanitation, and site improvement. Section 300 Planning 300-1 Complete architectural/engineering services in accordance with this subpart will be required if an LH grant is involved or the LH loan will involve more than four individual family units, or any number of group living units, or dormitory units accommodating 20 or more persons. 300-2 Buildings and site design shall provide for a safe, secure, economical, healthful, and attractive living facility and environment suited to the needs of the domestic farm laborer and his/her family. 300-3 At least 5 percent of the individual family units in a project, or one unit, whichever is greater, and all common use facilities will be accessible to or adaptable for physically handicapped persons. This requirement may be modified if a recipient/borrower shows, through a market survey acceptable to the Agency, that a different percentage of accessible or adapatable units is more appropriate for a particular project and its service area. Site Design 301-1 General—The site design shall be arranged to utilize and preserve the favorable features and characteristics of the property and to avoid or minimize the potential harmful effect of unfavorable features. Particular attention is directed to § 1944.164 (l), (m) and (n) of subpart D of part 1944 of this chapter with reference to compliance with 7 CFR part 1970. Some of the features which must be considered are the topography, drainage, access, building orientation to sun and breezes; and advantageous features, such as vegetation, trees, good views, etc. or disadvantageous features, such as offensive odors, noxious plants, noise, dust, health hazards, etc. 301-2 Drainage—Surface and subsurface drainage systems shall be provided in accordance with the applicable development standard and subpart C of part 1924 of this chapter. 301-3 Water and Sewage Disposal—Water supply and sewage disposal installations shall comply with subpart C of part 1924 of this chapter, the applicable development standard and all governing state and local department of health requirements. Where environmentally and economically feasible, the LH facility shall connect to public water and waste disposal systems. 301-4 Electrical—Adequate electrical service shall be provided for exterior and interior lighting and for the operation of equipment. 301-5 Vehicular Access and Parking. 301-5.1 Safe and convenient all-weather roads shall be provided to connect the site and its improvements to the off-site public road. 301-5.2 All-weather drives and parking shall be provided for tenants, and for trucks and buses as needed within the site. Driveways, parking areas and walkway locations shall be in substantial conformance with the applicable development standard. 301-6 Walks: 301-6.1 Walks shall be provided for safe convenient access to all dwellings and for safe pedestrian circulation throughout the development between locations and facilities where major need for pedstrian access can be anticipated, such as laundry, parking to dwelling units, common dining rooms, etc. 301-6.2 Walkways shall be hard surface, such a concrete, asphalt, or stablized gravel, and shall be adequately drained. 301-7 Building Location: 301-7.1 Side and rear yards and distances between buildings shall conform to the applicable development standard. 301-8. Garbage and Refuse: 301-8.1 Garbage and refuse containers for individual units are required and shall be stored on durable functional racks or shall be located in a central screened area with easily cleaned surfaces. Single containers for multiple units shall be screened and in locations designed to accommodate collection vehicle functions. 301-9 Fencing: 301-9.1 Fencing used in the site design for project privacy or building security shall be harmonious in appearance with other fences and surrounding facilities which fall within the same view. 301-10 Outdoor living: 301-10.1 All public areas where pedestrian use can be anticipated after sunset shall be adequately lighted for security purposes, such as walkways to common use facilities—laundry, dining halls, building entrances, parking areas, etc. 301-11 Planting and Landscaping: 301-11.1 Planting and lawns or ground covers shall be provided as required to protect the site from erosion, control dust, for active and passive recreation areas, and provide a pleasant environment. Building Design 302-1.1 Living Units Design: 302-1.1 Individual Family Unit a. The minimum total net living unit size shall be 400 square feet. This size assumes occupancy of four persons. Units planned for additional occupants shall include an additional 60 square feet of living area per person. b. A living/dining area shall be provided to accommodate a table and chairs with adequate dining and circulation space for the intended number of occupants. The living/dining area should be combined with the kitchen area. c. The kitchen shall contain a sink, cooking range and refrigerator. A minimum free countertop area of six square feet is required. A minimum of 40 square feet of shelf area is required. d. Each bathroom shall contain adequate space and circulation for a bathtub and/or shower, water closet and lavatory. Access to the bathroom shall not be through another bedroom in dwelling units containing more than one bedroom. e. Bedroom areas separate from living areas are required. The design of the unit shall provide a minimum of 50 square feet of sleeping area per intended occupant including storage. Housing for families with children shall have a separate bedroom or sleeping area for the adult couples. A two foot by two foot shelf with a two foot long clothes hanging rod is required for each occupant. 302-1.2 Group Living Unit a. The design of the unit shall provide for a minimum of 620 square feet of total net living area for eight persons and an additional 60 square feet for each additional occupant. Additional area shall be planned for a second bathroom when anticipated occupancy will exceed eight persons, or if it will be occupied by persons of both sexes. b. The kitchen shall contain an adequate sink, cooking range, refrigerator, and space the size of which is commensurate with the needs of the group living unit. A minimum of free countertop area of eight square feet is required. A minimum of 50 square feet of shelf area is required. c. Refer to paragraph 302-1.1 b for living/dining requirements. d. Each bathroom shall contain adequate space and circulation for comfortable access to, and use of, fixtures which will include a bathtub and/or shower, water closet and lavatory. In no case shall minimum fixtures be less than that required per paragraph 302-1.3 c below. e. Refer to paragraph 301-1.1 e for bedroom requirements. 302.1.3 Dormitory Living Unit a. The design of areas for sleeping purposes, using single beds, shall provide for not less than 72 square feet per occupant including storage. b. The design of areas for sleeping purposes, using double bunk beds, shall provide for not less than 40 square feet per occupant. Triple bunk beds will not be allowed. c. The design of each dormitory building must include a water closet and a bathtub or shower for each 12 occupants, and a lavatory for each 8 persons. Urinals may be substituted for men's water closets on the basis of one urinal for one water closet, up to maximum of one-third of the required water closets. d. Adequate kitchen and dining facilities must be provided which may be in the dormitory building or detached at a distance of not more than 200 feet from the sleeping quarters. In either case, the space must contain adequate cooking ranges, refrigerators, sinks, countertop, food storage shelves, tables and chairs, and circulation space. These facilities will comply with the requirements of the “Food Service Sanitation Ordinance and Code,” part V of the “Food Service Sanitation Manual,” U.S. Public Health Service Publication 934 (1965). 302-2 Other Facilities: 302-2.1 General 302-2.2 Laundry Facilities 302-2.3 Office and Maintenance 302-2.4 Child Care Center 302-2.5 Manager's Dwelling 302-2.6 Recreation General Requirements 303-1 Materials and Construction—All materials and their installation in a LH facility shall meet the applicable development standard. Any exceptions to these requirements for materials and their installation must be obtained with the approval of the Agency National Office. Material should be selected that is durable and easily cleaned and maintained. 303-2 Fire Protection—Fire protection and egress shall be provided to comply with the applicable development standard. 303-3 Light, Ventilation, Screening—Natural light and ventilation requirements as specified in the applicable development standard shall be followed. Screening of all exterior openings is required. 303-4 Ceiling Heights—Ceiling heights of habitable rooms shall be a minimum of seven feet six inches clear, and seven feet in halls or baths in dwelling units. Public rooms shall have a minimum of eight feet clear ceiling height. Sloping ceilings shall have at least seven feet six inches for 1/2 303-5 Heating and Cooling—Heating and cooling and/or air circulation equipment shall be installed as needed for the comfort of the tenants, considering the climate and time of year the facility will be in operation. Maximum feasible use of passive solar heating and cooling techniques shall be required. All equipment installed will be in accordance with the applicable development standard to protect the health and safety of occupants. 303-6 Plumbing—Plumbing materials and their installation shall meet the applicable development standard. Hot water will be required to all living units, baths, kitchens and laundry facilities. 303-7 Insulation, Thermal Standards, Winterization—Insulation will be required where either heating or cooling is provided as per paragraph 303-5 above or when climatic conditions dictate a need for insulation. Insulation Standards will comply with exhibit D, paragraph IV C 3, of this subpart, or the state insulation standards, whichever are the more stringent. 303-8 Electrical—Electrical design, equipment and installation shall comply with the requirements of the latest edition of the National Electrical Code, and the applicable development standard for materials and their installation. Individual family units may be separately metered; other types of dwelling units may be separately metered as required. 303-9 Security and Winterization—Adequate management and physical measures will be provided as necessary to protect the facility during off-season periods, including adequate heating and insulation as required. [52 FR 8002, Mar. 13, 1987, as amended at 52 FR 19283, May 22, 1987; 58 FR 38922, July 21, 1993; 81 FR 11029, Mar. 2, 2016; 81 FR 26667, May 4, 2016] Exhibit J to Subpart A of Part 1924—Manufactured Home Sites, Rental Projects and Subdivisions: Development, Installation and Set-Up Part A—Introduction Part B—Construction and Land Development Part C—Drawings, Specifications, Contract Documents and Other Documentation Part D—Inspection of Development Work Part A—Introduction I. Purpose and Scope. This exhibit applies to all manufactured homes (except those referenced in exhibit B of this subpart) on scattered sites or in rental projects and subdivisions and covers the requirements for design and construction of manufactured home communities. The Agency may approve alternatives or substitutes if it finds the proposed design satisfactory for the proposed use, and if the materials, installation, device, arrangement, or method of work is at least equivalent to that prescribed in this exhibit considering quality, strength, effectiveness, durability, safety and protection of life and health. The Agency will require satisfactory evidence to be submitted to substantiate claims made regarding the use of any proposed alternative. II. Background. The manufactured home must be constructed in conformance with the Federal Manufactured Home Construction and Safety Standard (FMHCSS) and be permanently attached to a site-built permanent foundation which meets or exceeds the Minimum Property Standards (MPS) for One- and Two-Family Dwellings or Model Building Codes acceptable to the Agency. The manufactured home must be permanently attached to that foundation by anchoring devices adequate to resist all loads identified in the MPS. This includes resistance to ground movements, seismic shaking, potential shearing, overturning and uplift loads caused by wind. Note that anchoring straps or cables affixed to ground anchors other than footings will not 7 CFR part 1970 applies on scattered sites, in subdivisions and rental projects with regard to the development, installation and set-up of manufactured homes. To determine the level of environmental analysis required for a particular application, each manufactured home or lot involved will be considered as equivalent to one housing unit or lot. Because the development, installation and set-up of manufactured home communities, including scattered sites, rental projects, and subdivisions, differ in some requirements from conventional site and subdivision development, two of the purposes of this exhibit are to: A. Encourage economical and orderly development of such communities and nearby areas, and B. Promote the safety and health of residents of such communities. Therefore, this exhibit identifies those required standards and regulations and suggested guidelines for eliminating and preventing health and safety hazards and promoting the economical and orderly development and utilization of land for planning and development of manufactured home communities. The exhibit also provides the requirements for meeting the following: A. Resistance to Wind. B. Proper Installation. C. Proper Foundation Design. III. Definitions. Accessory Building or Structure. A subordinate building or structure which is an addition to or supplements the facilities provided by a manufactured home. Anchoring Systems. Contiguous. Federal manufactured Home Construction and Safety Standards (FMHCSS). AS EVIDENCED BY THIS LABEL NO. ________ THE MANUFACTURER CERTIFIES TO THE BEST OF THE MANUFACTURER'S KNOWLEDGE AND BELIEF THAT THIS MANUFACTURED HOME HAS BEEN INSPECTED IN ACCORDANCE WITH THE REQUIREMENTS OF THE DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT AND IS CONSTRUCTED IN CONFORMANCE WITH THE FEDERAL MANUFACTURED HOME CONSTRUCTION AND SAFETY STANDARDS IN EFFECT ON THE DATE OF MANUFACTURE. SEE DATA PLATE. Manufactured Home. Manufactured Home Community. Manufactured Home Rental Project. Manufactured Home Site. Manufactured Home Subdivisions. Permanent Perimeter Enclosure. Pier Support System. Related Facilities. Site-Built Permanent Foundation System. Set-Up. IV. Compliance with Local Regulations. V. Applicable Standards, Regulations and Manuals. 1. Federal Manufactured Home Construction and Safety Standards, 24 CFR part 3280, mandated by Congress under title VI of the Federal Housing and Community Development Act of 1974, except for § 3280.506, “Heat Loss,” of subpart F, “Thermal Protection,” to part 3280. 2. Foundation requirements of the Minimum Property Standards as adopted by the Agency or a Model Building Code acceptable to the Agency. 3. [Reserved] 4. Uniform Federal Accessibility Standard (UFAS). 5. ANSI A58.1-1982, Minimum Design Loads for Buildings and Other Structures. B. Manufactured housing to be financed by the Agency shall comply with all applicable Agency regulations, including but not limited to the following: 1. Subpart C of part 1924 of this chapter, “Planning and Performing Development Work.” 2. Subpart A of part 1924, exhibit D, “Thermal Performance Construction Standards.” 3. 7 CFR part 1970. 4. 7 CFR part 3550, “Direct Single Family Housing Loans and Grants.” 5. Subpart E of part 1944, “Rural Rental Housing Loan Policies, Procedures, and Authorizations.” The requirements of the above references have not been repeated in this exhibit. Those requirements contained above are either mandatory or minimums and every effort should be made by the applicant, builder-developer or dealer-contractor to utilize higher standards, when appropriate. Part B—Construction and Land Development I. General Acceptability Criteria. A. A manufactured home development including a site, rental project or subdivision shall be located on property designated for that use, where designations exist, by the local jurisdiction. B. Conditions of soil, ground water level, drainage, flooding and topography shall not create hazards to the property and health or safety of the residents. C. The finished grade elevation beneath the manufactured home or the first floor elevation of the habitable space, whichever is lower, must be above the 100-year flood elevation. This requirement applies wherever manufactured homes may be installed, not just in locations designated by the National Flood Insurance Program as areas of special flood hazards. The use of fill to accomplish this is a last resort. As is stated in EO 11988 and 7 CFR part 1970, it is the Agency's policy not to approve or fund any proposal in a 100-year floodplain area unless there is no practicable alternative to such a floodplain location. D. Essential services such as employment centers, shopping, schools, recreation areas, police and fire protection, and garbage and trash removal shall be convenient to the development and any site, community, or subdivision must comply with the environmental review requirements in accordance with 7 CFR part 1970. E. Manufactured home sites, rental projects and subdivisions shall not be subject to any adverse influences of adjacent land uses. An adverse influence is considered as one that is out of the acceptable level or range of a recognizable standard or where no standard exists is considered a nuisance irrespective of a site being zoned for manufactured home use. Health, safety and aesthetic consequences of location shall be carefully assessed by inspection of the site prior to selection of development. Undesirable land uses sush as deteriorated residential or commercial areas and noxious industrial properties shall be avoided to ensure compatibility. Other undesirable elements such as heavily traveled highways, airport runways, railroad, or fire hazards and other areas subject to recognizably intolerable noise levels shall be avoided. F. The requirements for streets shall be those found in subpart C of part 1924 of this chapter. G. The site design and development shall be in accordance with sound engineering and architectural practices and shall provide for all utilities in a manner which allows adequate, economic, safe, energy efficient and dependable systems with sufficient easements for their required installation and maintenance. H. Utilities for each manufactured home site, rental housing project or subdivision shall be designed and installed in accordance with subpart C of part 1924 of this chapter; and the State health authority having jurisdiction, and all local laws and regulations requiring approval prior to construction. I. Exhibit C, section V of this subpart shall be complied with by the applicant, dealer-contractor or builder-developer for manufactured home projects with individual water supply and sewage disposal systems. This exhibit shall be used by the Agency County Supervisors, District Directors, and State Directors in reviewing submissions. J. During the planning, design, and construction of the foundation system and/or perimeter enclosure, provisions shall be made for the installation and connection of on-site water, gas, electrical and sewer systems, which are necessary for the normal operation of the manufactured home. Water and sewer system hookups shall be adequately protected from freezing. II. Development on Scattered Sites and in Subdivisions. 1. Be erected with or without a basement on a site-built permanent foundation that meets or exceeds applicable requirements of the Agency/MPS for One- and Two-Family Dwellings or Model Building Codes acceptable to the Agency; 2. Be permanently attached to that foundation by anchoring devices adequate to resist all loads identified in the Agency adopted MPS (this includes resistance to ground movements, seismic shaking, potential shearing, overturning and uplift loads caused by wind, etc.); 3. Have had the towing hitch or running gear, which includes tongues, axles, brakes, wheels, lights and other parts of the chassis that operate only during transportation removed; 4. Have any crawl space beneath the manufactured home properly ventilated and enclosed by a continuous permanent perimeter enclosure. If it is not the supporting foundation, designed to resist all forces to which it may be subject without transmitting to the building superstructure movements or any effects caused by frost heave, soil settlement (consolidation), or shrinking or swelling of expansive soils; and be constructed of materials that conform to Agency adopted MPS requirements for foundations; 5. Have the manufactured home insulated to meet the energy conserving requirements contained in exhibit D of this subpart; 6. Have a manufactured home site, site improvements, and all other features of the mortgaged property not addressed by the Federal Manufactured Home Construction and Safety Standards, meet or exceed applicable requirements of this subpart and subpart C of part 1924 of this chapter, the Agency adopted MPS except paragraph 31-2.2 or a Model Building Code acceptable to the Agency; 7. Have had the manufactured unit itself braced and stiffened where necessary before it leaves the factory to eliminate racking and potential damage during transportation; and 8. Be eligible for financing in accordance with the requirements of either section 502, or section 515 of the Agency's Housing Program, for which purpose the beginning of construction will be the commencement of on-site work even though the manufactured home itself may have been produced and temporarily stored prior to the date of application for financing. B. Site Planning and Development. 1. Arrangement of Structures and Facilities. 2. Adaptation to Site Assets. 3. Site Plan. 4. Lot Size. C. Foundation Systems, Anchoring and Set-up. 1. The foundation system shall be constructed in accordance with this subpart and one of the following: (a) The foundation system included in the manufacturer's installation instructions meeting Agency/MPS requirements, (b) the Agency/MPS 4900.1, which specifies performance requirements for foundations in section 600 “General” and paragraph 601-16 “Foundations,” or (c) an FmHA or its successor agency under Public Law 103-354 recognized model building code. 2. The manufactured home permanent foundation system shall constitute a permanent load bearing support system for the manufactured home. The manufacturer or applicant shall be permitted to design or specify the installation of a foundation system which meets Agency/MPS design requirements for foundations and the general requirements above. 3. The applicant's responsibility for proper design and installation of the permanent foundation system, anchoring and set-up shall be in accordance with § 1924.5(f)(1), of this subpart. 4. The builder/developer of the manufactured home property, for proposed construction, shall submit with the application for financing by the applicant or for a conditional commitment design calculations, details and drawings for the installation, anchorage and construction of permanent foundation and perimeter enclosure to be used. III. Rental Housing Project Development. B. Site Planning and Development. C. Foundation Systems, Anchoring and Set-up. IV. Accessory Structures and Related Facilities. General. 1. Accessory structures and related facilities shall be planned, designed and constructed in accordance with the applicable provisions of this subpart; the Agency/MPS; and local criteria of the authority having jurisdiction. 2. Accessory structures and related facilities shall be designed in a manner that will eliminate and prevent health and safety hazards and enhance the appearance of the manufactured home and its environment. 3. Accessory structures and related facilities shall not obstruct required openings for light and ventilation of the manufactured home and shall not hamper installation and utility connections of the unit. B. Accessory Structures. 2. Accessory structures shall be carefully designed and constructed for the convenience and comfort of the manufactured home occupant. These features significantly affect the visual appearance of the community and influence livability. C. Related Facilities (Rental Housing Projects). 2. Related facilities built on-site must meet the Agency/MPS and subpart A of part 1924 of this chapter or other building codes approved by by the Agency. 3. Workmanship shall be of a quality equal to good standard practice. Material shall be of such kind and quality as to assure reasonable durability and economy of maintenance, all commensurate with the class of building under consideration. 4. All members and parts of the construction shall be properly designed to carry all loads imposed without detrimental effect on finish or covering materials. 5. The structure shall be adequately braced against lateral stresses and each member shall be correctly fitted and connected. 6. Adequate precautions shall be taken to protect against fire and accidents. 7. All related facilities which require accessibility to the handicapped must comply with the Uniform Federal Accessibility Standard (UFAS). V. Fire Protection and Safety. B. All fire detection and alarm systems, and water supply requirements for fire protection for manufactured communities shall be in accordance with the local authority responsible for providing the necessary fire protection services. C. Any portion of a manufactured home shall not be closer than the local separation requirements of the development standard for side to side, end to end, and end to side siting. If the exposed composite wall and roof of two or more manufactured homes are proposed to be joined they shall be without openings and constructed of materials which will provide a minimum one-hour fire rating each, or the manufactured homes are separated by a one-hour fire rated barrier designed and approved for such installation and permitted by the authority having jurisdiction. D. Manufactured homes shall not be positioned vertically (stacked) with one over the other in whole or in part without the specific approval of the authority having jurisdiction. Part C—Drawings, Specifications, Contract Documents and Other Documentation I. General. A. The documents recommended shall be used as a guide for drawings and specifications to be submitted in support of all types of loan and/or grant applications involving manufactured homes. Adequate and accurate drawings and specifications are necessary to: 1. Determine the acceptability of the physical environment and improvements, 2. Determine compliance with the applicable standards and codes, 3. Review cost estimates, and 4. Provide a basis for financing, inspections, and the warranty. B. Detailed floor plans, drawings and specifications are not required for any manufactured home to be installed on a scattered site, in a subdivision or rental housing project. However, a schematic floor plan should be submitted by the applicant when applying for Agency financing. The unit must have an affixed label as specified in exhibit D of this subpart indicating that the unit is constructed to the Agency thermal requirements for the appropriate winter degree days. This will indicate that the manufacturer certifies that the unit has been properly inspected and it meets the Agency Thermal Performance Construction Standard. C. For proposed construction, the builder or dealer-contractor shall submit with the loan or grant application design calculations, details and drawings for the installation, anchorage and construction of the permanent foundations and perimeter enclosure to be used. Drawings and specifications for foundation systems will be reviewed and examined by either the Agency County Supervisor, District Director, or State Architect/Engineer for foundation support locations, loads and connection requirements specified by the manufacturer as a basis for evaluating foundation compliance with the Agency/MPS or Model Building Code, and for determining design suitability for soil conditions. Drawings and specifications will also be examined by the Agency to determine compliance with all other on-site features not covered by the FMHCSS. D. Foundation design sections and details of all critical construction points systems, anchorage methods, and structural items shall be scaled as necessary to provide all appropriate information 1:30 (3/8″ = 1′-0″) minimum. II. Scattered Sites. III. Subdivisions. IV. Rental Housing Projects. V. Specifications. B. The material identification information shall be in sufficient detail to fully describe the material, size and grade. Where necessary, additional sheets shall be attached as well as manufacturer's specification sheets for equipment and/or special materials. Part D—Inspection of Development Work I. General. II. Inspections. The Stage 2 inspection for manufactured homes will be made within two working days after erection or placement on the foundation to determine compliance with accepted installation drawings and specifications for installation and set-up and to verify that the correct unit is on the site. Stages 2 and 3 inspections for manufactured homes may be combined when authorized by the State Director. B. The borrower will join the County Supervisor or the District Director in making periodic inspections as often as possible and always for the final inspection. C. The borrower should be encouraged to make enough periodic visits to the site to be familiar with the progress and performance of the work in order to protect the borrower's interest. If the borrower observes or otherwise becomes aware of any fault or defect in the work or nonconformance with the contract documents, the borrower should give prompt written notice thereof to the dealer-contractor and a copy of the notice to the appropriate County Supervisor or District Director. D. During inspection, it will generally be infeasible to determine whether a manufactured unit erected on a site was properly braced and stiffened during transportation. Inspectors should examine these units to determine that there is no obvious damage or loosening of fastenings that may have occurred during transportation. The dealer-contractor must warrant these units against such damage, which should protect the Agency's interest. III. Warranty Plan Coverage. [51 FR 41603, Nov. 18, 1986, as amended at 52 FR 19283, May 22, 1987; 53 FR 2156, Jan. 26, 1988; 67 FR 78327, Dec. 24, 2002; 81 FR 11029, Mar. 2, 2016] Exhibit K to Subpart A of Part 1924—Classifications for Multi-Family Residential Rehabilitation Work I. General This exhibit distinguishes between what the Agency considers maintenance and repair work, moderate rehabilitation and substantial rehabilitation. In all cases, the building or project to be rehabilitated shall be structurally sound. The applicant shall have a structural analysis of the existing building made to determine the adequacy of all structural systems for the proposed rehabilitation. II. Definitions Maintenance and Repair—Work involved in the selective replacement and general maintenance and repair of certain materials, appliances or components of an existing residential building. Moderate Rehabilitation—All work directly involved in the rearrangement of interior space, the replacement of finish materials or components of the electrical, plumbing, heating or conveyance systems of an existing multi-family residential building. Work and improvements are considered to be more than routine maintenance and repair. Substantial Rehabilitation—All work directly involved in the rearrangement of interior space that involves alteration of load bearing partitions and columns; the replacement of the electrical, plumbing, heating or conveyance systems; and the addition to and/or major conversion of existing multi-family residential buildings or other building structures. Moderate rehabilitation and repair shall not be limited to building changes for cosmetic or convenience purposes. In all cases moderate rehabilitation shall involve a minimum of three (3) components of building rehabilitation listed as moderate. Unless combined with other improvements in a project that are considered to be moderate or substantial rehabilitation the items identified as maintenance and repair are considered to be cosmetic and convenience changes. When a rehabilitation project consists of both moderate and substantial rehabilitation components, those substantial rehabilitation components shall be in accordance with the Agency's development standards and local codes and regulation requirements. Where the majority of project components of building rehabilitation are considered substantial the project shall be considered in the substantial rehabilitation category. Those site components of rehabilitation such as landscaping, grading, drainage, fencing, parking areas, recreation areas, water and waste disposal systems, etc., whether considered either maintenance and repair, moderate rehabilitation or substantial rehabilitation shall be in accordance with the Agency's development standards for site development work; all local codes and regulation requirements; and sound engineering and architectural practices. Any alteration of a structure listed or eligible for listing on the National Register of Historic Places may be considered either moderate or substantial rehabilitation; however, it shall conform first to the Secretary of the Interior's Standards for Rehabilitation and Guidelines for Rehabilitating Historic Buildings and then to the Agency's requirements. In cases where the Secretary of the Interior's standards cannot be met, rehabilitation will conform to the agreed upon approaches, treatments and techniques resulting from the consultation process between the Agency, the borrower, the State Historic Preservation Officer and the Advisory Council of Historic Preservation. III. Components of Multi-Family Building Rehabilitation The components of multi-family building rehabilitation necessary and generally considered by the Agency to be either maintenance and repair, moderate rehabilitation or substantial rehabilitation include but are not limited to those listed in the following chart. Components of Multi-Family Building Rehabilitation Components Maintenance and repair Moderate rehabilitation Substantial rehabilitation Air conditioning o Appliance replacement or repair o Cabinet replacement or repair o Carpeting o Caulking o Ceiling framing o Clothes closets or shelving improvements o Door repair o Drywall repair o Gutters and downspouts o Hardware replacement or repair o Kitchen cabinet improvement o Lighting fixture replacement or repair o Mail boxes o Painting o Paneling o Partition repair o Roof repair o Signage o Stair repair o Tile work o Wallpapering o Window shades and curtains o Door replacement o Drywall replacement o Elevator components replacement o Exterior entrance redesign, relocation o Finish flooring materials o Flashing o Furnace replacement o Gas pipes o Insulation o Lath and plaster replacement o New shingles or roof replacement o Partition (nonbearing) replacement, or relocation o Plumbing fixture replacement o Pointing o Porch and steps alterator or replacement o Stair replacement, or relocation o Storm windows and weatherstripping o Subfloor material replacement o Trim—exterior and interior o Window replacement o New or alteration to the: Mechanical system o Soil pipes o Vent pipes o Waste pipes o Alteration or replacement of structural components: Beams Chimneys and vents o Columns and post o Electrical service—replacement or new o Elevator replacement o Exterior walls o Floor construction o Footing o Foundation wall o Foundation waterproofing o Interior walls o Moderate repair and rehabilitation shall not be limited to building changes for cosmetic purposes. In all cases moderate rehabilitation shall involve a minimum of three (3) components of building rehabilitation listed as moderate. Unless combined with other improvements in a project that are considered to be moderate or substantial rehabilitation the items identified as maintenance and repair are considered to be cosmetic and convenience changes. Exhibit L to Subpart A of Part 1924—Insured 10-Year Home Warranty Plan Requirements I. Purpose In recent years, numerous third-party home warranty plans have been developed offering new homeowners varying degrees of protection against builder default and/or major structural defects in their homes. This exhibit establishes the criteria and procedures by which a warranty plan is found acceptable for new construction of single family homes financed by the Agency. An acceptable warranty plan will: A. Assure that the Agency borrowers receive adequate warranty coverage, B. In certain circumstances, eliminate the requirement for the Agency personnel to make the first two construction inspections, and C. Permit a loan up to the market value of the security (less the unpaid principal balance and past due interest of any other liens against the security), even though the Agency personnel may not have performed period inspections during construction. II. Types of Warranty Companies A. An insured warranty company is underwritten by an insurance carrier, licensed to operate as an insurer by the states where the warranty company plans to operate, and has an acceptable rating from a nationally recognized rating company such as A.M. Best Company. B. A risk retention group is an insurer which is licensed in one state and is authorized, under the Products Liability Risk Retention Act of 1981, to issue its policies in all states. This authority is not challenged by the Agency; however, there remains some question as to the legal propriety of a 10-year insured warranty insurer to be a risk-retention group. If at some future time any state insurance commission or regulatory agency challenges the legal authority of such group, the Agency will reconsider its acceptance of the group. C. Individual state warranty plans, such as that offered by the State of New Jersey, are backed by the full faith and credit of the state government. III. Plan Requirements To be considered acceptable, a warranty plan must include the following features: A. The entire cost (fee, premium, etc.) of the coverage is prepaid and coverage automatically transfers to subsequent owners without additional cost. B. The coverage is not cancellable by the warrantor (builder), warranty company or insurer. C. The coverage age includes at least the following: (1) For one year from the effective date, any defects caused by faulty workmanship of defective materials. (2) During the second year after the effective date, the warranty continues to cover the wiring, piping and duct work of the electrical, plumbing, heating and cooling systems, plus the items in (3). (3) During the third through the tenth years, the warranty continues to cover major structural defects. A major structural defect is actual damage to the load-bearing portion of the home including damage due to subsidence, expansion or lateral movement of the soil (excluding movement caused by flood or earthquake) which affects its load-bearing function and which vitally effects or is imminently likely to affect use of the home for residential purposes. D. A system is provided for complaint (claims) handling which includes a conciliation and, if necessary to resolve matters in dispute, arbitration arranged by the American Arbitration Association or similar organization. E. A construction inspection plan is required if the Agency is to eliminate the first two Agency inspections or permit a full market value loan when Agency inspections are not conducted. IV. Information for Review A. Companies submitting warranty plans for a determination of acceptability must support requests with the following information. (1) Evidence that the insured warranty company has met the applicable state licensing and/or regulatory requirements in the state in which the company plans to operate. (2) Evidence that the insurance carrier underwriting the warranty plan is licensed to operate as an insurer in the states in which the company plans to operate and has an acceptable rating from a nationally recognized company such as A.M. Best Company. (3) State warrenty plan agencies will provide evidence that the plan is backed by the full faith and credit of the state. (4) A full description of the warranty plan including information on the fees, builder and home registration procedures, required construction standards, construction inspection procedures, coverage provided and claims procedures. (5) A sample copy of the warranty information and/or policy which is provided to the homeowner. (6) Suggested means by which Agency field offices can readily assure that the builder is a member in good standing prior to loan approval and that a warrant will be issued upon the completion of construction prior to the final release of funds. B. Submission and Acceptance: (1) Insured warranty companies, except those operating as risk retention groups, and state warranty plan agencies will submit their requests and supporting information to the Agency State Director in the state in which they plan to operate. State Directors will determine the acceptability of insured warranty plans and state warranty plans in their jurisdictions, notify the company or agency of the decision in writing and notify field offices by issuance of a State Supplement including the names and addresses of acceptable warranty companies and any other pertinent information. (2) Warranty companies claiming authority as risk retention groups will submit their requests and supporting information including certification that it has complied with all requirements of the Products Liability Risk Retention Act of 1981 (Pub. L. 97-45) and information indicating the state in which it is licensed, information to the Agency National Office, Single Family Housing Processing Division. The National Office will determine the acceptability of the warranty of a risk retention group, notify the company of the decision in writing and notify field offices by issuance of an attachment to this exhibit. V. Warranty Performance A. County Supervisors will report inadequate warranty performance through their District Director to the State Director. State Directors will review the situation, assist in resolving any problems and, if necessary, initiate action under subpart F of part 1942 of this chapter. State Directors will inform, by memorandum, the Director, Single Family Housing Processing Division, National Office, of any problems with warranty performance and if any debarment action is initiated. B. State Directors will annually monitor each warranty company and/or its insurer to assure continued compliance with state licensing and/or regulatory requirements. Attachment 1—Acceptable Warranty Companies The warranty companies listed below claim authority to act as a risk retention group under the Products Liability Risk Retention Act of 1981 and as such, to operate in all States to provide 10-year home warranties. This authority remains subject to future challenges by any State insurance commissioner or regulatory agency; however, until such challenge is made, the Agency accepts their warranty. Name and address Area of operation Home Owners Warranty Corporation/HOW Insurance Company, 11 North Glebe Road, Arlington, Virginia 22201, (703) 516-4100 All States. Home Buyers Warranty, 89 Liberty Street, Asheville, North Carolina 22801, Telephone: (704) 254-4478 All States. Residential Warranty Corporation, P.O. Box 641, Harrisburg, Pennsylvania 17108-0641, Telephone: 1-800-247-1812 All States. Manufactured Housing Warranty Corporation, P.O. Box 641, Harrisburg, Pennsylvania 17108-0641, Telephone: 1-800-247-1812 All States. [52 FR 8002, Mar. 13, 1987, as amended at 56 FR 29167, June 26, 1991] Subpart B [Reserved] Subpart C—Planning and Performing Site Development Work Source: 60 FR 24543, May 9, 1995, unless otherwise noted. § 1924.101 Purpose. This subpart establishes the basic Rural Housing Service (RHS) policies for planning and performing site development work. It also provides the procedures and guidelines for preparing site development plans consistent with Federal laws, regulations, and Executive Orders. § 1924.102 General policy. (a) Rural development. (1) Recognize community needs and desires in local planning, control, and development. (2) Recognize standards for building-site design which encourage and lead to the development of economically stable communities, and the creation of attractive, healthy, and permanent living environments. (3) Encourage improvements planned for the site to be the most cost-effective of the practicable alternatives. Encourage utilities and services utilized to be reliable, efficient, and available at reasonable costs. (4) Provide for a planning process that will consider impacts on the environment and existing development in order to formulate actions that protect, enhance, and restore environmental quality. (5) No site will be approved unless it meets the requirements of this part and all state and local permits and approvals in connection with the proposed development have been obtained. (b) Subdivisions. (c) Development related costs Applicant. (2) Developer. § 1924.103 Scope. This subpart provides supplemental requirements for Rural Rental Housing (RRH) loans, Rural Cooperative Housing (RCH) loans, Farm Labor Housing (LH) loans and grants, and Rural Housing Site (RHS) loans. It also provides a site development standard, as indicated in exhibit B of RD Instruction 1924-C, which supplements this subpart to provide the minimum for the acceptability of development. All of this subpart applies to Single Family Housing unless otherwise noted. All of this subpart also applies to Multiple Family Housing except §§ 1924.115 and 1924.120, and any paragraph specifically designated for Single Family Housing only. In addition, RHS will consult with appropriate Federal, state, and local agencies, other organizations, and individuals to implement the provisions of this subpart. § 1924.104 Definitions. As used in this subpart: Applicant. Community. Developer. Development. Multiple Family Housing. Single Family Housing. Site. Site approval official. Street surfaces. (1) Hard surface (2) All-weather Subdivision. § 1924.105 Planning/performing development. (a) General. (1) [Reserved] (2) Technical Services. (i) [Reserved] (ii) An applicant or developer for a Multiple Family Housing project or a Single Family Housing site which requires technical services under § 1924.13(a), must contract for the technical services of an architect, engineer, land surveyor, landscape architect, or site planner, as appropriate, to provide complete planning, drawings, and specifications. Such services may be provided by the applicant's or developer's “in house” staff subject to RHS concurrence. Technical services must be performed by professionals who are qualified and authorized to provide such services in the state in which the project would be developed. All technical services must be provided in accordance with the requirements of professional registration or licensing boards. At completion of all construction or completion of a phase or phases of the total project, the persons providing technical services under this section must notify the RHS field office in writing that all work has been completed in substantial conformance with the approved plans and specifications. (iii) For developments not specifically required to have technical services under paragraph (a)(2)(ii) of this section, such services may be required by the state director when construction of streets or installation of utilities is involved. (3) Drawings, specifications, contract documents, and other documentations. (b) Single Family Housing. (1) Site development design requirements. (2) [Reserved] (c) Multiple Family Housing. § 1924.106 Location. (a) General. (1) The site must be located in an eligible area as defined in the program regulations under which the development is being funded or approved. (2) The site must comply with the environmental review requirements in accordance with 7 CFR part 1970. (b) Single Family Housing. (c) Multiple Family Housing. [60 FR 24543, May 9, 1995, as amended at 81 FR 11030, Mar. 2, 2016] § 1924.107 Utilities. All development under this subpart must have adequate, economic, safe, energy efficient, dependable utilities with sufficient easements for installation and maintenance. (a) Water and wastewater disposal systems Single Family Housing. (2) Multiple Family Housing. (i) Sites which are not presently served by a central system, but are scheduled for tie-in to the central system within 2 years, should have all lines installed during the initial construction. Such sites must have an approved interim water supply or wastewater disposal system installed capable of satisfactory service until the scheduled tie-in occurs. (ii) In addition to written assurance of compliance with state and local requirements, there must be assurance of continuous service at reasonable rates for central water and wastewater disposal systems. Public ownership is preferred whenever possible. In cases where interim facilities are installed pending extension or construction of permanent public services, the developer must assume responsibility for the operation and maintenance of the interim facility or establish an entity for its operation and maintenance which is acceptable to the local governing body. If a system is not or will not be publicly owned and operated, it must comply with one of the following: (A) Be an organization that meets the ownership and operating requirements for a water or wastewater disposal system that RHS could finance under 7 CFR part 1942, subpart A or be dedicated to and accepted by such an organization. (B) Be an organization or individual that meets other acceptable methods of ownership and operation as outlined in HUD Handbook 4075.12, “Ownership and Organization of Central Water and Sewerage Systems.” RHS should be assured that the organization has the right, in its sole discretion, to enforce the obligation of the operator of the water and sewerage systems to provide satisfactory continuous service at reasonable rates. (C) Be adequately controlled as to rates and services by a public body (unit of Government or public services commission). (iii) Multiple family developments of more than 25 units with individual system must have national office concurrence. (A) [Reserved] (B) Supporting information for the proposed individual water systems, covering the following points: ( 1 ( 2 (C) Supporting information for individual wastewater disposal systems with subsurface discharge provided by a soil scientist, geologist, soils engineer, or other person recognized by the local regulatory authority. This data must include the following: ( 1 ( 2 ( 3 ( 4 ( 5 ( 6 (D) Supporting information for individual wastewater disposal systems with surface discharge covering the following points: ( 1 ( 2 ( 3 (b) Electric service. (c) Gas service. (d) Other utilities. § 1924.108 Grading and drainage. (a) General. (b) Cuts and fills. (c) Slope protection. (d) Storm water systems. §§ 1924.109-1924.114 [Reserved] § 1924.115 Single Family Housing site evaluation. (a) Site review. (b) Site access. (1) A hard surfaced or all weather road which is developed in full compliance with public body requirements, is dedicated for public use, and is being maintained by a public body or a home owners association that has demonstrated its ability or can clearly demonstrate its ability to maintain the street; or (2) An all weather extended driveway which can serve no more than two sites connecting to a hard surface or all weather street or road that meets the requirements of paragraph (b)(1); or (3) A hard surfaced street in a condominium or townhouse complex which: (i) Is owned in common by the members or a member association and is maintained by a member association that has demonstrated its ability or can clearly demonstrate its ability to maintain the street; and (ii) Connects to a publicly owned and dedicated street or road. (c) Exceptions to street requirements. (1) The applicant is a builder for a conditional commitment (a loan will not be approved until the site meets the conditions in paragraph (b) of this section), or the builder posts an irrevocable performance and payment bond (or similar acceptable assurance) that assures the site approval official that the site will be developed to meet the conditions in paragraph (b) of this section; or (2) The site is recommended by the site approval official and approved by the state director. A request for state director approval must justify that it is in the best interest of both the government and the applicant to approve the site. (d) Site layout. (2) Sites shall meet all requirements of state and local entities and RHS. (e) Covenants, conditions and restrictions. (1) CC&Rs shall be recorded in the public land records and specifically referenced in each deed. (2) The intent of the CC&Rs is to assure the developers that the purchasers will use the land in conformance with the planned objectives for the community. In addition, the CC&Rs should assure the purchasers that the land covered by the CC&Rs will be used as planned and that other purchasers will use and maintain the land as planned to prevent changes in the character of the neighborhood that would adversely impact values or create a nuisance. §§ 1924.116-1924.118 [Reserved] § 1924.119 Site Loans. Subdivisions approved under subpart G of part 1822 (RD Instruction 444.8) or exhibit F of subpart I of part 1944, will meet the general requirements of this subpart to insure lots in the subdivision will meet the requirements of § 1924.115. §§ 1924.120-1924.121 [Reserved] § 1924.122 Exception authority. The Administrator of RHS may in individual cases, make an exception to any requirement or provision of this subpart or address any omission of this subpart which is not inconsistent with the authorizing statute or other applicable law if the Administrator determines that application of the requirement or provision would adversely affect the Government's interest. The Administrator will exercise this authority upon the written request of the state director or the appropriate program assistant administrator. Requests for exceptions must be supported with documentation to explain the adverse effect on the Government, proposed alternative courses of action, and show how the adverse effect will be eliminated or minimized if the exception is granted. §§ 1924.123-1924.149 [Reserved] § 1924.150 OMB Control Number. The reporting requirements contained in this subpart have been approved by the Office of Management and Budget (OMB) and have been assigned OMB control number 0575-0164. Public reporting burden for this collection of information is estimated to vary from 5 minutes to 10 minutes per response, with an average of .13 hours per response, including time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the Department of Agriculture, Clearance Officer, OIRM, Ag Box 7630, Washington, DC 20250; and to the Office of Management and Budget, Paperwork Reduction Project (OMB #0575-0164), Washington, DC 20503. Exhibit A to Subpart C of Part 1924 [Reserved] Exhibit B to Subpart C of Part 1924—Site Development Design Requirements This exhibit prescribes site development requirements to be used in developing residential sites in all housing programs. These requirements cover only those areas which involve health and safety concerns. They are not intended to cover all aspects of site development. Applicants and developers are expected to follow local practice, as a minimum, in all areas of site development not addressed in this exhibit. When State, local, or other requirements are applicable in addition to FmHA or its successor agency under Public Law 103-354's requirements, the most stringent requirement shall apply. Proper integration of the natural features of a site with the manmade improvements is one of the most critical aspects of residential development. Poor site planning in large scale subdivisions, rental projects and individual sites, has resulted in a loss of valuable private and public natural resources and caused economic burdens and conditions unsuitable for healthy and pleasant living. Proper site design can preserve desirable natural features of the site, minimize expenses for streets and utilities, and provide a safe and pleasant living environment. Table of Contents I. Streets A. Types 1. Collector Streets 2. Local Streets B. Design Features 1. Emergency Access 2. Cul-de-sacs 3. Intersection Angle 4. Intersection Sight Distance C. Street Geometry 1. Definitions 2. Design Requirements D. Construction II. Walks and Steps A. Walks B. Exterior Steps Not Contiguous to Dwelling or Building 1. Flight 2. Risers and Treads 3. Landings 4. Handrails III. Grading A. Compaction B. Gradients IV. Drainage A. General 1. Collection and Disposal 2. Concentrated Flow B. Drainage Design and Flood Hazard Exposure 1. Storm Frequences 2. Street Drainage 3. Foundation Drainage C. Primary Storm Sewer 1. Pipe Size 2. Minimum Gradient 3. Easements D. Drainage Swals and Gutters 1. Design 2. Easements E. Downspouts 1. Outfall 2. Piped Drainage F. Storm Inlets and Catch Basins 1. Openings 2. Access G. Drywells V. Water Supply Systems A. Individual Water Systems 1. General 2. Well Location 3. Well Construction 4. Pumps and Equipment 5. Storage Tanks B. Community Water Systems 1. Definition 2. Design VI. Wastewater Disposal Systems A. Individual Wastewater Disposal Systems 1. General 2. Percolation Tests 3. Subsurface Absorption Systems B. Community Wastewater Disposal Systems 1. Definition 2. Design I. Streets A. Types Collector streets. 2. Local streets. B. Design Features Emergency Access. 2. Cul-de-sacs. 3. Intersection Angle. 4. Intersection Sight Distance. C. Street Geometry Definitions. a. Terrain Classifications. (1) Ordinary—Slope less than 8%. (2) Rolling—Slope range of 8% to 15%. (3) Hilly—Slope greater than 15%. b. Development Density (1) Low—Less than 2 lots per acre. (2) Medium—2 to 6.0 lots per acre. (3) High-More than six lots per acre. 2. Design Requirements. Table 1—Pavement Widths (feet) Street type On-street parallel parking Development density Low Medium High Collector Prohibited 26 32 36 Collector No Restrictions 36 36 40 Local Prohibited 18 18 20 Local Partial, One Side 1 18 20 26 Local Partial, One Side 1 22 26 32 Local Total, One Side 2 22 26 26 Local Total, Both Sides 2 26 32 36 ( 1 ( 2 Table 2—Street Design (feet) Terrain Ordinary Rolling Hilly (1) Collector street: (a) Minimum centerline radius of curvature 300 225 150 (b) Minimum sight distance 250 200 150 (c) Minimum right-of-way width 60 60 60 (2) Local Street: (a) Minimum centerline radius of curvature 200 150 100 (b) Minimum sight distance 200 150 100 (c) Minimum right-of-way width 1 50 50 50 ( 1 D. Construction. II. Walks and Steps A. Walks. B. Exterior Steps Not Contiguous to Dwelling or Building Flight. b. Steps shall be set back from an intersecting walk or drive a minimum of 1 foot at a retaining wall and 2 feet at slopes. 2. Risers and Treads. b. Treads shall be a minimum of 12 inches and uniform throughout the flight. c. Treads shall have a slip resistant surface. d. Treads shall be pitched appropriately to ensure drainage. 3. Landings. b. A change in direction in a flight of stairs shall be accomplished only at a landing or by a winder which has a tread width at a point 18 inches from the converging end, equal to the full straight stair tread width. 4. Handrails. III. Grading A. Compaction B. Gradients. Table 3—Access and Parking Gradients 1 [In percent] Minimum Maximum Center line Crown or cross slope Center line Crown or cross slope Streets 0.5 1.0 14.0 5.0 Street Intersections 0.5 1.0 2 5.0 Driveways ( 3 .05 1.0 14.0 5.0 Sidewalks ( 4 Concrete 0.5 Bituminous 1.0 Building Entrances & Short Walks 1.0 12.0 5.0 Main Walks 0.5 10.0 5.0 Adjoining Steps 2.0 Landings 1.0 Stepped Ramp Treads 1.0 2.0 5.0 Parking 0.5 5.0 5.0 1 1 16 1 8 1 4 5 8 1 4 1 2 5 8 2 3 4 Table 4—Slope Gradients 1 [In percent] Minimum Maximum Slope Away From Foundations: Pervious Surfaces 2 3 Impervious Surfaces 2 21.0 Pervious Surfaces: Ground Frost Area 2.0 Non-Ground Frost Areas 4 Impervious Surfaces 0.5 Slopes to be maintained by Machine 3 1 2 3 4 IV. Drainage A. General Collection and Disposal. 2. Concentrated Flow. B. Drainage Design and Flood Hazard Exposure Storm Frequency. 2. Street Drainage. 3. Foundation Drainage. C. Primary Storm Sewer Pipe Size. 2. Minimum Gradient. 3. Easements. D. Drainage Swals and Gutters Design. 2. Easements. E. Downspouts Outfall. 2. Piped Drainage. F. Storm Inlets and Catch Basins Openings. 2. Access. G. Drywells V. Water Supply Systems A. Individual Water Systems General. b. The system for an individual household should be capable of delivering a sustained flow of 5 gpm. A system supplying water to multiple household shall be designed by a Professional Engineer and have sufficient capacity to serve estimated demand. A test of at least 4 hours duration shall be conducted to determine the yield and maximum drawdown for all wells developed as part of an individual water system. This test may be waived by the State Office based on the hydrologic and geologic conditions in the area. c. Water that requires continual or repetitive treatment to be safe bacterially is not acceptable. d. After installation, the system should be disinfected in accordance with the recommendations of the health authority. In the absence of a health authority, system cleaning and disinfection should conform with the current EPA Manual of Individual Water Supply Systems. e. Any method for individual water supply contained herein which is not permitted by the local health authority having jurisdiction shall not be used. 2. Well Location b. Water which comes from soil formation which may be polluted or contaminated or is fissured or creviced or which is less than 20 feet below the natural ground surface (subject to the requirements of the local health authority) is not acceptable. c. Individual water supply systems are not acceptable for individual lots in areas where chemical soil poisoning is practiced if the overburden of soil between the ground surface and the water bearing strata is coarse-grained sand, gravel, or porous rock, or is creviced in a manner which will permit the recharge water to carry the toxicants into the zone of saturation. d. Table 5 shall be used in establishing the minimum acceptable distances between wells and sources of pollution located on either the same or adjoining lots. These distances may be increased by either the health authority having jurisdiction or the FmHA or its successor agency under Public Law 103-354 State Director. Table 5—Distance From Source of Pollution Source of pollution Minimum horizontal distance (feet) Property Line 10 Septic Tank 50 Absorption field 1 Seepage pit 1 Absorption Bed 1 Sewer Lines w/Permanent Watertight Joints 10 Other Sewer Lines 50 Chemically Poisoned Soil 1 Dry Well 50 Other ( 2 Notes: 1 2 3. Well Construction b. All drilled wells shall be provided with a sound, durable and watertight casing capable of sustaining the loads imposed. The casing shall extend from a point several feet below the water level at drawdown or from an impervious strata above the water level, to 12 inches above either the ground surface or the pump room floor. The casing shall be sealed at the upper opening. c. Bored wells shall be lined with concrete, vitrified clay, or equivalent materials. d. The space between the casing or liner and the wall of the well hole shall be sealed with cement grout. e. The well casing shall not be used to convey water except under positive pressure. A separate drop pipe shall be used for suction line. f. When sand or silt is encountered in the water-bearing formation, the well shall either be gravel packed, or a removable strainer or screen shall be installed. g. The surface of the ground above and around the well shall be graded to drain surface water away from the well. h. Openings in the casing, cap, or concrete cover for the entrance of pipes, pump or manholes, shall be made watertight. i. If a breather is provided, it shall extend above the highest level to which surface water may rise. The breather shall be watertight, and the open end shall be screened and positioned to prevent entry of dust, insects and foregin objects. 4. Pumps and Equipment b. Pumps and equipment shall be mounted to be free of objectionable noises, vibrations, flooding, pollution, and freezing. c. Suction lines shall terminate below maximum drawdown of the water level in the well. d. Horizontal segments of suction line shall be placed below the frost line in a sealed casing pipe or in at least 4 inches of concrete. The distance from suction line to sources of pollution shall be not less than shown in table 5. 5. Storage Tanks b. Tanks shall be equipped with a clean-out plug at the lowest point, and if pressurized, a suitable pressure relief valve. c. When additional storage is necessary because the well yield will not meet the system peak demands, all nonpressurized intermediate tanks shall be designed and installed in a manner that will prevent the pollution or degradation of the water supply. B. Community Water Systems Definition. 2. Design. VI. Wastewater Disposal Systems Each dwelling shall be provided with a water-carried system adequate to dispose of domestic wastes in a manner which will not create a nuisance, contaminate any existing or prospective water source or water supply, or in any way endanger the public health. A. Individual Wastewater Disposal Systems General. b. When service from an acceptable public or community system is not available or feasible, and ground water and soil conditions are acceptable, an individual system may be used. c. Each individual wastewater disposal system shall consist of a house sewer, a pretreatment unit (e.g., septic tank, individual package treatment plant), and acceptable absorption system (subsurface absorption field, seepage pit(s), or subsurface absorption bed). The system shall be designed to receive all sanitary sewage (bathrooms, kitchen and laundry) from the dwelling, but not footing or roof drainage. It shall be designed so that gases generated anywhere in the system can easily flow back to the building sewer stack. 2. Percolation Tests b. In uniform soils one percolation test shall be made within each area proposed for an absorption system. If significant soil variations are encountered or expected, additional tests shall be made for each variation. c. Percolation tests shall be conducted in accordance with good practice. Guidance for performing these tests is included in the EPA design manual, “Onsite Wastewater Treatment and Disposal Systems.” 3. Subsurface Absorption System b. Soils with percolation rates less than 1 minute per inch may be used if the soil is replaced with a layer of loamy or fine sand at least 2 feet thick. (Refer to the EPA Design Manual, “Onsite Wastewater Treatment and Disposal System”.) c. Soils with percolation rates greater than 60 minutes per inch are not acceptable for subsurface wastewater disposal systems. B. Community Wastewater Disposal Systems Definition. 2. Design. [52 FR 19284, May 22, 1987] Exhibit C to Subpart C of Part 1924—Checklist of Visual Exhibits and Documentation for RRH, RCH, and LH Proposals U.S. Department of Agriculture Farmers Home Administration or its successor agency under Public Law 103-354 This exhibit lists visual exhibits and documentation necessary for FmHA or its successor agency under Public Law 103-354 to properly evaluate proposed development. Intermediate consultation by the applicant, builder-developer and others hereafter referred to as the sponsor with the FmHA or its successor agency under Public Law 103-354 District or State Offices should be as frequent as necessary to reduce chances of misunderstandings and limit the amount of non-productive time and expense for all parties concerned. I. Preapplication Submission Documents: A. Environmental review requirements. B. Location Map. C. Property Survey Map. D. Soils Map and Report. E. Market survey. F. Request for Exceptions. G. Other. 1. Schematic design drawings showing the proposed plot plan, typical unit plans, and elevations. If available, the proposed preliminary drawings and specifications may be submitted. This would be of assistance if it is determined that the loan must receive National Office authorization. 2. Type of construction. 3. The total number of living units and the number of each type of living unit proposed. 4. Type of utilities such as water, sewer, gas, and electricity and whether each is public, community, or individually owned. II. Application Submission Documents: A. Property Survey. B. Topographic Map. C. Preliminary Site Plan. D. Preliminary Dwelling Drawings and Specifications. E. Statement of Planning and Zoning Compliance. F. Technical Service Contracts. G. Utility Approvals. 1. Verification of adequate capacity and approval to tie-in with local existing water, wastewater disposal, electric, telephone, and other utility systems, as appropriate. 2. Tentative approval of local or State health authority for individual water and/or wastewater disposal systems when it is clear that central systems are unfeasible at this time. Use § 1924.108(a)(5) of this subpart when preparing information required. H. Facility Acceptance. I. Preliminary Specifications. J. Incremental Slopes Plan. K. Preliminary Grading Plan. L. Other. 1. A detailed trade-item cost breakdown of the project for such items as land and right-of-way, building construction, equipment, utility connections, architectural/engineering and legal fees, and both on- and off-site improvements. The cost breakdown also should show separately the items not included in the loan, such as furnishings and equipment. This trade-item cost breakdown should be updated just prior to loan approval. 2. Information on the method of construction, on the proposed contractor if a construction contract is to be negotiated and on the architectural, engineering, and legal services to be provided. 3. For all projects containing over four units the applicant will submit an Affirmative Fair Housing Marketing Plan for approval by FmHA or its successor agency under Public Law 103-354 in accordance with § 1901.203 of subpart E to part 1901 of this chapter. The Affirmative Fair Housing Marketing Plan must be prepared in a complete, meaningful, responsive and detailed manner. 4. A description and justification of any related facilities (including but not limited to workshops, community buildings, recreation center, central cooking and dining facilities, or other similar facilities to meet essential needs) to be financed wholly or in part with loan funds. III. Technical Documents Necessary for the Obligation of Funds. [52 FR 19284, May 22, 1987, as amended at 56 FR 2202, Jan. 22, 1991; 81 FR 11030, Mar. 2, 2016] Subparts D-E [Reserved] Subpart F—Complaints and Compensation for Construction Defects Source: 56 FR 40241, Aug. 14, 1991, unless otherwise noted. § 1924.251 Purpose. This subpart contains policies and procedures for receiving and resolving complaints concerning the construction of dwellings and construction, installation and set-up of manufactured homes (herein called “units”), financed by the Rural Development, and for compensating borrowers for structural defects under section 509(c) of the Housing Act of 1949, as amended. Provisions of this subpart do not apply to dwellings financed with guaranteed section 502 loans. § 1924.252 Policy. Rural Development is responsible for receiving and resolving all complaints concerning the construction of dwellings and the construction, installation and set-up of units financed by Rural Development. Rural Development must determine whether defects are structural or non-structural. If the defect is structural and is covered by the builder's/dealer-contractor's (the “contractor”) warranty, the contractor is expected to correct the defect. If the contractor cannot or will not correct the defect, the costs of correcting the defect may be paid by the Government, or the borrower may be compensated for correcting the defect, under the provisions of this subpart. If the defect is non-structural but is covered under the provisions of the contractor's warranty or independent home warranty, the contractor is still expected to correct the defect. Rural Development will assist the borrower in obtaining assistance through the independent home warranty company's and/or manufacturer's complaint resolution process. However, if the contractor cannot or will not correct a non-structural defect covered under the provisions of the contractor's warranty, the Government will not pay the costs for correcting the defect, nor will the borrower be compensated for doing so. § 1924.253 Definitions. As used in this subpart, the following definitions apply: (a) Newly constructed dwelling. (1) Is financed with a section 502 insured loan; (2) Was constructed substantially or wholly under the contract method, or under a conditional commitment, or, as to only work performed by a contractor or covered by a manufacturer's warranty, under the mutual self-help program; (3) Was not more than one year old and not previously occupied as a residence at the time financial assistance was granted unless Rural Development has extended the conditional commitment issued on a newly constructed dwelling in accordance with 7 CFR part 3550; and (4) Had the required construction inspections performed by Rural Development, the Department of Housing and Urban Development (HUD), or the Veterans Administration (VA). (b) Newly constructed manufactured home (unit). (1) Is financed with a section 502 insured loan; (2) Was not more than one year old and not previously occupied as a residence at the time financial assistance was granted; and (3) Is built to the Federal Manufactured Home Construction and Safety Standards (FMHCSS) and is certified by an affixed label as shown in exhibit J of subpart A of part 1924 of this chapter. (c) Non-structural defect. (1) Cracks attributed to normal curing or settlement. (2) Cosmetic defects in cabinets, woodwork, floorcovering, wallcovering, ornamental trim, etc. (3) Improper or incomplete seeding or sodding of yard, or failure of trees, shrubs, grass and other landscaping items to thrive. (4) Improper grading of yard, unless the grade is causing damage which may lead to a structural defect. (d) Structural defect. (1) Structural failures which directly and significantly affect the basic integrity of the dwelling or unit such as in the foundation, footings, basement walls, slabs, floors, framing, walls, ceiling, or roof. (2) Major deficiencies in the utility components of the dwelling or unit or site such as faulty wiring, or failure of sewage disposal or water supply systems located on the property securing the loan caused by faulty materials or improper installation. (3) Serious defects in or improper installation of heating systems or central air conditioning. (4) Defects in or improper installation of safety and security devices, such as windows, external doors, locks, smoke detectors, railings, etc., as well as failure to provide or properly install devices to aid occupancy of dwellings by handicapped individuals, where required. (5) Defects in or improper installation of protective materials, such as insulation, siding, roofing material, exterior paint, etc. [56 FR 40241, Aug. 14, 1991, as amended at 67 FR 78327, Dec. 24, 2002] §§ 1924.254-1924.257 [Reserved] § 1924.258 Notification of borrowers. Rural Development will notify by letter all borrowers who receive Section 502 RH financial assistance for a newly constructed dwelling or unit of the provisions of this subpart. Subsequent owners of eligible dwellings will also be notified in accordance with this section. Borrowers will be notified within 30 days after the loan is closed, or within 30 days after final inspection, whichever is later. This notification will contain information concerning time frames for filing claims under this subpart. Rural Development will also notify and advise borrowers of the construction defects procedure at any time construction defects are apparent within the statutory time frame and favorable results cannot be obtained from the contractor. This notification will be documented in the borrower's case file. § 1924.259 Handling dwelling construction complaints. This section describes the procedure for handling construction defect complaints. (a) Each borrower who complains about construction defects will be requested to make a written complaint using a Rural Development approved format. All known defects will be listed. An oral complaint may be accepted if making a written complaint will impose a hardship on the borrower. If an oral complaint is made, Rural Development will notify the contractor on behalf of the borrower. (b) The borrower will be informed that if, after 30 calendar days, the defects have not been corrected or other satisfactory arrangements made by the contractor, the borrower should notify Rural Development using a Rural Development approved format. (c) Rural Development will advise the contractor in writing of the borrower's complaint, the time and date of planned inspection by Rural Development personnel, and request that the contractor accompany the inspector and borrower on a joint inspection of the property in an attempt to resolve the complaint. (d) If, prior to the planned inspection, the contractor informs Rural Development that the alleged defect(s) has been or will be corrected within 30 calendar days, Rural Development will notify the borrower. (e) If the case is not resolved as outlined in paragraph (d) of this section, Rural Development will: (1) [Reserved] (2) Notify the borrower, contractor and manufacturer, if applicable, in writing of the findings and who has been determined responsible for correcting the defect(s). (i) If the defects are determined to be covered under the contractor's warranty, Rural Development will advise the contractor that the repairs must be completed within 30 calendar days or other time period agreed to by the borrower, the contractor, and Rural Development. (ii) Rural Development will further advise the contractor and/or manufacturer that if the defect(s) are not corrected, the Government will consider compensating the borrower for the costs of correcting the defect(s). In such a case, the contractor and/or manufacturer may be liable for costs paid by the Government and may be subject to suspension and/or debarment pursuant to subpart M of part 1940 of this chapter (available in any Rural Development office). Even if the manufacturer is determined to be solely responsible for the defect, the contractor will still be held liable for correction of the defect. (3) Should a contractor refuse to correct a defect after being officially requested in writing to do so, Rural Development will promptly institute formal suspension and debarment proceedings against the contractor (as a company and as individual(s)) in accordance with subpart M of part 1940 of this chapter (available in any Rural Development office). The contractor's failure to reply to official correspondence or inability to correct a defect constitutes noncompliance. (4) If the contractor is willing to correct legitimate defects but the borrower refuses to permit this, Rural Development will document the facts in the borrower's case file. If the borrower chooses to file a claim for compensation for these defects, the circumstances of the borrower's refusal will be reviewed and may be sufficient grounds for disapproval of the claim. (f)-(h) [Reserved] § 1924.260 Handling manufactured housing (unit) construction complaints. When a borrower who has purchased a manufactured home (or “unit”) complains about construction defects, the borrower will be instructed to first contact the dealer-contractor from whom the unit was purchased. Rural Development will assist the borrower in obtaining assistance through the dealer-contractor's and/or HUD's complaint resolution process. If the dealer-contractor cannot resolve the complaint, the borrower should contact the appropriate State Administrative Agency (SAA) or HUD. If the complaint resolution process does not result in the correction of the defect, the borrower's complaint will be handled in accordance with § 1924.259 of this subpart. § 1924.261 Handling complaints involving dwellings covered by an independent or insured home warranty plan. Borrowers with complaints about dwellings covered by an independent or insured home warranty plan will be instructed to first contact the warranty company and follow the complaint resolution process for that company, with the assistance of Rural Development, if needed. If the complaint is not resolved in this manner, it will be handled under § 1924.259 of this subpart. § 1924.262 Handling complaints involving dwellings constructed by the self-help method. When a borrower whose dwelling was constructed by the self-help method complains about construction defects, Rural Development will determine whether the defect is the result of work performed by a contractor or work performed by the borrower under the guidance of the self-help group. Defects which are determined to be the responsibility of a contractor will be handled in accordance with § 1924.259 of this subpart. Defects determined to be the result of work performed by the borrower are not eligible for compensation under this subpart. §§ 1924.263-1924.264 [Reserved] § 1924.265 Eligibility for compensation for construction defects. (a) To be eligible for assistance under this subpart, the following criteria must be met: (1) The approval official, in consultation with the State Architect/Engineer and/or Construction Inspector, must determine that: (i) The construction is defective in workmanship, material or equipment, or (ii) The dwelling or unit has not been built in substantial compliance with the approved drawings and specifications, or (iii) The dwelling or unit does not comply with the Rural Development construction standards in effect at the time the loan was approved or the conditional commitment was issued, or (iv) The property does not meet code requirements. (2) The claim must be for one or more of the following: (i) To pay for repairs; (ii) To compensate the owner for repairs; (iii) To pay emergency living or other expenses resulting from the defect; or (iv) To acquire title to property. (3) The dwelling or unit must be newly constructed as defined in § 1924.253 of this subpart and financed with an insured Section 502 RH loan. (4) The claim seeking compensation from Rural Development must be filed with Rural Development within 18 months after the date financial assistance is granted. Defects for which claims are filed beyond the 18-month period must have been documented by Rural Development in the borrower's case file or on the form designated by Rural Development (available in any Rural Development office), prior to expiration of the 18-month period. For loans made to construct a new dwelling or erect a new manufactured housing unit, financial assistance is granted on the date of final construction inspection and acceptance by the borrower and Rural Development. Claims must be submitted by completing the designated form (available in any Rural Development office). (5) Any obligation of the contractor to correct the defect(s) under a contractor's warranty must have expired, or the contractor is responsible for making corrections under the contractor's warranty but is unable or unwilling to do so. (b) Subsequent owners of eligible dwellings or units who are also Section 502 borrowers may be eligible to receive compensation for construction defects. These owners will be notified in accordance with § 1924.258 of this subpart. However, the claim for compensation must be filed in accordance with paragraph (a)(4) of this section within the 18-month period established for the original rural housing (RH) borrower. § 1924.266 Purposes for which claims may be approved. (a) Eligible purposes. (1) Pay, or reimburse the borrower for costs already paid, to repair major structural defects which are completed in accordance with plans and specifications approved by Rural Development. Repairs must be made by a reputable licensed contractor and a warranty covering the repairs will be issued by the contractor when the repairs are completed, as prescribed in subpart A of this part. Payment will be based on actual cost of the development and the borrower must provide evidence to reasonably establish the development cost. Workmanship and materials used in repairs must be consistent with the level of quality specified in the original dwelling or unit specifications and/or comparable to the items being replaced. Payment may be made: (i) To cover damages which are a direct result of the defect to permanent enhancements made, such as landscaping, completion of unfinished living spaces, etc., of the dwelling or unit, installation or set-up of the unit, or related facilities, and (ii) For costs approved by Rural Development for professional reports by engineers, architects or others needed to determine cause of or means to repair the defect. (2) Reimburse the borrower for funds expended for emergency repairs. Emergency repairs are those repairs necessary to preserve the integrity of the structure, to prevent damage or further damage to personal property or fixtures in the dwelling or unit and related facilities, or to prevent or eliminate immediate health hazards. Receipts or other evidence of borrower's expenditures must be provided. (3) Acquire title to the property by the Government and, when appropriate, compensate the claimant for any loss of borrower contribution at the time the loan was closed. Conveyance of properties under this section will be handled in accordance with 7 CFR part 3550. (i) Before Rural Development accepts a conveyance, the borrower must attempt to sell the dwelling or unit in accordance with 7 CFR part 3550, if the dwelling or unit is considered decent, safe and sanitary as prescribed in 7 CFR part 3550. If the property is sold, Rural Development will: (A) Pay the borrower's relocation expenses, including temporary living expenses as prescribed in paragraph (a)(4) of this section, until another suitable property can be located; (B) Pay related sales expenses, as prescribed in 7 CFR part 3550, if the property is sold for less than the debt against it; (C) Release the borrower from personal liability for the remaining Rural Development debt; and (D) Process an application for a new RH loan if the borrower so desires and is still eligible for Rural Development assistance. (ii) If the dwelling or unit is not considered decent, safe and sanitary as prescribed in 7 CFR part 3550, Rural Development should accept a voluntary conveyance of the property under the provisions of 7 CFR part 3550. Compensation for properties taken into inventory under this paragraph may not exceed the difference between the present market value of the security as established by the appraisal when the loan was made and the amount of the Rural Development loan and any prior liens. (iii) A borrower contribution which may be compensated for under this paragraph may be such things as: (A) A borrower's land or cash contribution, (B) Development work done by the borrower under the self-help program or borrower method of construction, the cost of which was not included in the loan funds, (C) Attorney fees, abstract costs or title insurance costs actually paid by the claimant in connection with closing the loan. (4) Pay or reimburse the borrower for temporary living expenses, miscellaneous expenses, storage of household goods and moving expenses incurred as a result of the defect. (i) Payment under this paragraph may be made under either of the following circumstances: (A) The property is acquired by the Government in accordance with 7 CFR part 3550 and Rural Development determines that the dwelling is not habitable and the severity of the defect(s) prevents the property from being repaired and made suitable as a permanent residence for the borrower. (B) The property is not acquired by the Government but Rural Development determines that the dwelling is not habitable or must be vacated in order to repair the defects. (ii) Claims for compensation under paragraph (a)(4) of this section are limited as follows: (A) Compensation may be granted for temporary living expenses for not more than 45 calendar days per claim unless a longer period is authorized by Rural Development. Compensation will be paid for actual cost to the claimant not to exceed the Government per diem rate for the area where the borrower's dwelling or unit is located. Reimbursement may be claimed for expenses such as food, lodging, laundering, etc., which would not have been incurred had the claimant remained in the house. (B) Compensation may be granted for actual miscellaneous expenses not to exceed $500 to cover such items as utility connect and disconnect fees. (C) Compensation may be granted for moving and storage expenses not to exceed $5,000 unless authorized by Rural Development and not to exceed the actual cost of moving the claimant household with personal belongings a distance of not more than 50 miles from the original residence. Compensation for storage expenses may not exceed that amount paid to store household furnishings for 45 days. (D) A strict accounting of the use of such funds must be maintained by the borrower and will be verified by Rural Development. (5) Compensate the claimant for reasonable interest paid on loans obtained for the sole purpose of correcting structural defects or other approved purposes under this section. (b) Ineligible purposes. (1) Completion of a dwelling or unit or installation of materials/items required under the construction contract and/or specifications. (2) Defective items which were not completed under the contract method or under the conditional commitment and supported by a builder's warranty. Work performed under the borrower method or self-help program without a warranty by a responsible party is not eligible for compensation. (3) Damage caused by defective design, workmanship, or material in making enhancements to or remodeling the dwelling or unit or related facilities which were not financed or approved by Rural Development. (4) The loss of past, present or future wages or salary directly or indirectly resulting from the defect. (5) Treatment for physical or psychological damages including medical and dental claims. (6) Death benefits or funeral expenses. (7) Damages encountered as a result of war, civil disorder, flood, tornado, lightning, earthquake or acts of nature which the structure was not designed to withstand. (8) Damages resulting from the homeowner's negligence or failure to properly maintain the property. (9) Damage to personal property. [56 FR 40241, Aug. 14, 1991, as amended at 67 FR 78327, Dec. 24, 2002] §§ 1924.267-1924.270 [Reserved] § 1924.271 Processing applications. An application for compensation for construction defects shall be submitted by the claimant to Rural Development on the designated form. The application shall be completed in its entirety. All structural defects and claims for which compensation is sought will be listed. Borrowers will be told not to incur any expenses for repairs or temporary living expenses, except for emergency situations, until funds have been allocated and the request has been approved under § 1924.273 of this subpart. § 1924.272 [Reserved] § 1924.273 Approval or disapproval. (a) Claimants will be notified in writing of the decision on the claim within 60 days of the date the designated form is signed by the borrower. If the claim or any part of the claim is denied at any level, the claimant will be informed in writing of the reason(s) for the denial and advised of appeal rights in accordance with 7 CFR part 11. (b) [Reserved] [56 FR 40241, Aug. 14, 1991, as amended at 67 FR 78327, Dec. 24, 2002] § 1924.274 Final inspection. Except for emergency repairs, all repair work must be performed in accordance with subpart A of this part. In all cases, Rural Development will make a final inspection of the repair work performed before final payment is made for the work. § 1924.275 [Reserved] § 1924.276 Action against contractor. If Rural Development pays for correction of construction defects which are the responsibility of the contractor, debarment proceedings will be initiated against the contractor in accordance with subpart M of part 1940 of this chapter (available in any Rural Development office), even if the contractor has gone out of business, declared bankruptcy, cannot be located, etc. The debarment will be pursued in both the contractor's company name and the principal parties as individuals, and any successor entities, if known. If the manufacturer of the defective product is determined to be solely responsible, no action will be taken against the contractor. In such a case, debarment will be initiated against the manufacturer. An assignment of the borrower's claim against the contractor or other party will be obtained if it appears to the approval officials, with any necessary advice from the Office of the General Counsel, that recovery is reasonably possible. §§ 1924.277-1924.299 [Reserved] § 1924.300 OMB control number. The reporting and recordkeeping requirements contained in this regulation have been approved by the Office of Management and Budget (OMB) and have been assigned OMB control number 0575-0082. Public reporting burden for this collection of information is estimated to vary from 15 minutes to 2 hours per response, with an average of .28 hours per response including time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Agriculture, Clearance Officer, OIRM, room 404-W, Washington, DC 20250; and to the Office of Management and Budget, Paperwork Reduction Project (OMB #575-0082), Washington, DC 20503.